Bill Witt Aquatic Center Presentation

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

Bill Witt Aquatic Center

Council District 5

Council Presentation
March 28, 2023
1
Bill Witt Aquatic Center
Construction Scope
Includes:
 Competition Pool
 Recreational Pool
 Bath & Admin Bldg.
 Parking Lot
 Fabric Shading
 Food Truck Area
 Facility Lighting
 Enclosed Body Flume
Slide
2
Bill Witt Aquatic Center

Design Is Part Of:


 The Bill Witt Master Plan
 The 10-year Parks Masterplan
 2020 Hanson Feasibility Study

3
Bill Witt Aquatic Center
(North Arial View)

4
Bill Witt Aquatic Center
(Recreational Pool Aerial View)

5
Bill Witt Aquatic Center
(Competition Pool West Aerial View)

6
Bill Witt Aquatic Center
( South Aerial View)

7
Project Schedule

2023 2024
January - March April - December January- May
Bid / Award Construction

Project schedule reflects construction starting in April 2023


with anticipated completion by May 2024.