JETIR2303676
JETIR2303676
org (ISSN-2349-5162)
Abstract-Energy meters are the key component of the Energy meter data, smart grid data and strengthen
Automatic Metering Infrastructure (AMI) and cybersecurity.
efficient measurement of electricity, interoperability, Advanced metering infrastructure (AMI) is a joined
interchangeable, collection of Energy meter data, system of smart meters for capturing data,
smart grid data and strengthen cyber security are the communications networks for transferring the data and
required features of the Energy Meters. data management systems for efficient use of data
To verify the compliance of these functionalities of the collected. With these systems and provision of two-way
Energy Meters Indian/InternationalStandards have communication between utilities and customers, the AMI
been introduced. provides several important functions that were not
This Paper shares the latest functionalities possible previously or performed manually, such as the
requirements of static meters in view of smart grid capability to measure electricity uses automatically and
and AMI also focus on series of Indian Companion remotely, disconnect and connect service, tamper
Specification (ICS)i.e. IS 15959 (Part1):2011, detection, identifying the abnormal conditions and isolate
IS15959(Part2):2016 and IS15959(Part3):2017 which it and monitor various parameters such as voltage,
specify operational capabilities of Data Exchange for current, Power factors and harmonics. With customer
Electricity Meter Reading,Tariff and Load control technologies, such as programmable communicating
which are the key features of the Smart Grid. thermostats and in-home displays, AMI enables utilities
Keywords – Smart Energy Meters, DLMS/COSEM, for offering time-based tariff and incentives which
Smart Prepaid Energy meters, load switch, two way encourage customers to reduce its demand during peak
communication, Communicability hours and get the benefit of less tariff rate by managing
their energy consumption. [10]
I. INTRODUCTION Advance metering infrastructure (AMI) is classified
The present situation of the world calls for sustainable intofour layers:
and efficient electricity generation and its appropriate Top layer is known as the master station consisting of
management method as we aretotally dependent for measure data management unit, communication
supply the energy demand onnon-renewable sources, management unit and power user management unit of
which takes many of years to replenish and it isn’t AMI system. The master station includes the network
sustainable in the long run[12]. The way out are the uses equipment, servers and various management terminals.
of renewable energy, Government of India also focusing The second layer provide cannels to released
on the sustainable energy through naturally available communication from the master station to smart meters
energy resourcessuch as hydroelectricity, biomass, and smart hand- held terminals and provided channels for
geothermal, wind, wave, tidal and solar energies.Results power company and users to realized two –way
indevelopment of micro grid and Nano grid, which interaction.
requires efficient Management of supply and demand of The Third Layer is smart measurement and distributed
electricity, improved interoperability, collection of power station, including smart meters, smart hand- held
terminals, distributed power generation systems. Smart
JETIR2303676 Journal of Emerging Technologies and Innovative Research (JETIR) www.jetir.org g497
© 2023 JETIR March 2023, Volume 10, Issue 3 www.jetir.org (ISSN-2349-5162)
meter is a core equipment mainly realize energy C. Static Energy Data IS 15959 (part
metering, parameters measurement, prepaid functions Meters, exchange 1), IS 15959
parameters setting, detection of events and reporting, Prepaid protocol (part 2) for
data acquisition and storage, communication, Energy and Direct Current
programming, electricity pricing etc. Meters and Communi meters and
Fourth Layer is indoor intelligent terminal i.e. Hand Held Smart meters cation IS15959 (part
Unit (HHU) and Smart meter constitute the interactive 3) for
portal for users. Smart display terminals can read, report transformer
and display the energy consumption of electricity, it can operated
report the information of fault and maintenance, meters.
announcements issued by the master station can be
received and can be seen by electric users and company.
A. Metrological Testing:There are around 40
nos. of tests to verify the performance of the
II.METER FUNTIONALITIES REQUIRED FOR THE
meters at different service conditions such as
AMI
electromagnetic fields, climatic conditions,
Meter being an intelligent component between under various influence quantities such as
distribution and consumption of electricity and of AMI, voltage variation, frequency variation,
many task to be performed by it as shown in the harmonics, magnetic fields etc. and also under
Figure.1 fault condition such as short circuits and earth
faults, which may affect at the fields.
B. Load switching capability: Smart meters roll
out is due to its functionality to manage supply
through the reduction of demand during peak
hour, individual loads switching for energy
saving, prepaid billing for the consumers and
user refusing to pay electric bill or abusing the
use of electricity can be disconnected by the
utility. This ability to
Figure1- Functions of Smart meter in AMI
disconnection/connectionof power is possible
To perform all the functions mentioned in the above because of the use of latching relays (Load
figure, Energy meters have different features. These Switch) inside the meter and hence the quality,
features of the Energy meter described Table 1 with reliability and safety of the latching relays are
reference to the Indian standards to confirm its an important aspect. There are tests stated in
performance. the standards IS 15888 to verify the load switch
[1].
Table. 1–Static meter functions and its Testing standards C. Data Exchange Protocol: The main intention
of introducing Meter protocol testing is to
Sl. ensure interoperability of Energy Meters of
Type of Function Standards
No various manufacturers for utilities and to
meters s
. support of AMI (Automatic Meter
A. Static Energy Metrologi IS 13779, IS infrastructure).DLMS (Device Language
Meters, cal 14697, IS Message Specification) is important for
Prepaid function 15884, IS achieving interoperability and hence changed
Energy 16444 (part 1) the Power sector from monopoly to open and
Meters and and (part 2) standardized market.‘Tests for Data Exchange
Smart meters Protocol’ carried out for data verification on
B. optical port to verify the association
Prepaid Load IS 15884 requirements, parameters and profiles in
Energy switching accordance with the standard. The ‘Tests for
Meters and Smart Meter Communicability and Functional
Smart meters requirements’ carried out on meter for
Compliance to DLMS/ COSEM (companion
JETIR2303676 Journal of Emerging Technologies and Innovative Research (JETIR) www.jetir.org g498
© 2023 JETIR March 2023, Volume 10, Issue 3 www.jetir.org (ISSN-2349-5162)
specification for energy metering) open In contrast to other types of equipment, testing of energy
protocol. meters for communication protocol is crucial to ensuring
III. CATEGORIES OF STATIC METERS that the meter complies with the Meter protocol
standards as stated in Table 1 and also in order to make
Static Meters are divided in deferent categories the device work vendor-neutrally, interoperability and
depending upon the energy load requirements and type the simple collecting of data from the meters using any
of consumer such as Domestic consumers, industrial third-party client tool or utility specified tools.
consumers and measurement of energy for utility. The
electricity meters have been selected for compiling The Open Systems Interconnection (OSI) model is used
comprehensive lists of parameters with theirdata by DLMS/COSEM to simulate information exchange
identifiers in the following categories as required for between meters and data gathering systems i.e. Head end
data networks in India for COSEM procedures and System (HES) of the utilities.
services[2][3][4]. The Open Systems Interconnection (OSI) consisting of
Table. 2 – Categories of Static meters functional layers for communication process arrange one
above other as shown in Figure 2 and each layers have
Sl.No. Service Metering Nomenclature/purpose different responsibilities. [9]
category
JETIR2303676 Journal of Emerging Technologies and Innovative Research (JETIR) www.jetir.org g499
© 2023 JETIR March 2023, Volume 10, Issue 3 www.jetir.org (ISSN-2349-5162)
testing parameters and Testing Tools as shown in Figure CTT has different version that used for testing
3.
CTT 3.0 has been introduced in July 2015 and
used until 31st December 2019
CTT 3.1 has been introduced in March 2017
DTT 4.1 & 4.2 had introduced recently and is the
latest version of the tool available.
Selection of communication parameters Test report is generated after completing the whole
Selection of Test options and test cases to be testing process. Test report is consisting general test
performed information like date of test, CTT version, manufacturer
information, FLAG I’d. Summary of test report mainly
Running the test sessions
contains number of test cases executed, application
Generation and saving of test results context supported, authentication mechanism supported,
JETIR2303676 Journal of Emerging Technologies and Innovative Research (JETIR) www.jetir.org g500
© 2023 JETIR March 2023, Volume 10, Issue 3 www.jetir.org (ISSN-2349-5162)
extended DLMS services and security features supported a) Basic Security -
by MUT.
Test report also contains different outcomes for all test The basic security provides sign-on authentication as low
cases performed on MUT, these outcomes are as follows: level and high level security as applicable to the
PASSED: respective association. Basic security does not provide
It means test outcome conforms to the requirement to encryption and authentication of data. All the meters
the standard. require implement basic security feature.
FAILED:
It means that test outcome does not conformance to the
requirement of the standard. b) Advance Security -
INCONCLUSIVE: In advance security, encryption and authentication of
It means test outcome neither pass nor fail (sometimes data are provided by application programmed and
the verdict of selective access test is inconclusive due to transferred using ciphered APDU’s. Smart meter is
unavailability of data in profile buffer). required to implement advance security.
INAPLLICABLE: The confidentiality of meter data is achieved by
It means that test cases are not applicable to the MUT as encryption. ‘Logical name with ciphering’ application
per declared CTI file. context provide encryption service in the smart meter.
SKIPPED: Ciphering can be encryption, authentication or both.
It means that test cases are not performed on the MUT.
iii) Simultaneous Operation
2. Parameter Verification: Simultaneous Operation is only applicable to meters that
have both Optical and Electrical port, so it is not
Parameter verification done as per the requirement of applicable to the smart meters. Simultaneous operation
Indian standard (IS15959).List of Parameter for different of both ports is not permitted as per standard. In case if
categories of meters already described in Indian standard. both ports are accessed, optical port shall have priority.
In the parameter verification, all the Interface Classes are
verified with their all the attributes. iv) Profile Generic Parameters
List of parameters that are verified are as follows: The profile generic objectsare classified as follows:
SlNo. Identified Push Push Setup Push Script Usage Triggering Object OBIS and IC
Instance Instance(O Table
BIS) Number
JETIR2303676 Journal of Emerging Technologies and Innovative Research (JETIR) www.jetir.org g503
© 2023 JETIR March 2023, Volume 10, Issue 3 www.jetir.org (ISSN-2349-5162)
VI. ADDITIONAL COMPLIANCE TESTING FOR SMART the load across meter is within limits meter shall
METERS remain in normal connect mode.
The smart meter shall support some tests with their
If the load across meter is still more than the preset
communication module (NAN / WAN)
load limits values, it will lock out and wait for 30
List of tests as given in Table 5 below.
min (lock out period). After this lock out period the
Table 5 – Tests to be carried out with communication module meter shall reconnect the load and if the
consumption is still above the limit, again whole
Sl. Name of Test Description process is repeated till the meter loading comes
No under defined loading conditions. All these
1 Association Object List download for connection and disconnection mandatorily notified
Properties all associations of the to Head end system.
meter
2 2 Data Read Any five parameters from
instantaneous parameters In all other disconnection that occurred in the meter
33 3 Profile Read Reading Billing Profile except due to overcurrent and load limit value, the
Parameters reconnection can be done form head end system
44 4 Selective Any two parameters from only. In any case when communication failure
Programmability Programmable occurs with HES, reconnection of load switch can
Parameters be done using optical port of the meter locally using
54 5 Reporting of Event Event Push and Periodic predefined security for that purpose.
Push
65 6 Connect/Disconnect Remote Connect and
iii) All connection and disconnection of load switch
Disconnect of Load
in the smart meter shall be logged into control
Switch
77 7 Firmware Upgrade Remote firmware Events profiles.
upgrade of meters.
iv) Smart Meters shall also respond to any kind of
request form HES that comes with specified
VII. COMPLIANCE TESTING AS PER IS16444: security.
Some of the request are as:
i) Disconnection Mechanism On demand meter reading request from HES
Scheduled meter readings request from HES
The load disconnection (Disconnection of all the load Remote Firmware Upgrade process from HES
switches) in the smart meter shall occur under the All kinds of Programming request from HES
following conditions:
When overcurrent event occurred in the meter for
a predefined period of time (Persistent Time). v) Status of load switch indication for connect &
When the loading on the meter increases the limit disconnect) shall be available on the Meter
defined in load control limit function. LCD Display.
When any tamper condition occurs.
When meter get disconnect command from head vi)Smart Meter shall detect all Power On and Power
end system, and Off condition that occurs in the meter and it shall
When balance exhausted in the meter in case of Communicate it to the HES[5][6].
pre-payment metering
JETIR2303676 Journal of Emerging Technologies and Innovative Research (JETIR) www.jetir.org g504
© 2023 JETIR March 2023, Volume 10, Issue 3 www.jetir.org (ISSN-2349-5162)
achieve the goal of demand side management and to Smart Meters as per Indian Standards by Viji
improve the operational efficiency. Bharathi,Jiju, Dhanavath Shankar and P.V.
HarinathBabu, CPRI, Bangalore andCDAC,
Meter data exchange protocol provides details of
Thiruvananthapuram.
parameters required to be monitored and action to be
taken at various levels with authentications and
[11] https://www.electricalindia.in/role of smart
encryptions. Introducing DLMS protocol in India also
meters in smart grid (visited on 22.02.23).
ensured interoperability of Energy Meters of various
manufacturers with different communication modules.
[12] https://genuspower.com/advanced-metering-
IX. ACKNOWLEDGEMENT infrastructure-for-sustainable-and-efficient-
electricity-management/(visited on 27.02.23).
The authors would like to thank management of CPRI
for providing an opportunity to carry out the work and
to publish this paper. [13 ]https://www.energy.gov/sites/prod/files/2016/12/3
X. REFERENCES 4/AMISummaryReport_09-26-16.pdf(visited on
27.02.23).
[1] IS 15884:2010a.c. direct connected static
prepayment meter for active energy, class1and2 [14] Zhang Luhua, YIZhonglin, Wang Sitong, Yuan
[2] IS 15959(Part 1):2011 Data Exchange for Ruiming Zhou Hui, Yin Qingduo “Effects of Advanced
Metering Infrastructure (AMI) on Relations of Power
Electricity Meter - Reading Tariff and Load
supply and application in Smart Grid”
Control - Companion Specification – Static
Energy meters
XI.AUTHORS
[3] IS15959 (Part 2):2016 Data Exchange for
Electricity Meter - Reading Tariff and Load
Gyan Prakash Nirmal, completed graduation in
Control - Companion Specification – Smart meters Electrical Engineering from MMMUT
[4]IS 15959(Part 3):2017 Data Exchange for Gorakhpur. Presently working as a Test
Electricity Meter - Reading Tariff and Load Engineer in Energy Meter Testing Lab
CPRI, Bhopal and having experience of
Control - Companion Specification – Smart
three and half year in field of testing and
meters(Transformer operated kWh and kVArh, certification on energy meters.
Class 0.2s,0.5s and 1.0s)
[5] IS 16444(Part1):2015 a.c.static direct connected Deepa Warudkar, completed graduation in
Watthour smartmeters,class1and2 Electrical Engineering from Nagpur
University and M.Tech in HEE from
MANIT, Bhopal. From last 20 years
[6] IS16444 (Part 2):2017 a.c Static Transformer
working as a Test co-ordinator in Energy
operated watthour and Var-Hour Smart Meters, Meter Testing Laboratory in CPRI, Bhopal.
Class 0.2s,0.5s and 1.0s
[7] IS 13779:2020 a.c.static watthour smart meters, B. A. Sawale : BE, MTech, MBA, Senior
Member IEEE. He is an Additional
class1and2
Director, Unit Head of CPRI Bhopal. He
[8] IS14697:2021 a.c. StaticTransformer operated is also Project Incharge and Unit Head of
watthour and Var-Hour Meters, Class 0.2s, 0.5s Regional Test Center, CPRI, Nashik. He
is also the Chairman of Sectional
and 1.0s
Committee ET13 of BIS on "Equipment
[9] https://www.electricalindia.in/Qualitative for Electrical Energy measurement and Load control".
Testing of DLMS/COSEM ICS compliant Energy He is a Member of International Electrotechnical
Meters by- V Sureshand V Arunachalam, CPRI, Committee (IEC) -Technical committee TC13 &
Bangalore(visited on 27.02.23). Working Group 11, 14 and 15, Member of Maintenance
Committee under IEC TC 13. He headed Task force
[10] Testing challenges for DLMS Compliance tests of under IEC TC 13 for Safety Standard, Member of state
tariff advisory committee of MPERC, NABL.
JETIR2303676 Journal of Emerging Technologies and Innovative Research (JETIR) www.jetir.org g505