Professional Documents
Culture Documents
BoQ Floc-Sed-Filtermodel 2021.07.03
BoQ Floc-Sed-Filtermodel 2021.07.03
Amount (US
Bill No Description
DOLLARS)
1 #REF! #REF!
6 #REF! #REF!
7 #REF! #REF!
9 #REF! #REF!
Earth Works of the Receiving Well & Mixing Tank including Site clearance,
2.1 Excavation, Disposal Soil, Compacting Soil and all contingencies related to Earth LS 1 4,586.40 4,096.13 8,682.53
Works
2.1.1 Excavate and carting away of excavated material m3 215.14 0.00 0.00 6.50 1,398.41 1,398.41
2.1.2 Disposal Soil m3 215.14 0.00 0.00 2.50 537.85 537.85
2.1.3 Backfilling m3 266.67 16.00 4,266.72 7.50 2,000.03 6,266.75
2.1.4 Crushed stone m3 13.32 24.00 319.68 12.00 159.84 479.52
Construction of the Foundation slab of Receiving Well and Mixing Tank complete
2.3 and including lean concrete, concrete pouring, curing and all contingencies related LS 1 6,094.93 2,036.18 8,131.11
to construction of
2.3.1 Lean Concrete C18 m3 6.66 86.00 572.76 28.00 186.48 759.24
2.3.2 Formwork m2 2.89 14.00 40.46 12.00 34.68 75.14
2.3.3 Concrete to base slab and sump C37 cube m3 31.80 95.00 3,021.00 28.00 890.40 3,911.40
2.3.4 Formwork m2 14.25 14.00 199.50 12.00 171.00 370.50
2.3.5 Reinforcement bar kg 2,218.99 0.88 1,952.71 0.28 621.32 2,574.03 140kg/m3
2.3.6 Concrete curing m3 31.80 2.50 79.50 2.00 63.60 143.10
2.3.8 Provision for water-stop,w=200mm m 22.90 10.00 229.00 3.00 68.70 297.70 Outside wall
Construction of the Wall of Receiving Well and Mixing Tank complete and
2.4 LS 1 14,558.86 7,551.00 22,109.86
including concrete pouring, curing and all contingencies related to construction of
2.4.1 Concrete C37 cube m3 65.53 95.00 6,225.35 28.00 1,834.84 8,060.19
2.4.2 Formwork m2 312.04 14.00 4,368.56 12.00 3,744.48 8,113.04
2.4.3 Reinforcement bar kg 3,787.57 0.88 3,333.07 0.28 1,060.52 4,393.59 160kg/m3
2.4.4 Concrete curing m3 65.53 2.50 163.83 2.00 131.06 294.89
2.4.5 Scaffold m2 312.04 1.50 468.06 2.50 780.10 1,248.16
Construction of the slab of Receiving Well and Mixing Tank complete and
2.5 LS 1 1,775.46 940.83 2,716.29
including concrete pouring, curing and all contingencies related to construction
2.5.1 Concrete slab C37 cube m3 3.17 95.00 301.15 28.00 88.76 389.91
2.5.2 Formwork m2 22.48 14.00 314.72 12.00 269.76 584.48
2.5.3 Reinforcement bar kg 1,132.13 0.88 996.28 0.28 317.00 1,313.27 140kg/m3
2.5.4 Concrete curing m3 3.17 2.50 7.93 2.00 6.34 14.27
2.5.6 Support m3 103.59 1.50 155.39 2.50 258.98 414.36
Construction of the Stair of Receiving Well and Mixing Tank complete and
2.6 LS 1 1,095.39 597.00 1,692.40
including concrete pouring, curing and all contingencies related to construction
2.6.1 Concrete stair C37 cube m3 3.93 95.00 373.35 28.00 110.04 483.39
2.6.2 Formwork m2 26.83 14.00 375.62 12.00 321.96 697.58
2.6.3 Reinforcement bar kg 340.33 0.88 299.49 0.28 95.29 394.78 140kg/m3
2.6.4 Concrete curing m3 3.93 2.50 9.83 2.00 7.86 17.69
2.6.5 Support m3 24.74 1.50 37.11 2.50 61.85 98.96
Construction of the Internal Wall of Receiving Well and Mixing Tank complete and
2.7 LS 1 15,487.55 6,598.43 22,085.97 `
including concrete pouring, curing and all contingencies related to construction
2.7.1 Concrete Internal Wall 200mm thk. C37 cube m3 15.62 95.00 1,483.90 28.00 437.36 1,921.26
2.7.2 Formwork m2 122.62 14.00 1,716.68 12.00 1,471.44 3,188.12
2.7.3 Reinforcement bar kg 5,667.46 0.88 4,987.36 0.28 1,586.89 6,574.25
2.7.4 Concrete curing m3 15.62 2.50 39.05 2.00 31.24 70.29
2.7.5 Scaffold m2 122.62 1.50 183.93 2.50 306.55 490.48
2.7.6 PVC hole ф100 L=150 hole 64.00 4.00 256.00 1.00 64.00 320.00
2.7.7 Provision for water-stop,w=200mm m 27.30 10.00 273.00 3.00 81.90 354.90
2.7.8 Waterproof m2 523.81 12.50 6,547.63 5.00 2,619.05 9,166.68
Civil works for installation of metal works (door, windows, ladders, platform,
2.8 LS 1 0.00 0.00 0.00
handrails, manhole cover, etc.)
2.8.1 Contingencies 10% L.s
Date: February 22,2014
KCC Quotation
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost Amount Remarks
Unit Rate Amount Unit Rate Amount
(US$) (US$) (US$) (US$)
Earth Works of the Receiving Well & Mixing Tank including Site clearance,
3.1 Excavation, Disposal Soil, Compacting Soil and all contingencies related to Earth LS 1 42,193.12 43,578.86 85,771.98
Works
3.1.1 Excavate and carting away of excavated material m3 2,637.36 0.00 0.00 6.50 17,142.84 17,142.84
3.1.2 Disposal Soil m3 2,637.36 0.00 0.00 2.50 6,593.40 6,593.40
3.1.3 Backfilling m3 2,507.89 16.00 40,126.24 7.50 18,809.18 58,935.42
3.1.4 Crushed stone m3 86.12 24.00 2,066.88 12.00 1,033.44 3,100.32
3.2.1 Lean Concrete C18 m3 43.06 86.00 3,703.16 28.00 1,205.68 4,908.84
3.2.2 Formwork m2 3.71 14.00 51.94 12.00 44.52 96.46
3.2.3 Concrete base slab C37 cube m3 17,907.80 95.00 1,701,241.00 28.00 501,418.40 2,202,659.40
3.2.4 Formwork m2 18.35 14.00 256.90 12.00 220.20 477.10
3.2.5 Reinforcement bar kg 13,175.92 0.88 11,594.81 0.28 3,689.26 15,284.06
3.2.6 Concrete curing m3 17,907.80 2.50 44,769.50 2.00 35,815.60 80,585.10
Construction of Flocculation External Wall including concrete pouring, curing and
3.3 LS 1 305,080.82 157,422.41 462,503.23
all contingencies related to construction .
3.3.1 Concrete External wall and internal wall C37 cube m3 655.48 95.00 62,270.60 28.00 18,353.44 80,624.04
3.3.2 Formwork m2 5,521.42 14.00 77,299.88 12.00 66,257.04 143,556.92
3.3.3 Reinforcement bar kg 62,704.97 0.88 55,180.38 0.28 17,557.39 72,737.77
3.3.4 Concrete curing m3 655.48 2.50 1,638.70 2.00 1,310.96 2,949.66
3.3.5 Provision for water-stop,w=200mm m 208.00 10.00 2,080.00 3.00 624.00 2,704.00
3.3.6 Scaffold m2 5,521.42 1.50 8,282.13 2.50 13,803.55 22,085.68
3.3.7 PVC hole ф100 L=250 ea 672.00 5.00 3,360.00 1.25 840.00 4,200.00
3.3.8 Concrete Slab C37 cube m3 28.46 95.00 2,703.70 28.00 796.88 3,500.58
3.3.9 Formwork m2 129.60 14.00 1,814.40 12.00 1,555.20 3,369.60
3.3.10 Reinforcement bar kg 2,445.74 0.88 2,152.25 0.28 684.81 2,837.06
3.3.11 Concrete curing m3 28.46 2.50 71.15 2.00 56.92 128.07
3.3.12 Support m3 543.80 1.50 815.70 2.50 1,359.50 2,175.20
3.3.13 Concrete C24 Stair m3 6.22 90.00 559.80 28.00 174.16 733.96
3.3.14 Formwork m2 19.35 14.00 270.90 12.00 232.20 503.10
3.3.15 Reinforcement bar kg 266.70 0.88 234.70 0.28 74.68 309.37
3.3.16 Concrete curing m3 6.22 2.50 15.55 2.00 12.44 27.99
3.3.17 Support m3 28.95 1.50 43.43 2.50 72.38 115.80
3.3.18 Waterproof m2 6,108.43 12.50 76,355.38 5.00 30,542.15 106,897.53
3.3.19 Plain Concrete C18 m3 40.37 86.00 3,471.82 28.00 1,130.36 4,602.18
3.3.20 Stop Gete Embaddet Fram m2 14.92 433.00 6,460.36 133.00 1,984.36 8,444.72
Construction of the Foundation slab of Pit 3200 x 11200 complete and including
3.4 lean concrete, concrete pouring, curing and all contingencies related to construction LS 1 27,107.60 12,683.78 39,791.38
of
3.4.1 Lean Concrete C18 m3 4.66 86.00 400.76 28.00 130.48 531.24
3.4.2 Formwork m2 3.14 14.00 43.96 12.00 37.68 81.64
3.4.3 Concrete base slab C37 cube m3 22.52 95.00 2,139.40 28.00 630.56 2,769.96
3.4.4 Formwork m2 13.22 14.00 185.08 12.00 158.64 343.72
3.4.5 Reinforcement bar kg 2,523.29 0.88 2,220.50 0.28 706.52 2,927.02
3.4.6 Concrete wall C37 cube m3 60.51 95.00 5,748.45 28.00 1,694.28 7,442.73
3.4.7 Formwork m2 298.54 14.00 4,179.56 12.00 3,582.48 7,762.04
3.4.8 Reinforcement bar kg 4,121.51 0.88 3,626.93 0.28 1,154.02 4,780.95
3.4.9 Concrete slab C37 cube m3 5.83 95.00 553.85 28.00 163.24 717.09
3.4.10 Formwork m2 25.56 14.00 357.84 12.00 306.72 664.56
3.4.11 Reinforcement bar kg 1,275.75 0.88 1,122.66 0.28 357.21 1,479.87
3.4.12 Concrete stair C37 cube m3 2.99 95.00 284.05 28.00 83.72 367.77
3.4.13 Formwork m2 24.50 14.00 343.00 12.00 294.00 637.00
3.4.14 Reinforcement bar kg 270.70 0.88 238.22 0.28 75.80 314.01
3.4.15 Concrete curing m3 91.85 2.50 229.63 2.00 183.70 413.33
3.4.16 Scaffold m2 298.54 1.50 447.81 2.50 746.35 1,194.16
3.4.17 Support m3 202.11 1.50 303.17 2.50 505.28 808.44
Waterproof m2 374.62 12.50 4,682.75 5.00 1,873.10 6,555.85
Construction of the Foundation slab of Pit 1400 x 2800 complete and including lean
3.5 LS 1 3,600.99 1,584.02 5,185.01
concrete, concrete pouring, curing and all contingencies related to construction of
3.5.1 Lean Concrete C18 m3 0.61 86.00 52.46 28.00 17.08 69.54
3.5.2 Formwork m2 0.68 14.00 9.52 12.00 8.16 17.68
3.5.3 Concrete base slab C37 cube m3 2.67 95.00 253.65 28.00 74.76 328.41
3.5.4 Formwork m2 3.10 14.00 43.40 12.00 37.20 80.60
3.5.5 Reinforcement bar kg 598.85 0.88 526.99 0.28 167.68 694.67
3.5.6 Concrete wall C37 cube m3 9.27 95.00 880.65 28.00 259.56 1,140.21
3.5.7 Formwork m2 44.16 14.00 618.24 12.00 529.92 1,148.16
3.5.8 Reinforcement bar kg 367.43 0.88 323.34 0.28 102.88 426.22
3.5.9 Concrete slab C37 cube m3 0.25 95.00 23.75 28.00 7.00 30.75
3.5.10 Formwork m2 1.20 14.00 16.80 12.00 14.40 31.20
3.5.11 Reinforcement bar kg 212.95 0.88 187.39 0.28 59.63 247.02
3.5.12 Concrete curing m3 12.19 2.50 30.48 2.00 24.38 54.86
3.5.13 Scaffold m2 9.27 1.50 13.91 2.50 23.18 37.08
3.5.14 Support m3 5.28 1.50 7.92 2.50 13.20 21.12
3.5.15 Waterproof m2 49.00 12.50 612.50 5.00 245.00 857.50
Construction of the Foundation slab of Pit 45400 x 2800 complete and including
3.6 lean concrete, concrete pouring, curing and all contingencies related to construction LS 1 56,236.24 24,119.41 80,355.64
of
3.6.1 Lean Concrete C18 m3 14.68 86.00 1,262.48 28.00 411.04 1,673.52
3.6.2 Formwork m2 4.50 14.00 63.00 12.00 54.00 117.00
3.6.3 Concrete base slab C37 cube m3 70.88 95.00 6,733.60 28.00 1,984.64 8,718.24
3.6.4 Formwork m2 22.50 14.00 315.00 12.00 270.00 585.00
3.6.5 Reinforcement bar kg 7,092.72 0.88 6,241.59 0.28 1,985.96 8,227.55
3.6.6 Concrete wall C37 cube m3 85.81 95.00 8,151.95 28.00 2,402.68 10,554.63
3.6.7 Formwork m2 408.60 14.00 5,720.40 12.00 4,903.20 10,623.60
3.6.8 Reinforcement bar kg 4,454.73 0.88 3,920.17 0.28 1,247.33 5,167.49
3.6.9 Concrete slab C37 cube m3 66.74 95.00 6,340.30 28.00 1,868.72 8,209.02
3.6.10 Formwork m2 127.12 14.00 1,779.68 12.00 1,525.44 3,305.12
3.6.11 Reinforcement bar kg 5,000.50 0.88 4,400.44 0.28 1,400.14 5,800.58
3.6.12 Concrete curing m3 223.43 2.50 558.58 2.00 446.86 1,005.44
3.6.13 Scaffold m2 408.60 1.50 612.90 2.50 1,021.50 1,634.40
3.6.14 Support m3 286.02 1.50 429.03 2.50 715.05 1,144.08
3.6.15 Waterproof m2 776.57 12.50 9,707.13 5.00 3,882.85 13,589.98
Civil works for installation of metal works (door, windows, ladders, platform,
3.7 LS 1 37,953.00 11,632.00 49,585.00
handrails, manhole cover, etc.)
3.7.1 Double Door (D2)Aluminium (1400x2200) set 1.00 414.00 462.00 114.00 114.00 576.00
3.7.2 Fixed frame Window (W1: 1040x1400) set 3.00 167.00 501.00 60.00 180.00 681.00
3.7.3 Grating Cover G1 : 8.76m2 set 1.00 3,793.00 3,793.00 1,165.00 1,165.00 4,958.00 AISI 304
3.7.4 Grating Cover G2 : 12.98m2 set 1.00 5,620.00 5,620.00 1,726.00 1,726.00 7,346.00 AISI 304
3.7.5 Grating Cover G3 : 8.76m2 set 1.00 3,793.00 3,793.00 1,165.00 1,165.00 4,958.00 AISI 304
3.7.6 Grating Cover G4 : 0.14m2 set 14.00 61.00 854.00 19.00 266.00 1,120.00 AISI 304
3.7.7 Grating Cover G5 : 1.15m2 set 2.00 498.00 996.00 153.00 306.00 1,302.00 AISI 304
3.7.8 Grating Cover G12 : 4.12m2 set 12.00 1,784.00 21,408.00 548.00 6,576.00 27,984.00 AISI 304
3.7.9 Ladder L1 :4270mm set 1.00 175.00 175.00 26.00 26.00 201.00 AISI 304
3.7.10 Manhole Cover 900x900 set 1.00 351.00 351.00 108.00 108.00 459.00
1
2
3
m2
150 462
37 113.96
Date: February 22,2014
KCC Quotation
Construction Costs
Item N° Description Unit Quantity Material Cost
Unit Rate
(US$)
Water Treatment Facility
4 Sedimentation Basin
Earth Works of the Sedimentation Basin including Site clearance, Excavation,
4.1 LS 1
Disposal Soil, Compacting Soil and all contingencies related to Earth Works
4.1.1 Excavate and carting away of excavated material m3 4,669.69 0.00
4.1.2 Disposal Soil m3 4,669.69 0.00
4.1.3 Backfilling m3 3,825.67 16.00
4.1.4 Crushed stone bedding m3 390.42 24.00
Construction of the Sedimentation Basin Base slab complete and including lean
4.2 LS 1
concrete, concrete pouring, curing and all contingencies related to construction
4.2.1 Lean Concrete C18 m3 195.21 86.00
4.2.2 Formwork m2 12.69 14.00
4.2.3 Concrete base slab and sump C37 cube m3 972.83 95.00
4.2.4 Formwork m2 61.20 14.00
4.2.5 Reinforcement bar kg 60,790.38 0.88
4.2.6 Concrete curing m3 972.83 2.50
4.2.7 Provision for water-stop,w=300mm m 45.40 24.50
Construction of Sedimentation Basin External Wall including concrete pouring,
4.3 LS 1
curing and all contingencies related to construction .
4.3.1 Concrete External wall and internal wall C37 cube m3 954.64 95.00
4.3.2 Formwork m2 5,208.96 14.00
4.3.3 Reinforcement bar kg 104,363.11 0.88
4.3.4 Concrete curing m3 954.64 2.50
4.3.5 Provision for water-stop,w=300mm m 125 24.50
4.3.6 Scaffold m2 5,208.96 1.50
4.3.7 PVC hole ф100 L=300 ea 1,056.00 6.00
4.3.8 Concrete Slab C37 cube m3 36.08 95.00
4.3.9 Formwork m2 293.96 14.00
4.3.10 Reinforcement bar kg 5,140.87 0.88
4.3.11 Concrete curing m3 36.08 2.50
4.3.12 Support m3 1,060.56 1.50
4.3.13 Concrete cubeU_Tran C37 cube m3 60.10 95.00
4.3.14 Formwork m2 665.47 14.00
4.3.15 Reinforcement bar kg 3,452.52 0.88
4.3.16 Concrete curing m3 60.10 2.50
4.3.17 Support m3 779.59 1.50
4.3.18 Waterproof m2 8,961.97 12.50
4.3.19 Plain Concrete C18 m3 345.39 86.00
Civil works for installation of metal works (door, windows, ladders, handrails,
4.6 LS 1
manhole cover, etc.)
4.6.1 Grating Cover G6 : 0.52m2 set 4.00 225.00
4.6.2 Grating Cover G7 : 0.30m2 set 20.00 130.00
4.6.3 Step iron (Steel Leder) L2 :3990mm set 12.00 164.00
4.6.4 Step iron (Steel Leder) L3 :3690mm set 12.00 151.00
Material Cost Labor Cost Amount Remarks
Amount Unit Rate Amount
(US$) (US$) (US$)
Earth Work
Earth Work
Earth Work
Gravel
Concrete
Concrete
Form
Re-Bar
Curing
WPW
Concrete
Form
Re-Bar
Curing
WPW
Scaffold
Concrete
Support
Form
Re-Bar
Concrete
Filter M.
Filter M.
Filter M.
Filter M.
Filter M.
WPW