Integrated Schedule For Upgradation of Online Corrosion Monitoring System - North Location - Rev-02Latest

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Construction Schedule for Upgradation of Online Corrosion Monitoring System - Qarn

Alam and Yibal


Activity ID Activity Name Original Start Finish December 2021 January 2022 February 2022 March 2022
Duration
12 19 26 02 09 16 23 30 06 13 20 27
Upgradation of Online Corrosion Monitoring System 63 15-Dec-21 28-Feb-22

Milestone 19 06-Feb-22 28-Feb-22

Construction completion 17 06-Feb-22 26-Feb-22


MQ100 Qarn Alam 28" QA to KM 83 - Construction completion 0 06-Feb-22 Qarn Alam 28" QA to KM 83 - Construction completion
MQ110 Qarn Alam Main pumping Station - Construction completion 0 16-Feb-22 Qarn Alam Main pumping Station - Constructio
MY120 Yibal Station -A / MLPS - Construction completion 0 26-Feb-22 Yibal Station -A / MLPS
Commissioning completion by Emerson vendor 17 08-Feb-22 28-Feb-22
EM120 Qarn Alam 28" QA to KM 83 - Commissioning completion by Emerson 0 08-Feb-22 Qarn Alam 28" QA to KM 83 - Commissioning completion by Em
EM130 Qarn Alam Main pumping Station - Commissioning completion by Emerson 0 19-Feb-22 Qarn Alam Main pumping Station - Com
EM140 Yibal Station -A / MLPS - Commissioning completion by Emerson 0 28-Feb-22 Yibal Station -A / ML
Procurement 13 15-Dec-21 30-Dec-21
P1010 Fencing Material Procurement initiated 0 15-Dec-21* Fencing Material Procurement initiated
P1020 Fencing material delivery to Site 0 30-Dec-21* Fencing material delivery to Site
General 0 10-Jan-22 10-Jan-22
GEN1000 Start of plot preparation works 0 10-Jan-22* Start of plot preparation works
Vendor Mobilization Required at site 28 25-Jan-22 27-Feb-22

Qarn Alam 28" QA to KM 83 11 25-Jan-22 07-Feb-22


QA1000 Emerson Vendor mobilization to QA Location 0 25-Jan-22 Emerson Vendor mobilization to QA Location
QA1010 OFO Vendor mobilization to QA location 0 29-Jan-22 OFO Vendor mobilization to QA location
QA1020 Emerson Vendor mobilization to Fahud for Commissioning at CCR 0 07-Feb-22 Emerson Vendor mobilization to Fahud for Commissioning at CCR
Qarn Alam Main pumping Station 11 05-Feb-22 17-Feb-22
QA1040 Emerson Vendor mobilization to QA Location 0 05-Feb-22 Emerson Vendor mobilization to QA Location
QA1030 OFO Vendor mobilization to QA location 0 08-Feb-22 OFO Vendor mobilization to QA location
QA1050 Emerson Vendor mobilization to Fahud for Commissioning at CCR 0 17-Feb-22 Emerson Vendor mobilization to Fahud for C
Yibal Station -A / MLPS 10 15-Feb-22 27-Feb-22
YB1070 Emerson Vendor mobilization to Yibal location 0 15-Feb-22 Emerson Vendor mobilization to Yibal location
YB1060 OFO Vendor mobilization to Yibal location 0 17-Feb-22 OFO Vendor mobilization to Yibal location
YB1080 Emerson Vendor mobilization to Fahud for Commissioning at CCR 0 27-Feb-22 Emerson Vendor mobil
Qarn Alam 28" QA to KM 83 26 10-Jan-22 08-Feb-22
A1180 Survey and Marking 1 10-Jan-22 10-Jan-22
A1190 Filling ,Grading ,levelling and Compaction -Plot Size 10X10 4 11-Jan-22 15-Jan-22
A1200 Excavation for Fence Post -20Nos-05x0.3 4 16-Jan-22 19-Jan-22
A1210 Pre casting for FSM Pole,Fence Post and Gate Post 7 16-Jan-22 23-Jan-22
A1220 Excavation for FSM Pole Mounted Foundation 2 20-Jan-22 22-Jan-22
A1230 Excavation for Earthing cable for Fence 6 20-Jan-22 26-Jan-22
A1240 Installation of Pre cast foundation after PCC for FSM Pole 2 23-Jan-22 24-Jan-22
A1250 Excavation for Instrument and Electrical Cable trench 5 23-Jan-22 27-Jan-22
A1280 Installation of Fence Post and Gate Post 2 24-Jan-22 25-Jan-22
A1260 Backfilling and compaction on FSM pole foundation 2 25-Jan-22 26-Jan-22
A1540 Emerson - Installation of FSM by Emerson vendor 1 25-Jan-22 25-Jan-22
A1300 Backfilling and compaction for Fence Post and Gate Post 4 26-Jan-22 30-Jan-22
A1270 Laying and Terminatio n of Earthin g Cable with Fence 4 27-Jan-22 31-Jan-22
A1290 Pre padding / inspection Completion 2 29-Jan-22 30-Jan-22
A1550 OFO - WIMAX and solor panel foundation/ panel installation/Data Cable laying 1 29-Jan-22 29-Jan-22
A1340 Fence Mesh and Gate Fixing 3 31-Jan-22 02-Feb-22

Date Revision Checked Approved


Actual Work Milestone  
16-Nov-21 Schedule -Rev-01
Remaining Work Summary Data Date -28-Nov-21
28-Nov-21 Schedule -Rev-02
Critical Remaining Work Page 1 of 3
Construction Schedule for Upgradation of Online Corrosion Monitoring System - Qarn
Alam and Yibal
Activity ID Activity Name Original Start Finish December 2021 January 2022 February 2022 March 2022
Duration
12 19 26 02 09 16 23 30 06 13 20 27
A1310 LV cable laying 2 31-Jan-22 01-Feb-22
A1320 Post Padding and Backfilling / Compaction 3 02-Feb-22 05-Feb-22
A1330 Glanding and Termination wit h Solar Panel 2 02-Feb-22 03-Feb-22
A1350 Construction and Final completion 1 06-Feb-22 06-Feb-22
A1560 Emerson - Integration testing and Final SAT Commg at Fahud CCR 2 07-Feb-22 08-Feb-22

Qarn Alam Main pumping Station 26 20-Jan-22 19-Feb-22


A1360 Survey and Marking 1 20-Jan-22 20-Jan-22
A1370 Filling ,Grading ,levelling and Compaction -Plot Size 10X10 4 22-Jan-22 25-Jan-22
A1380 Excavation for Fence Post -20Nos-05x0.3 4 26-Jan-22 30-Jan-22
A1390 Pre casting for FSM Pole,Fence Post and Gate Post 7 26-Jan-22 02-Feb-22
A1400 Excavation for FSM Pole Mounted Foundation 2 31-Jan-22 01-Feb-22
A1410 Excavation for Earthing cable for Fence 6 31-Jan-22 06-Feb-22
A1420 Installation of Pre cast foundation after PCC for FSM Pole 2 02-Feb-22 03-Feb-22
A1430 Excavation for Instrument and Electrical Cable trench 5 02-Feb-22 07-Feb-22
A1460 Installation of Fence Post and Gate Post 2 03-Feb-22 05-Feb-22
A1440 Backfilling and compaction on FSM pole foundation 2 05-Feb-22 06-Feb-22
A1580 Emerson - Installation of FSM by Emerson vendor 1 05-Feb-22 05-Feb-22
A1480 Backfilling and compaction for Fence Post and Gate Post 4 06-Feb-22 09-Feb-22
A1450 Laying and Terminatio n of Earthin g Cable with Fence 4 07-Feb-22 10-Feb-22
A1470 Pre padding / inspection Completion 2 08-Feb-22 09-Feb-22
A1570 OFO - WIMAX and solor panel foundation/ panel installation/Data Cable laying 1 08-Feb-22 08-Feb-22
A1520 Fence Mesh and Gate Fixing 3 10-Feb-22 13-Feb-22
A1490 LV cable laying 2 10-Feb-22 12-Feb-22
A1500 Post Padding and Backfilling / Compaction 3 13-Feb-22 15-Feb-22
A1510 Glanding and Termination wit h Solar Panel 2 13-Feb-22 14-Feb-22
A1530 Construction and Final completion 1 16-Feb-22 16-Feb-22
A1590 Emerson - Integration testing and Final SAT Commg at Fahud CCR 2 17-Feb-22 19-Feb-22
Yibal Station -A / MLPS 25 31-Jan-22 28-Feb-22
A1000 Survey and Marking 1 31-Jan-22 31-Jan-22
A1010 Filling ,Grading ,levelling and Compaction -Plot Size 10X10 4 01-Feb-22 05-Feb-22
A1020 Excavation for Fence Post -20Nos-05x0.3 4 06-Feb-22 09-Feb-22
A1030 Pre casting for FSM Pole,Fence Post and Gate Post 7 06-Feb-22 13-Feb-22
A1070 Excavation for FSM Pole Mounted Foundation 2 10-Feb-22 12-Feb-22
A1140 Excavation for Earthing cable for Fence 6 10-Feb-22 16-Feb-22
A1080 Installation of Pre cast foundation after PCC for FSM Pole 2 13-Feb-22 14-Feb-22
A1100 Excavation for Instrument and Electrical Cable trench 4 13-Feb-22 16-Feb-22
A1040 Installation of Fence Post and Gate Post 2 14-Feb-22 15-Feb-22
A1090 Backfilling and compaction on FSM pole foundation 2 15-Feb-22 16-Feb-22
A1610 Emerson - Installation of FSM by Emerson vendor 1 15-Feb-22 15-Feb-22
A1050 Backfilling and compaction for Fence Post and Gate Post 4 16-Feb-22 20-Feb-22
A1110 Pre padding / inspection Completion 2 17-Feb-22 19-Feb-22
A1150 Laying and Terminatio n of Earthin g Cable with Fence 4 17-Feb-22 21-Feb-22
A1600 OFO - WIMAX and solor panel foundation/ panel installation/Data Cable laying 1 17-Feb-22 17-Feb-22
A1120 LV cable laying 2 20-Feb-22 21-Feb-22
A1060 Fence Mesh and Gate Fixing 3 21-Feb-22 23-Feb-22
A1130 Post Padding and Backfilling / Compaction 3 22-Feb-22 24-Feb-22

Date Revision Checked Approved


Actual Work Milestone  
16-Nov-21 Schedule -Rev-01
Remaining Work Summary Data Date -28-Nov-21
28-Nov-21 Schedule -Rev-02
Critical Remaining Work Page 2 of 3
Construction Schedule for Upgradation of Online Corrosion Monitoring System - Qarn
Alam and Yibal
Activity ID Activity Name Original Start Finish December 2021 January 2022 February 2022 March 2022
Duration
12 19 26 02 09 16 23 30 06 13 20 27
A1160 Glanding and Termination wit h Solar Panel 2 22-Feb-22 23-Feb-22
A1170 Construction and Final completion 1 26-Feb-22 26-Feb-22
A1620 Emerson - Integration testing and Final SAT Commg at Fahud CCR 2 27-Feb-22 28-Feb-22
Construction/ Commissioning completion 0 28-Feb-22 28-Feb-22
COM130 All Location Construction / commissioning completion By AIP -PDC & Emesron 0 28-Feb-22 All Location Constru

Date Revision Checked Approved


Actual Work Milestone  
16-Nov-21 Schedule -Rev-01
Remaining Work Summary Data Date -28-Nov-21
28-Nov-21 Schedule -Rev-02
Critical Remaining Work Page 3 of 3