Professional Documents
Culture Documents
GPCS369 - Electronic Drain Traps
GPCS369 - Electronic Drain Traps
■ Simple maintenance
requirements
BEST PRACTICE
PROGRAMME
ELECTRONIC CONDENSATE DRAIN TRAPS
BACKGROUND
Receiver No.12
6 bar Receiver No.6 throughout the compressed air distribution system
nominal
Compressor Foundry
B - 706 scfm low (see Fig 1), saving energy and giving an average
pressure air payback time on total investment of 14 months.
Receiver No.3
Compressor
A - 632 scfm CONDENSATE FORMATION AND COLLECTION
In compressed air systems where the air is treated by
filtration and refrigerated drying, condensate forms in
the air receivers and distribution piping network
L.P. Compressed air to when the air temperature falls below the delivered air
Foundry and No.1 shop
dewpoint. With oil injected compressors, such as
Receiver No.18 those at GKN, the condensate contains water and oil.
Compressor 7 bar nominal Foundry Air quality is important for most plant and processes
C - 631 scfm high
pressure air utilising compressed air. The condensate must be
removed as poor air quality, due to entrained
condensate, may lead to:
Receiver No.28 Receiver No.2
■ damage to plant;
Monitoring Shop numbers
point
Compressor 6 bar nominal 2 and 5 ■ plant failure;
D - 631 scfm
compressed air
New ECDT ■ pressure drop and other systems problems.
BACKGROUND
GKN Sheepbridge Stokes Ltd, Chesterfield, is a large
industrial company engaged principally in the
casting and machining of cylinder liners for
automotive, bus, truck, marine industrial and
locomotive applications.
consumption (kW/scfm)
The specific power consumption of each system 0.35
Specific power
was established by relating each compressor’s 0.3
0.25
electrical power consumption reading to the 0.2
measured system air demand at that time (Fig 3). 0.15
0.1
0.05
Leakage Measurement and Annual Savings 0
The compressed air leakage from each of the Foundry Foundry Shop numbers
low pressure high pressure 2 and 5
compressed air system’s drain traps (Fig 4) was compressors compressor compressor
measured using a test pipe and turbine meter. The
Fig 3 Specific power consumption of the compressor plant prior to installation of ECDTs
annual cost of leakage from each drain trap was
determined, using the specific power consumption.
From this, the annual energy savings resulting
25
from the installation of ECDTs was calculated.
This is shown in Fig 5, together with the cost of 20
Leakage (scfm)
hours, the physical size of the leak, and the cost of Reference number of receiver to which ECDT fitted
electricity (Fig 6).
Fig 4 Leakage from individual receiver drain valves
Compressor Oversizing
Fig 3 shows the particularly poor efficiency of the
1,100
compressor serving the machinery and finishing 1000 Installed cost of ECDT
900
shops. This was due to the machine being too Annual saving
Cost/saving (£)
800
large for the small system air demand. It therefore 700
600
operated inefficiently for long periods ‘off load’,
500
resulting in a disproportionately high cost of 400
300
leakage from the system. Energy savings made
200
from fitting ECDTs were therefore higher than 100
0
would be expected on a system with a more typical
12 6 3 18 28 2
specific power consumption. As a result of this
Reference number of receiver to which ECDT fitted
survey, GKN intend to replace the compressor with
a more appropriately sized machine. Fig 5 Installed costs and annual savings from the installation of ECDTs
25
Payback period (months)
20
15
10
0
12 6 3 18 28 2
Reference number of receiver to which ECDT fitted
Ian Mottishaw
Site Facilities Manager, GKN Sheepbridge Stokes Ltd
This project was monitored independently by Cadogan Consultants. Tel: 0141 270 7060.
The equipment was supplied by Automated Industrial Services Ltd. Tel: 01484 719921.
There may be other suppliers of similar energy efficient equipment on the market. Please consult your
supplier directories or ETSU who may be able to provide you with more details.
ELECTRONIC CONDENSATE DRAIN TRAPS
CONCLUSIONS
The Department of the Environment, Transport and the Regions’ Energy Efficiency Best Energy Consumption Guides: compare energy use in
Practice Programme provides impartial, authoritative information on energy efficiency techniques specific processes, operations, plant and building types.
and technologies in industry, transport and buildings. The information is disseminated through
Good Practice: promotes proven energy efficient techniques
publications, videos and software, together with seminars, workshops and other events. through Guides and Case Studies.
Publications within the Best Practice Programme are shown opposite.
New Practice: monitors first commercial applications of new
energy efficiency measures.
Further information
Future Practice: reports on joint R & D ventures into new
energy efficiency measures.
For buildings-related topics please contact: For industrial and transport topics please contact:
Enquiries Bureau Energy Efficiency Enquiries Bureau General Information: describes concepts and approaches
BRECSU ETSU yet to be fully established as good practice.
Building Research Establishment Harwell, Didcot, Oxfordshire,
Fuel Efficiency Booklets: give detailed information on
Garston, Watford, WD2 7JR OX11 0RA specific technologies and techniques.
Tel 01923 664258 Tel 01235 436747
Fax 01923 664787 Fax 01235 433066 Energy Efficiency in Buildings: helps new energy managers
E-mail brecsuenq@bre.co.uk E-mail etsuenq@aeat.co.uk understand the use and costs of heating, lighting etc.
© CROWN COPYRIGHT FIRST PRINTED APRIL 1998
REPRINTED JULY 1999