Task 1a

Learners will plan their roles and activities as per the requirement of project. For
example, if project is based on design of residential building, roles will be:

 Planning and Design team,

 Rate Analysis and Quantity Estimator,

 Development of project summary using Software (Microsoft Project


Planner).

Introduction planning and design team


Proper management of resources is called planning. Planning is one of the core
areas of project construction. Planning in a construction projects is done in order to
work out with quantities required to cover the total scope of project completion schedule
using project management tools like MS project.

A designer is an organization or individual whose business involves preparing or


modifying designs for construction projects, or arranging for, or instructing, others to do
this. Designs include Drawings, Design details, Specifications, Bills of quantity and
design calculations, Architects, Consulting engineers, Quantity surveyors and interior
designers etc.

Roles of Project Members


In order to start a project first of all we decided to make a team and appoint roles
to them. These roles and activities may include:

 Planning and design team


 Rate analysis and quantity estimator
 Project development using Microsoft process planer software.

.
Sr. Designated Phase of Activities
no. Member project
1.  Zoha Reconisence  Site visit and will have a meeting with
 Sarmad community staff and discuss their needs
 Maham regarding construction activity.

 Afzal
2.  Maham Planning  Cost allocation
 Afzal  Time allocation
 Zoha  Defining scope of the project.

3.  Zoha Design  Architectural design and development of


 Maham CAD drawings.

 Sarmad  Structural design and development of


 Afzal CAD drawings.
4.  Sarmad Rate Analysis  Preparation of rate analysis of
 Afzal And Quantity architectural work.
Estimator  Rate analysis of structural works.

 Maham  Preparation of BOQ of architectural work


 Zoha  Preparation of BOQ of structural work.
 The calculation of BOQ of plumbing work.

5.  Maham Costing and  Cost analysis of architectural works


 Zoha estimation

 Sarmad  Cost analysis of structural works


 Afzal
6.  Zoha Presentation  Presentation of architecture works
 Maham
 Sarmad  Presentation of structure works
 Afzal
Task 1b

Learners should formulate specification with regard to constraint. Learners will


have to incorporate following mentions areas in specification:

 Client Brief,
 Technical and non-technical Specification,
 Costs,
 Timescales,
 Standards, code of Practice.

Task 1c

Learners are advised to formulate initial proposal of project and justify the
selection of project with cost, suitability and with environmental impacts.

Project justification
We visited rural area and observed that there is a requirement of school in global
aspect. We perceived that the schools were far apart from village area. The
transportation cost was very high, so therefore most of the children cannot go to school.
We saw that literacy rate at that area was very low.

We visited the nearby school as well. It was not in good condition. There were no
facilities like labs etc. all students of different classes were in same class room. There
was no playground and no proper teaching staff.

As we know that school is a basic requirement of any community. We thought to


build a school in that area. Then we met one person over there, he came from abroad
and was highly qualified. He wanted to make school but he was not having resources.
We recommended him to visit an NGO and human development authority, as they tend
to invest for building a school in that area.
By constructing a school building more students will get education and literacy
rate will also increase. Moreover, students who are already going in school that are far
away from their home can also save their time and transportation cost as well.

Task 2a

Learners will produce complete evidence of project development in the form of


Logbook entries, team minutes of meetings etc.

Log sheet
Sr. no Activity Date Remarks
1. Site visit 3 – Oct – 2017 I have done meeting with the
people of village to get there
opinion.
2. Site visit 5 – Oct – 2017 I have done meeting with client. In
meeting we discussed his
requirements.
3. Met GM of Emaar 8 – Oct – 2017 I met the general manager of
NGO Emaar and done meeting
regarding the project.
4. Met GM of Emaar 11 – Oct – 2017 I met GM of Emaar and discussed
NGO
5. Visited human 12 – Oct – 2017
development
authority
6. Meeting with 16 – Oct – 2017
community staff
7. Meeting with group 19 – Oct – 2017
members
8. Architecture design 23 – Oct – 2017 Using AutoCAD architectural
of a project design of a project is made.
9. Architecture design 24 – Oct – 2017 Using AutoCAD architectural
for ground floor drawings was being made.
plan Proposal 1
10. Architecture design 26 – Oct – 2017 Proposal 2
for ground floor
plan
11. Amendments made 30 – Oct – 2017 White board was not used in class
in class room rooms. So we made changes and
used white board in class as well.
12. Preparation of roof 1 – Nov – 2017 Slopes were required on roof for
plan the drainage of rainwater.
13. Preparation of 4 – Nov – 2017 Elevation of school was made.
elevation 1
14. Preparation of 6 – Nov – 2017 Changes is made in elevation
elevation 2 drawings.
15. Preparation of 9 – Nov – 2017 Cross section of a school building
cross-section 1 was made and checked.
16. Preparation of 6 – Nov – 2017 Cross section is made for the
cross section 2 second time due to some issues in
accuracy.
17. Preparation of 8 – Nov – 2017 It was being checked that where
washroom details washrooms are required in school.
18. Preparation of 14 – Nov – 2017 Structural drawings is made.
structural drawings
19. Design of 22 – Nov – 2017 Design of foundation carried out
foundation level using excel sheet.
plan
20. Development of 6 – Jan – 2017 Footing layout plan preparation
Footing plan using was done.
AutoCAD
21. Design of plinth 15 – Jan – 2017 Plinth beam design is made using
beams excel sheet
22. Preparation of 20 – Jan – 2017
plinth beam
designs
23. Preparation of lintel 28 – Jan – 2017
beam design
24. Slab design 5 – Feb – 2017 Design of slab is made using excel
sheet.
25. Preparation of slab 15 – Feb – 2017
drawings
26. Group meeting 26 – Feb – 2017 Meeting with the all team members
is made in order to discuss all
above activities.
27. Preparation of 4 – March – 2017 Preparation of elevation report was
elevation report done to perceive what flaws are
left. And how to overcome them.
28. Power point 11 – March –2017 I worked out for Presentation of
presentation Project Details by Power Point
slides.
29. Preparation of 15–March– 2017 Finalization of Project Report with
report future recommendation.

Learners are advised to produce final design proposal to meet the agreed
specification. Learners will have to incorporate following areas:

 Geotechnical information,
 Project drawings,
 Costings and calculations.
Task 3

Learners are advised to submit complete evaluation report on project and also
include recommendation for further improvement.

Project Making Recommendations for Improvement


In order to enhance the excellence of work associated to time, budget and scope
I recommend to use steel chokaths if required and also use water proofing DPCs in
foundation. Use termite in foundation at the binging of the project and also use it for the
second time before floor PCC.

Increase the size of footing because if column is being jacketed, the transfer of
load from column to footing becomes easy. In non-technical specification I recommend
that the better quality doors can be used, such as “diyar wood”. This will also not affect
the cost. It also gives a good aesthetic look.

Moreover, the diameter and number of steel bars should be according to the
design. Furthermore, weather sheet paints can be used in the external walls of a house
as it is water resistant. I will also recommend fiber optic wire cables for an electrical
wiring.