QP-ENG-PRC-008
TABLE OF CONTENTS
Page No.
1.0 OBJECTIVE .............................................................................................................. 4
2.0 SCOPE ..................................................................................................................... 4
3.0 TERMINOLOGY ....................................................................................................... 4
3.1 DEFINITIONS ........................................................................................................ 4
3.2 ABBREVIATIONS.................................................................................................. 5
4.0 PROCESS .................................................... ERROR! BOOKMARK NOT DEFINED.
4.1 IDENTIFY SAT REQUIREMENTS ........................................................................ 6
4.2 INCLUSION OF SAT(S) REQUIREMENTS IN EPIC SCOPE OF WORK (SOW) . 6
4.3 PREPARE SAT(S) STRATEGY ............................................................................ 6
4.4 PREPARE PROJECT SPECIFIC SAT PROCEDURES DURING IHC .................. 6
4.5 PRE-REQUISITES OF AN SAT ............................................................................ 7
4.6 PERFORM SAT(S) ................................................................................................ 8
4.6.1 Equipment and System SAT(s) ........................................................................ 8
4.6.2 Plant SAT ......................................................................................................... 8
4.7 INFRASTRUCTURE AND CIVIL PROJECTS ....................................................... 9
5.0 REFERENCES........................................................................................................ 10
6.0 RESPONSIBILITIES ............................................................................................... 11
6.1 PROJECT TEAM ................................................................................................. 11
6.2 COMMISSIONING TEAM .................................................................................... 11
6.3 ASSET HOLDER ................................................................................................. 11
7.0 APPENDICES ......................................................................................................... 12
7.1 Appendix - A - FLOWCHART .............................................................................. 12
REVISION HISTORY LOG ................................................................................................ 13
QP-ENG-PRC-008
FOREWORD
This document has been developed by Projects, Engineering and Procurement Services
Directorate (VP) as a result of “Tatweer – QP Project Management Transformation Project” and
has been endorsed by QP Management for use as QP Procedure for Site Acceptance Test (SAT).
All comments, recommendations, clarifications about this document shall be forwarded to the
Asst. Manager, Process, Systems & Admin, (PSS) as the responsible entity for Management
Systems within VP Directorate, email at injaz@qp.com.qa.
QP-ENG-PRC-008
1.0 OBJECTIVE
This corporate procedure is a supplement to Commissioning and Handover Procedure
QP-ENG-PRC-005 and defines the process, interfaces, key deliverables and required
approvals for the planning, preparation and execution of Site Acceptance Tests (SATs)
for the projects executed by VP within QP.
2.0 SCOPE
This procedure applies to all capital engineering projects executed by VP within QP. It
applies to onshore and offshore oil & gas production, processing and transmission
facilities, refinery, infrastructure and civil projects, and associated utilities and auxiliaries.
3.0 TERMINOLOGY
3.1 DEFINITIONS
QP-ENG-PRC-008
3.2 ABBREVIATIONS
EPIC - Engineering, Procurement, Installation and
Commissioning
FEED - Front End Engineering Design (equivalent to
Engineering Definition stage – Stage 4 as per QP-
ENG-PRC-001)
SAT - Site Acceptance Test
SOW - Scope Of Work
QP-ENG-PRC-008
4.0 PROCESS
The Commissioning Team that is led by the Asset Holder team member shall lead
identifying the requirements of the various SATs during the FEED stage with full support
of the Project Team, contractor and vendors.
a) The Equipment, Systems and Plant operations meet the design intent;
b) The safe operability of Equipment, Systems and Plant so that Operational and
Final handover can be made.
These tests may include, but are not limited to, the following:
a) SATs for individual Equipment and Systems;
b) Overall Plant SAT.
The Project Team shall ensure inclusion of the agreed SAT requirements in the EPIC
(Implementation, Handover and Completion) SOW, as per the Project Execution Plan.
The Commissioning Team, shall develop a strategy for the SATs during FEED and
detailed design (Implementation, Handover and Completion) with support from the
Project Team. This strategy will be a deliverable and should include as a minimum:
Methodology;
Test parameters;
Duration of each SAT;
Acceptance criteria.
QP-ENG-PRC-008
• Parameters to be monitored;
• Data to be collected;
• Roles and responsibilities of parties involved in the test;
• Acceptance criteria;
• Test report formats.
The pre-requisites for SAT for any Equipment, System or Plant are listed below, as
a minimum:
• Pre-commissioning activities successfully completed and documented in relevant
dossiers;
• Mechanical Completion Certificate is signed off;
• SAT strategy and procedure is approved;
• Relevant training is conducted;
• Check relevant FAT records (if any);
• All Category ‘A’ Punch List Items are cleared;
• All relevant operational tests are conducted;
• Availability of vendor representative, if required;
• Cause & Effect checks are tested and documented;
For the Plant SAT, the Pre-start-up Safety Review and plant start-up shall be completed
before the SAT.
QP-ENG-PRC-008
a) The Commissioning Team shall perform the Equipment and System SATs as per the
approved procedures after their successful pre-commissioning, with the full support
of the Project Team, contractor and vendors.
c) The Performance Test may also be performed along with the SAT for Equipment or
Systems, if possible.
d) If the SAT fails, the Commissioning Team and Project Team shall jointly identify the
root cause and rectify the shortcomings with full support of the Contractor and
Vendors based on contractual agreements (in case of design-related issues, Project
team shall rectify). In such a case, the Commissioning Team shall repeat the SAT
after the necessary rectification is carried out.
e) All relevant parties who witness the SAT (i.e. representatives of Asset Holder,
Commissioning Team, Project Team, Contractor, Vendor, etc.) shall sign off the test
records/logs at agreed intervals, as defined in the project specific SAT procedures.
f) The SAT information (i.e. log sheets, etc.) shall be collected by the Commissioning
Team with support of the Project Team, contractor and vendors.
g) The Commissioning Team shall prepare the SAT Report with the full support of the
Project Team, Contractor and Vendors.
a) After Start-up and Plant stabilisation, the Asset Holder shall perform the Plant SAT.
They shall have full support of the Commissioning Team, Project Team, Contractor
and Vendors. The criteria for an acceptable Plant SAT shall be as defined and agreed
in the project-specific Commissioning Plan. A predefined, project-specific period
(generally 72 hours) of non-interrupted and stable Plant operation could be
considered as a successful Plant SAT.
b) The Performance Test may also be performed along with the SAT, if possible.
c) If the Plant SAT fails, the Asset Holder and Project Team shall jointly identify the root
cause and rectify the shortcomings with full support of the Contractor and Vendors
based on contractual agreements (in case of design-related issues, Project team
shall rectify). In such a case, the Asset Holder shall repeat the SAT after the
necessary rectification is carried out.
d) All relevant parties who witness the Plant SAT (i.e. representatives of Asset Holder,
Commissioning Team, Project Team, Contractor, Vendor, etc.) shall sign off the test
records/logs at agreed intervals, as defined in the project specific SAT procedures.
QP-ENG-PRC-008
e) Once the Plant SAT is successful, the information (i.e. log sheets, etc.) shall be
collected by the Asset Holder with support of the Project Team, Commissioning
Team, Contractor and Vendors.
f) The Asset Holder shall prepare and approve the Plant SAT Report with full support
of the Project Team, Commissioning Team, Contractor and vendors.
g) After a successful Plant SAT, the Plant Performance Test can be implemented in
accordance with QP-ENG-PRC-010 Procedure for Performance Test.
QP-ENG-PRC-008
5.0 REFERENCES
QP-ENG-PRC-001 - Procedure for Project Stage Gate Approval Process
QP-ENG-PRC-005 - Project Commissioning and Handover
QP-ENG-PRC-010 - Performance Test
QP-ENG-PRC-008
6.0 RESPONSIBILITIES
QP-ENG-PRC-008
7.0 APPENDICES
Page
Item Revised Revision Description
No.
IP-ENG-038 Rev Issued for Use. All
A1. Nov 2009
IP-ENG-038 Rev Fast-Track update to only reflect the new organizational All
A1.2. Sept 2015 changes.
Remarks :
Nil.