METHOD STATEMENT: BORED PILE CONSTRUCTION
TABLE OF CONTENTS
1.0 PURPOSE .................................................................................................................................................. 3
2.0 SCOPE ....................................................................................................................................................... 3
3.0 DEFINITIONS ............................................................................................................................................. 4
4.0 RESPONSIBILITIES .................................................................................................................................. 4
4.1 PROJECT MANAGER: .......................................................................................................................... 4
4.2 PROJECT HSE REPRESENTATIVE: ................................................................................................... 5
4.3 CONSTRUCTION MANAGER/PROJECT ENGINEER ......................................................................... 5
4.4 QA/QC ENGINEER ................................................................................................................................ 6
4.5 SURVEYOR ........................................................................................................................................... 6
4.6 PROJECT EMPLOYEES: ...................................................................................................................... 6
5.0 RESOURCES ............................................................................................................................................. 7
5.1 WORKFORCE........................................................................................................................................ 7
5.2 PLANT / EQUIPMENT / TOOLS............................................................................................................ 7
5.3 MATERIALS / PRODUCTS ................................................................................................................... 7
6.0 PROCESS DESCRIPTION ........................................................................................................................ 7
6.1 QUALITY ASSURANCE / QUALITY CONTROL ................................................................................... 7
6.1.1 Inspection and Testing Plan (ITP) ...................................................................................................... 7
6.2 HEALTH AND SAFETY ......................................................................................................................... 8
6.2.1 Emergency Response ........................................................................................................................ 8
6.2.2 Risk Assessment ................................................................................................................................ 8
6.3 ENVIRONMENT ..................................................................................................................................... 8
6.3.1 Environmental Aspects and Impacts .................................................................................................. 8
6.4 PRELIMINARY ACTIVITIES .................................................................................................................. 8
6.5 CONSTRUCTION SEQUENCE ............................................................................................................. 9
6.5.1 Working Platform .............................................................................................................................. 10
6.5.2 Setting Out / Survey of Piles ............................................................................................................ 10
6.5.3 Temporary Casing Installation .......................................................................................................... 10
6.5.4 TOLERANCES ................................................................................................................................. 11
6.5.5 Fabrication of Pile Reinforcement .................................................................................................... 11
6.5.6 Drilling of Pile Borehole .................................................................................................................... 11
6.5.7 Disposal of Excavated Spoil ............................................................................................................. 13
6.5.8 Reinforcement .................................................................................................................................. 13
6.5.9 Installation of Reinforcement Cage .................................................................................................. 13
6.5.10 REINFORCEMENT CAGE LIFTING PROCEDURE .................................................................... 15
6.5.11 Placement of Pile Concrete .......................................................................................................... 17
6.5.12 Concreting Using Funnel .............................................................................................................. 19
6.5.13 Casing Extraction after Concreting Works ................................................................................... 20
7.0 PILE TESTING ......................................................................................................................................... 22
7.1 CALLIPER LOGGING .......................................................................................................................... 22
7.2 PILE INTEGRITY TEST ....................................................................................................................... 22
7.3 CROSS HOLE SONIC LOGGING........................................................................................................ 22
7.4 STATIC LOAD TESTS ......................................................................................................................... 22
7.5 DYNAMIC LOAD TESTS ..................................................................................................................... 22
8.0 RETAINED INFORMATION ..................................................................................................................... 23
9.0 REFERENCES ......................................................................................................................................... 23
APPENDIX 1: INSPECTION AND TEST PLAN .................................................................................................. 25
APPENDIX 2: CONTROL FORMS ...................................................................................................................... 26
1.0 PURPOSE
The purpose of this Method Statement is to provide specific instructions for the execution of Bored Pile
lete the project in a
save and timely manner to achieve the expected Quality and HSE outcomes.
Pile Foundation
2.0 SCOPE
This method statement covers the processes required to be undertaken for the execution of the Bored Pile
Construction on the project which include, but are not limited to:
1. Mobilization of necessary plant & equipment necessary to carry out the works.
2. Employment of skilled, semi-skilled personnel necessary to carry out the works.
3. Providing construction materials at the pile location.
4. Survey Works/ Setting out of points.
5. Bored Pile Construction:
• Installation of temporary steel casing having nominal diameter as per approved IFC drawings.
• Fabrication of pile reinforcement.
• Drilling of borehole using appropriate tools up to the toe level as shown in IFC drawings.
• Cleaning of borehole base.
• Disposal of Excavated Spoil.
• Installation of Reinforcement Cage.
• Placing of pile concrete.
6. Maintaining “As Built” record of the pile construction data and submitting the same to Consultant/
Engineer for records.
7. Performing quality control tests on production piles and submission of test reports.
8. Logistics, General Site Management and Lighting.
3.0 DEFINITIONS
4.0 RESPONSIBILITIES
4.1 PROJECT MANAGER:
ible for ensuring that
project quality meets the Employer’s requirements. The Project Manager is the leading authority on site and is
responsible for ensuring that the project meets both the statutory minimum legal and Employer’s Health and
Safety requirements. The Project Manager ensures the proper and timely execution of the issued design works
and the execution and maintenance of site works according to specifications, IFC drawings and program of
work. Individual responsibilities including specific quality requirements for all staff will be set by the Project
Manager and shall be defined in their Job Description.
Their role and responsibilities include but are not limited to:
• Provision of all necessary resources required to comply with this Method Statement;
• Approval of Method Statement and associated ITP
• Ensure that all Environmental aspects, together with potential impacts and all OHS Hazards and Risks
associated with this Method Statement are identified, documented and mitigated;
• Ensure that all HSE related incidents are reported to appropriate stakeholders and investigated to
identify corrective actions to prevent recurrence
• Ensure that all potential Emergency situations arising out of this Method Statement are considered in
the Project Emergency Response Plan
• Ensure that all Project employees receive appropriate HSE related training.
• Nominate and appoint Competent Authorized persons to fulfil key roles (e.g., PTW Issuing Authority);
• Obtain a copy of all relevant documents such as Construction Permit, Demarcation Certificates, NOC
from the authorities, release of site from the Client/ Main Contractor/ Engineer before commencement
of work.
• Approval of all sub-contractor, supplier, and materials.
• Stop any work activity where imminent danger to Project employees and other stakeholders or potential
for damage to the environment exists.
4.2 PROJECT HSE REPRESENTATIVE:
The Project HSE Representative’s role and responsibilities includes but is not limited to:
• Assist with the development of Project HSE Plan, Procedures and Project Emergency Response Plan
• Devise and implement Project HSE Training Program;
• Establish and maintain a Project HSE legal register and evaluate compliance periodically;
• Evaluate / review work methodologies and preparation of suitable and sufficient risk assessments;
• Devise and implement active site monitoring programmes to verify legal and other HSE compliance,
report identified issues and provide guidance / assistance as necessary;
• Ensure closure of any HSE related non-compliances identified through audit or inspection processes;
• Attend all Employer / Employer’s Representative meetings and site inspections.
• Report all HSE related incidents to Project Stakeholders;
• Lead, or assist with the investigation of HSE related incidents (as required);
• Stop any work activity where imminent danger to Project employees and other stakeholders or potential
for damage to the environment may exist.
• Ensure associated HSE related contemporary records are maintained at all times;
The Construction Manager/ Project Engineer reports directly to the Project Manager. Their role and
responsibilities include but are not limited to:
• To support implementation and maintenance of the ‘Project Operations’ elements of the Integrated
Management System (IMS) on assigned Project;
• To monitor the effectiveness of Construction Processes and drive continual improvement.
• Lead / coordinate pre-construction work preparation meetings with Technical Manager, Resource Manager,
Workshop & Logistics Managers to ensure maximum understanding of the works, ensuring efficient Project
mobilisation and operation;
• To share specifications, method statements and available drawings with subordinate teams, including
subcontractors, to deliver expected construction requirements, including any revisions.
• To implement effective change management ensuring that latest versions of drawings and other relevant
documents, inclusive of contract variations are available and maintained.
• Establish positive working relationships with Project stakeholders (Eg Engineer) to include timely and
accurate document preparation and submission, and onsite coordination with Employers Representative
teams,.
• Develop construction programme with PM and implement active monitoring and controls, to ensure works are
delivered in accordance Project Contract requirements, inclusive of all subcontractor activities.
• To ensure all necessary construction permits, and PTWs are in hand before starting relevant work activities.
• To fulfil quality, health, safety and environment responsibilities in accordance with IMS.
• Undertake all relevant training and identify development opportunities as required.
• To attend the Weekly Progress Meetings (Internal & Client) and ensure timely close out of all action items;
• To lead internal construction team meetings and ensure timely close out of action items;
• In absence of PM, agree all Contract variations with client, in accordance with defined Change Management
processes, inclusive of invoicing and project controls reporting to Branch office.
• To report directly to PM on all matters related to construction activities, in respect of cost, forecasts and
progress, identifying Project risks & opportunities throughout the project lifecycle;.
• To coordinate, control and optimise the work outputs of the plant and human resources across working areas,
ensuring compliance to work program throughout project lifecycle;
• Liaise with Workshop and Resource Managers for forecasting and planning of project resources (equipment
& manpower) throughout Project lifecycle;
• Prepare weekly cost / performance reports in accordance with requirements
• Support PM to achieve effective handover and project close out.
• To lead subordinate teams by example to ensure compliance with IMS and applicable statutory duties
4.5 SURVEYOR
The Surveyor reports to the Project Manager through the Site Engineer. Their roles and responsibilities include
but are not limited to:
• Execute daily survey field tasks according to the procedures of the Survey Department.
• Perform setting-out tasks and as-built survey tasks as assigned by the Construction Manager.
• Maintain proper survey records.
• Prepare survey data and sketches in an agreed format for transfer/ handover of information.
• Control subcontractor’s surveyor’s daily work and data.
5.0 RESOURCES
5.1 WORKFORCE
• Project Manager
• Construction Manager
• Environmental Engineer
• HSE Officer
• QA/QC Engineer
• Foreman
• Electricians
• Mechanics
• Operators
• Riggers
• Helpers
• Welders
document.
When considering the Bored Pile Construction, consideration has been given to the associated hazards and
risks and ensuring that all staff receive the requisite training.
All Staff and workers wear the following minimum Project PPE requirements:
• Hard hat (mandatory);
• Steel Toed Safety boots (mandatory);
• Safety glasses (Clear or dark, as required);
• Hi-Viz vest (mandatory);
• Coveralls (mandatory for labour trades);
• Gloves (for all manual handling activities).
6.3 ENVIRONMENT
Environmental Management measures and activities are to be implemented in accordance with the Project HSE
Plan.
The casing is of sufficient strength to withstand handling, driving, extracting stresses, concrete pressures,
surrounding earth and fluid pressure. A sufficient number of casings are provided to each pile diameter, in
order to concrete more than one pile at the same time. The casing is installed by using crane and vibrator or
using drilling rig. The casing is rotated into the ground in stages and simultaneously the auger inside the casing
drill as well but not more the casing depth in order not to destabilize the soil below.
A survey checks during casing installation of frequent spirit level measurement by the qualified riggers in two
perpendicular directions to ensure that the position of casing is within the tolerances allowed. This is to ensure
that the position of casing is within the allowed tolerance limit as per project specifications. Same procedure
applies continuously until the full length of casing installed.
After installing the casing, a survey check will be carried out by the Supervision Team; the casing centre will be
checked and verified if in compliance with the tolerances as per project specification.
6.5.4 TOLERANCES
Prior to boring the Contractor shall check the casing position for each pile during and immediately after
placing the casing and agree it with the Engineer. All piles shall be constructed having the pile diameter not less
than the minimum specified diameter.
A. Setting out of the main grid lines shall be carried out by the Contractor. The installation of piles at
plan positions as required by the Engineer shall be accurate to 75 mm as measured at cut-off level, in
any direction.
B. Pile commencement level shall be at sufficient dimension above the specified cut-off level so that,
after trimming, a sound concrete connection with the pile can be made.
C. The maximum permitted deviation of the finished pile from the vertical is 1 in 75, as measured at
cut off level.
D. Forcible corrections to concrete piles to overcome errors of position or alignment shall not be
made.
The reinforcing cage is fixed using templates required to obtain the correct spacing and support shape. The
reinforced cages are provided in manageable lengths to avoid distortion of cages during lifting. To avoid the
deformation of cage and ensure safe lifting, the inner rings are welded on the longitudinal rebar. The spacers
are to be fixed on the spiral of the cage as per the approved drawing.
Once the drilling is completed and the designed pile toe is reached the following details are checked and
witnessed by the Engineer:
• Pile Toe
6.5.7 Disposal of Excavated Spoil
The spoil produced by drilling of pile borehole is continuously removed from the pile location using a wheel
loader and stock piled on the site. The spoil is disposed off as quickly as possible to approved offsite dump
location by using dumpers and shovel loader in such a manner that spillage and annoyance are minimized.
6.5.8 Reinforcement
All steel reinforcement shall conform to the requirements of the Specifications for Type 500B to BS
4449 or A615M - 16, unless otherwise shown on the Drawings or specified by the Engineer. The
frequency of sampling and the method of quality control shall be in accordance with BS 4449.
If same steel from a single factory is delivered and which is already tested than random sampling
shall be done with minimum one set of samples from any dia/all diameters as per reinforcement
drawings. Test shall be conducted for minimum 03 samples. Samples shall be selected by engineer
upon delivery. If sample are not taken from the same bars or dia then they can taken from other
delivery or diameters due to same source.
All reinforcement bars shall be free from detrimental dirt, mill scale, loose rust, paint, grease, oil or
other foreign substance, fins, or tears. There shall be no evidence of visual flaws in the bars, test
specimens or on the sheared ends of the bars. All reinforcement shall be cleaned before use to
remove rust, oil, grease, salt and other deleterious materials. Where pitting has occurred the bars
shall be rejected. Blasting may be required when the reinforcement is in position, or partially cast in.
Partially set concrete adhering to exposed bars during concreting operations shall be removed. The
minimum thickness of concrete cover to reinforcement shall be as per below schedule
In order to avoid deformations of the rebar cage during lifting, the welds are used as construction aids with
minimum length of 50 mm using low hydrogen electrodes by welders subject to the approval of Project
Manager (Steel must be weld-able steel & welding process is in accordance with project specification). To keep
the steel cage in place and at the correct levels during lowering, the cage top level (in line as per the IFC
drawing) is monitored using measuring tape and is measured against top of casing to determine the level.
During fabrication of the pile reinforcement cages, PVC sleeve pipes of appropriate diameter are capped on the
rebar extending above the cut-off level to prevent concrete from adhering to the steel bars. The clear concrete
cover to all the reinforcement is maintained as per approved IFC drawings and spacing rings securely fixed to
the reinforcement are used at all times to maintain this cover.
Hook No 1 Hook No 2
Crane will start lifting the steel cage simultaneously upward with hook No.1 & Hook No. 2 as per the sketch
below approx. 1.0m above ground level.
Hook No 1 Hook No 2
Hook No. 1 will start lifting the steel cage upward until the position of steel cage will be at the approx. angle of
35°, while Hook No. 2 will guide the steel cage to a proper inclination. The helper/rigger should hold the nylon
rope tight enough to minimize the movement of steel cage.
Crane will continue lifting the steel cage simultaneously upward with hook No.1. & the same Hook No. 2 will guide
the inclination position of the steel cage until the position will be at the approx. 80° angle. The helper/rigger
should hold the nylon rope tight enough to minimize the movement of steel cage as per the sketch below.
Hook No 1
Hook No 2
Crane continues lifting the steel cage with the same procedures above until the position of steel cage will be in
vertical position. While the steel cage is in the vertical position, the crane start swings the steel cage & move to
the pile location for steel cage installation.
Hook No 1
Hook No 2
For steel cage installation, while lowering into the pile the sling rope connected to Hook No.2 will detach one by
one & the steel cage will continue lowering up to the design level.
The concrete is poured, without interruption to prevent hardening of the previously placed batch, by using a
concrete pump and a clean watertight tremie pipe. The tremie pipe is made up of sections (joints provided with
seals) with sufficient length to reach the toe of the pile. The size of tremie pipe is not less than 150mm as per
specification. The tremie pipe is inserted at the centre of the pile to reach up to the toe.
The top of the tremie pipe is connected to the funnel/hopper. The concrete is delivered directly from the
pump/truck to the funnel.
As the concreting starts, the tremie pipe is lowered at approx. 200mm above the bottom of drilling. While
concreting the length of the tremie pipe is reduced if necessary but at least 3.0 m length of tremie pipe is
maintained full time into the concrete. During the concreting the level of the concrete within the pile is monitored
by use of an end weight tape measure. No spoil or any other foreign materials should contaminate the
concrete.
A sufficient quantity of concrete is maintained within the tremie to ensure that the ground water or drilling fluid
pressure does not exceed from the pressure of concrete. The tremie connections are checked properly and to
avoid any seepage or leakage of concrete to the tremie pipe, a tape is provided around the connection joints of
the tremie. Any damage of O-ring & Seal rope is changed immediately. A second (backup) tremie pipe is
available in case of any damage or repair of the 1st tremie pipe. In order to have water tight joints at junction of
two tremie pipes, an O-ring and steel wire rope (seal Rope) are used as shown in the figure 3.
Figure 2- Tremie System
In case of deep cut-off level, the concreted pile length above cut-off level is determined as per the method given
in I.C.E. specification. The following formula of pile head casting level tolerance is normally used to determine
the casting tolerance above cut off level as per I.C.E Specifications Section 3.5.3.
Where,
In normal practice, casting level of piles is approximately 1.5 to 2.0 above cut-off level.
.
Borehole Borehole
After the completion of concreting, the temporary casing is withdrawn by drilling rig/ vibrator. When the casing
is being extracted, a sufficient quantity of concrete is maintained within it to ensure that pressure from external
water or soil is exceeded and that the pile is neither reduced in section nor contaminated. The casing is lifted
about 1m to 1.5m to add extra concrete. During the course of casing extraction, the concrete level within a
temporary casing is topped up if required. Following points should be considered during casing extraction
A. Temporary casings shall be extracted while the concrete within them remains sufficiently workable
to ensure that the concrete is not lifted. During extraction the motion of the casing shall be maintained
in an axial direction relative to the pile.
B. When the casing is being extracted, a sufficient quantity of concrete shall be maintained within it to
ensure that pressure from external water, drilling fluid or soil is exceeded and that the pile is neither
reduced in section nor contaminated.
C. The concrete level within a temporary casing shall be topped up where necessary during the
course of casing extraction in such a way that the base of the casing is always below the concrete
surface until the casting of the pile has been completed.
D. Piles shall be cast to a level above the specified cut-off so that, after trimming, a sound concrete
connection with the pile can be made.
E. Excavation around temporary casing to assist in their extraction will not be permitted.
Working Platform Level
Cross-hole sonic logging shall be carried out on a minimum of 10% of the total number of piles.
Number of tests required, and number of cross test combinations should be decided based diameter
of piles and should be agreed by Engineer. The piles to be tested shall be to the approval of the
Engineer. Upon satisfactory receipt of results the sonic tubes are to be backfilled with an equivalent
strength grout to that of the concrete.
The hammer and all other equipment used shall be conforming to thestandard. The hammer shall be
capable of delivering an impact force sufficient to mobilize the equivalent specified dynamic test load
without damaging the pile.
The Contractor is to demonstrate and provide calculations to prove the hammer proposed has
sufficient weight to mobilize the toe of the pile, the pile having to move 2.5mm per blow. Either a
wave equation analysis based on the GRLWEAP program or drivability study if it is not possible to
prove by calculation.
The preparation of the pile head shall involve the trimming of the head, all poor concrete, cleaning
and building up the pile using higher grade concrete. The impact surface shall be flat and at right
angles to the pile axis.
Pile reinforcement is to be the full length of the pile, including where the pile head may have to be
raised.
The interpretation of the tests shall be carried out by competent and experience persons to be
approved by the Engineer. The Contractor shall give all available details of the ground conditions, pile
dimensions and construction method to the specialist firm in order to facilitate interpretation
of the tests.
Test results shall be provided to the Engineer within agreed time and with all necessary details as per
project specifications.
9.0 REFERENCES
The following references should be read / accessed and /or used in conjunction with this Method Statement:
Health, Safety & Environmental Plan – Project
Hazard Identification & Risk Assessment
Procedure
Permit To Work Procedure
Lifting Operations Procedure
Excavation Safety Procedure
START Checklist
Project Quality Plan (PQP)
CONSULTANT REFERENCE DRAWINGS
GENERAL NOTES PILING
PILE LAYOUT MASTER PLAN
PILE LAYOUT
SCHEDULE OF PILES
SHOP DRAWINGS
OVERALL PILE LAYOUT
PILES SHOP DRAWINGS-ALL AREAS
CONSTRUCTION PLANS