Water Storage Tank Construction Methodologies

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 14

[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR

January 24, 2013 WATERUTILITIES]

DESIGN & CONSTRUCTION


CONSIDERATIONS OF
REINFORCED CONCRETE
STRUCTURES FOR WATER
UTILITIES

Prepared by
ADNAN NAJEM LAZEM
M.Sc. in Structural Engineering

CONTENTS

1. Introduction
2. Examples of reinforced concrete structures for water utilities
3. Advantages of reinforced concrete structures
4. Disadvantages of reinforced concrete structures
5. Design considerations
6. Construction considerations
7. Summary

Page 1 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

INTRODUCTION
In 1907, Leonard Metcalf, a Boston civil engineer whose specialty was water
supply issues, and Harrison Eddy, superintendent of the sewer department in Worcester,
Massachusetts, were introduced by a professor at Worcester Polytechnic. Shortly
thereafter, they decided to join forces and create an environmental engineering firm
called Metcalf & Eddy.

Wilmington, Delaware
 10 million gallon covered water storage tank
 construction completed at December 2007

Page 2 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

IRAQ, BAGHDAD
• Complex of Twin Apartment water storage tanks
• Construction completed at march 2010
• 375,000 cubic meters storage capacity

Page 3 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

Pile foundation of the RC water tank “Reservoir”

Page 4 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

Final Stages of the RC Tank Construct

ADVANTAGES
1. Easily adaptable to a myriad of different shapes & architectural treatments
2. Many contractors have the capability to place reinforced concrete
3. Reinforced concrete contractor will likely already be on site
4. Durability, Proven track record of over 100 years
DISADVANTAGES
1. Owner preferences may dictate against using reinforced concrete
2. Cost considerations due to quantity of materials required
3. Construction nuances
4. Cracking & durability
DESIGN CONSIDERATIONS
1. Seismic loads
2. Floatation
3. Abnormal pressure loads
4. Retaining elements
5. Influence of adjacent / superimposed structures
6. Integration into existing facilities
7. Security
8. Details, Details, Details!
9. Liner systems

Page 5 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

SEISMIC LOADS
According to ACI 350 in chapter four Art (4.1), for Earthquake pressures above
base, the walls of liquid-containing structures shall be designed for the following
dynamic forces in addition to the static pressures:
a. inertia forces Pw and Pr ;
b. hydrodynamic impulsive pressure Pi from the contained liquid;
c. hydrodynamic convective pressure Pc from the contained liquid;
d. dynamic earth pressure from saturated and unsaturated soils against
the buried portion of the wall;
e. the effects of vertical acceleration.

BUOYANCY
A reinforced concrete reservoir – or any tank – is a boat. A boat floats if designed
Right. Therefore a design checks is required:
1. Buoyant force (uplift) on bottom slab
2. Buoyant force causing tank to float
3. Reduced base slab friction if tank sliding (uneven backfill) is a design consideration

SECURITY
Any reservoir requires security considerations.
1. How will the reservoir be inspected?
2. How will venting be accomplished?
3. Will public access be required of the top slab?

DETAILS
1. Minimum Concrete Strength
2. Minimum Reinforcing Steel
3. Expansion and Construction Joints
4. Waterstops
MINIMUM “ACI.350 CODE” REQUIREMENT:
1. Min. Concrete Strength=4000 psiat 28 days

Page 6 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

2. Air Entrainment=5%±1%
3. Maximum Water-cement Ratio=.45
4. Maximum Slump=4 inches
5. Aggregates per ASTM C33, max. aggregate size=1 inch
6. No admixtures containing calcium chloride
EXPANSION JOINTS:

Page 7 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

Expansion joints, main location.

WATERSTOP DETAIL
Base slab to wall interface is most critical and most difficult to construct of all
construction joints:
1. Raised starter wall
2. Bend top steel down at wall

Page 8 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

3. Drop top steel down below waterstop for entire slab Options 2 & 3 easier to construct
than option 1 but require relatively more material

CONSTRUCTION CONSIDERATIONS
Proper adherence to specifications
1. Water proofing process
2. Mix design
3. Placement
4. Curing
5. Deflection of structural members during pouring and vibrating of fresh concrete
6. Details, Details, Details
7. Integration into existing Facilities

Step 1, Water proofing process

Page 9 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

Step 2, Water proofing process

Page 10 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

Placement of fresh concrete

MIX DESIGN
Adding 1 gallon of water to 1 yd3 of concrete will:
1. Increase slump about 1 inch
2. Increase air content about 1%
3. Increase shrinkage about 10% and increase cracking
4. Reduce compressive strength about 200 psi
5. Waste about 25 lbs of cement per cubic yard
6. Increase shrinkage about 10% and increase cracking
7. Decrease freeze-thaw durability about 20%
8. Decrease wear resistance to traffic
9. Increase dusting and other surface defects
10. Increase time needed to finish the concrete

Deflection of structural members during construction:

CURING
According to ACI 350-01 “Environmental Structures” Code Requirements:

Page 11 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

“Minimum permeability of the concrete will be obtained by using water-cementitious


materials ratios as low as possible, consistent with satisfactory workability and
consolidation. Impermeability increases with the age of the concrete and is improved by
extended periods of moist curing.”

Plastic membrane and water retaining agent were used for curing process

MINIMUM CONCRETE COVER OF STEEL REINFORCEMENT:


Checking of Minimum Concrete Cover according to ACI 350.1:
1. Concrete Base=3 inches (4” COE)
2. Concrete Walls=2 inches (3” COE)
3. Stilling Basin=6” (COE)

Page 12 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

Checking first carried out before Pouring of fresh concrete

LEAK TESTING
According to ACI 350-01 “Environmental Structures” Code Requirements:
1.1.3—Each cell of multi-cell tanks shall be considered a single tank and tested
individually unless otherwise directed by the engineer.
1.2.3—Unless specifically allowed by the engineer, the tank shall not be tested before all
of the structure is complete and the tank’s concrete has attained its specified
compressive strength.
2.3.5—The water shall be kept at the test level of unlined concrete tanks for at least three
days prior to the actual test.
2.3.6—The exterior surfaces of the tank shall be inspected during the period of filling the
tank. If any flow of water is observed from the tank exterior surfaces, including
joints or cracks, the defect causing the leakage shall be repaired.
BACKFILLING
Backfill and compaction continues as dump trucks haul dirt in and a skid steer and
dozer spread the backfill into eight-inch lifts for compaction.

Page 13 of 14
[DESIGN & CONSTRUCTION CONSIDERATIONS OF RC STRUCTURES FOR
January 24, 2013 WATERUTILITIES]

SUMMARY
1. Engineer helps the owner determine best structural system for the facility.
2. Proper engineer detailing is a major contributor to the long-term success of the
project.
3. Proper concrete mix design, placement, and curing practices is the single most
important factor toward the long-term durability of the structure.
4. Reinforced concrete is not a “forever” material. It requires on-going care and
maintenance. A well-defined asset management program will contribute to the
long-term operation of the structure.

REFRENCE:
1. Maine Water Utilities Association April 12, 2007. Michael E. Malenfant, P.E.
Metcalf & Eddy
2. ACI 350-01 “Environmental Structures” Code Requirements.
3. University of technology, engineering consulting office. Baghdad, Iraq.

Page 14 of 14

You might also like