Department of Education

Region XII
Schools Division Office of Cotabato
Arakan West District
NAJE ELEMENTARY SCHOOL
Naje, Arakan, Cotabato
School I.D.: 129921

2023 SIP/AIP Review Form


PERFORMANCE MONITORING
A. MID-YEAR REVIEW OF PLANNED PROGRAMS AND ACTIVITIES (PPAs)
Using your SIP/AIP-WFP, Identify the following:
(a) PPAs already implemented, (b) PPAs with on-going implementation, and (c) PPAs that have yet to be implemented. Then fill out the tables with required
data and information.
A.1. PPAs Already Implemented/Conducted/Completed/Done
No. PPAs Already STATUS Actual Number of IF ON GOING/ COMPLETED IF NOT IMPLEMENTED
implemented/Completed/Condected/Don beneficiaries What is the initial/ final results ( What are the hindering
e PLEASE RELATE WITH KPI’S Factors)
ACCESS
1. Conduct Early Registration Implemented M-114, F-95 T- 209 100% Early Registration Conducted
2. Posting Announcement in Populace Area Implemented M-114, F-95 T- 209 100% Posting/ Announcement
3. Conduct Brigada Eskwela 2022 Implemented M-114, F-95 T- 209 100% Brigada Eskwela
4. Conduct Enrolment-June 2022 Implemented M-114, F-95 T- 209 100% Conduct Enrolment
5. Conduct Home Visitation On Going M-114, F-95 T- 209 Monitoring every Month those -
PARDOS

QUALITY
1. Capacitate Teachers Through In-Service Implemented M-114, F-95 T- 209 100% Every month conducted
Trainings, Seminars, and Capabilities in SLAC
Coordinatorship Through Virtual Webinars Teachers capacitated
(SLAC)
2. Conduct Grading Examinations Implemented M-114, F-95 T- 209 100% Every Grading Period -
Conducted Examinations
3. Provision of Instructional Materials Implemented M-114, F-95 T- 209 100% Provision of Instructional
Materials through MOOE Funds
4. Provision of Teaching Equipment Partially M-114, F-95 T- 209 Some Gadgets like printers, laptop
Implemented and TV purchased
5 Conduct Brigada Pabasa Implemented M-114, F-95 T- 209 100% Brigada Pagbasa Conducted
By Puroks
6 Conduct Instructional Supervision to 8 Implemented M-114, F-95 T- 209 Every Month 8 Teachers
teachers monitored and Conduct
Instructional supervision
7 Conduct of PTA meeting/SMEPA Implemented M-114, F-95 T- 209 100% Conducted Monthly SMEPA
And PTA Meetings every Quarter
8 CFSS/Child Protection Policy/DRRM Implemented M-114, F-95 T- 209 100% CFSS, Child Protection
Policy and DRRM -disseminated
guidelines and implemented
9 Health and Nutrition Implemented M-114, F-95 T- 209 100% SBFP
10 Project SHARP and CNR Implemented M-114, F-95 T- 209 Conducted Reading with the use of
Localized Teacher Made Work
books in Reading

GOVERNANCE
1. Construction of Perimeter Fence Not yet implemented M-114, F-95 T- 209 Funds to be downloaded 2nd
Quarter MOOE Funds
2. Repainting and Enhancement of Office Not yet implemented M-114, F-95 T- 209 Funds to be downloaded
1ST Quarter MOOE Funds
3. Additional Gendered Comfort Rooms Not yet implemented M-114, F-95 T- 209 Nonavailability of Funds/ Needs
Follow-Up Coordination for the
Project Proposal to External
Stakeholders
4 Put up Reading Center and Parking Space Not yet implemented M-114, F-95 T- 209 On going PTA Funds
collectibles/ Unavailability of
Materials
5. Enhancement of Parks and GPP On Going M-114, F-95 T- 209 50% implemented due to
insufficient funds for materials
Prepared by:
GERALDINE J. DULAY
Head Teacher III Noted by:
JULIET B. VILLA
Principal In-Charge