QUOTATION FOR CABRO FIXING PARKING AREA 228M2.

A) Materials required for cabro work.


- Cabro area 228m2 @850 - 193,800/=
- Road Kerbs 33pcs - 13,860/=
- Stone dust 22 tones - 30,600/=
- Road Channels 8pcs - 2000/=
- Cement 7 bags - 4,760/=
- Transport - 10,000/=
B) Labour Charge - 57,000/=
Grand Total - 312,020/=

SMOOTH CABRO
A. Materials Required.
- Cabro area 228m @1200/= - 273,600/=
- Road kerbs 33pcs - 13,860/=
- Road channels 8pcs - 2000/=
- Stone Dust 22tones - 30,600/=
- Cement 7 bags - 4,760/=
- Transport - 10,000/=

Labour Charge - 57,000/=


Grand Total - 334,820/=

Prepared by Benson 0724-015431