Download as pdf or txt
Download as pdf or txt
You are on page 1of 27

12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and

lation and Egress Shaft in India

     

Search …

Hydraulic Heave Failure Mitigation Approach for the construction of the


Deepest Metro Ventilation and Egress Shaft in India

Dr. Lakshmana Rao Mantri, Assistant General Manager (Designs), and Satya Narayan Kunwar,
Project Manager, AFCONS Infrastructure Ltd. , discuss the design and construction challenges of
constructing India’s deepest underground metro ventilation and escape shaft, how the issues
were addressed, and the preemptive and mitigation measures taken.

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-th… 1/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

East West Kolkata Metro has bagged national and international accolades by constructing India’s
first under water twin rail transportation tunnel including the deepest underground metro station
of India – the Howrah Metro station, surpassing the Hauz Khas station and Chawri Bazaar station
in Delhi. Kolkata East West Metro Project has also added another feather in its cap by
constructing India’s deepest metro ventilation cum egress shaft very close to the east bank of the
Hooghly River.

India’s deepest underground metro escape shaft, which is not less than an engineering marvel, is
now completed. The excavation depth of shaft is 43.5m, which means it can swallow a 14 storied
building inside it!

The shaft was constructed under very challenging hydro-geological conditions and at an equally
challenging location. This groundbreaking work has pushed design and construction engineering
boundaries and helped in achieving this extraordinary feat.

This article outlines the design and construction challenges and how they have been addressed.
It also outlines the spirit of challenging the status quo and shows how use of the very basic
engineering principles brought about a turnaround and helped us in carving an engineering
marvel. It also highlights the preemptive and mitigation measures that were taken, and which can
be replicated to deal with other unique challenges, though they may require completely different
solutions based on the specific requirements.

Critical Features

a) Precarious Location:
The location of this deepest shaft is very precarious from construction point of view. The shaft is
close to the mighty River Hooghly. Circular Railway track runs abutting to the shaft at west end
and the overly busy Strand Road at east end. The north and south ends of the shaft are occupied
by two bored tunnels, hardly 3.0 m away from the shaft. The ideal construction sequence would
have been to construct the shaft before tunnels are bored for avoiding impact of construction of
shaft on tunnels. But due to unavoidable circumstances, both the tunnels were done before shaft
construction was taken up (figure 1).

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-th… 2/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

At the west bank of the Hooghly River is the deepest Howrah metro station, whereas at the east
bank sits the deepest metro shaft. Moving ahead from Howrah station, tunnels took plunge into
the Hooghly River at 36m depth and achieved its deepest point, 39m below ground level, at
ventilation shaft. This being deepest point between two stations, the shaft accommodates sump
and pumping arrangement for tunnel drainage apart from housing tunnel ventilation and
emergency egress system. The vertical alignment of the tunnels below river has been kept
sufficiently below the riverbed considering safety and stability of the tunnel under all
circumstances (figure 2).

b) Innovative Shaft Construction sequence


After studying various options for construction of ventilation shaft, a very distinctive
methodology was adopted. Such methodology has been tried for the first time in India. A square
box of 13 m was decided to be constructed with the help of temporary diaphragm walls (1.0m
thick and 60m deep) which acted as “retaining structure” for supporting external soil during
excavation of the shaft. The shaft was then excavated 1.5m deep at a time (total 24 lifts) in a top-
down manner and then a circular lining wall, 500mm thick, was cast inscribing the square
diaphragm wall box. This sequence was repeated till excavation reached the final level and all the
lining walls were cast and finally base slab was completed. These lining walls acted as strut and
provided support to temporary diaphragm walls and hence no strutting was used for completing
excavation to the tune of 43.5m (figure 3).

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-th… 3/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

c) Unique Hydrogeology
The Shaft is very close to the East Bank of River Ganges and this area has undergone numerous
erratic alluvial subsoil depositions and river course transformation cycles. Apart from that, the city
of Kolkata dates back to more than 200 years making geology of this area very erratic and full of
surprises due to varied land usage over the time. Top 18m of the soil consisted of wooden logs,
boulders, traces of coal, steel pieces, bricks and foundations of the past, now non-existent,
buildings and installations. Such variations and hidden surprises posed enormous difficulty in
mapping the sub-soil strata and carrying out construction activities, especially in construction of
Diaphragm walls and piles (figure 4).

The top 18m of soil is very weak organic soft clay having N value of 5 or less. This layer is
underlain by a 17m thick fine silty sand, a water bearing strata, which is connected to Hooghly
River and has enormous source of water. Since this layer is followed by a 25m thick stiff clay
layer, this water bearing strata is, in fact, a confined aquifer running at high pressure. This
confined aquifer was considered a potential threat during excavation of shaft. Further the stiff
clay stratum is underlain by a coarse sand layer which too is expected to be connected with river
and extends much deeper (nearly 200m deep*). This water bearing sandy strata too is a confined
high-pressure aquifer, as this sandy stratum is followed by a stiff clay stratum (nearly 200m
deep*). The average pressure of this aquifer is 3 bars to 3.3 bars (based on site instrumentation
data) acting at the base of stiff clay layer. This huge pressure in lower confined aquifer was a big
threat for deep excavation and feared to result into hydraulic heave during excavation, as the
factor of safety against hydraulic heave was calculated to be lower than 1.0 much before reaching
final level of excavation.

Challenges Faced for Design and Construction

a) Design Challenges
Construction of India’s deepest Ventilation cum Egress Shaft under challenging geo-hydrological
condition was not less than creating an engineering marvel. It was, in fact, a unique kind of
challenge having no precedence in India or abroad. This situation demanded unique treatment of
the problem and pushed everyone to think beyond boundaries and seek innovative design and
construction solutions. Such construction sequence as constructing square D wall box and
carrying out top-down construction using circular lining wall inscribing the square box has been
adopted for the first time ever and there is no precedence anywhere. The construction sequence
uniquely fitted into our requirements and needed no additional equipment or resources. All the
available resources at the project were used to construct the shaft. Design of lining wall to
function as a strut for deep top-down construction was a unique idea and evaluation of its
equivalent strut function remained debated due to absence of a clear-cut guideline matching to
this situation. But the lining wall performed excellent strut function and kept diaphragm wall
deflection within permissible limit.

Since 500mm thick circular lining wall was inscribing a square box, the thickness of wall was

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-th… 4/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

varying, the corners of square box being the thickest. This situation was debated extensively as to
whether forces exerted from diaphragm walls onto the lining wall, how the forces from D wall will
be transferred to the lining wall, and how the forces, eventually, will be translated into
compressive force in the lining wall. Whether benefit of circularity could be derived or not.
Various ways of load transfer mechanisms from diaphragm walls onto the lining walls were
modelled and studied and reinforcement of lining wall was designed choosing most likely
situation and rejecting extreme conditions. Since design and construction sequence was quite
new, it was necessary to observe closely the structural behaviors and keep adjusting
reinforcement requirements, construction sequences and time cycles from time to time.
Observatory methods yielded excellent results and helped completing the construction of shaft.
The details pertaining to innovative structural design and observations made during construction
require a separate case study.

Mitigating challenge of Hydraulic Heave has also been treated very uniquely where strength of
soil has been utilized such that the soil cover has been treated as a 9m thick plug negotiating
hydraulic uplift through its weight and frictional resistance between shaft and diaphragm wall.
Accepted calculation methods ended assessing FOS equal to 0.38, much below the FOS assessed
using shaft-plug-friction approach (equal to 1.11). There was no guideline for assessing FOS
based on the concept as stated above. Due to its uniqueness and nontraditional way of
treatment, this approach too remained debated. Its successful implementation using extensive
pre-emptive and mitigation measures along with extensive instrumentation and monitoring will
surely go longways and shape the trend of design and construction strategies under similar
situations (figure 5).

b) Proximity to the Riverbank and Railway Track


Deep excavation close to riverbank and very close to a running railway track was very
challenging. It was very pertinent to adopt a construction methodology that allows minimal
deflection of diaphragm walls and thereby minimal settlement in the track. Construction of
circular lining wall in the stages provided excellent rigidity to the system. The maximum
deflection observed was 35 mm. The estimated deflection for D wall was 45 mm.

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-th… 5/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

c) Surprises Lay Buried Below


Many surprises lay hidden in the top 15m of soil in the form of wooden logs, boulders, bricks,
ropes, coal, and steel plates etc. This indicates that this particular area including the location
selected for shaft construction has been a prime business location and has witnessed various
modes of activities in the distant past leaving traces of activities lay buried in the ground. During
construction of diaphragm walls buried objects as mentioned above made grabbing work very
difficult. The accuracy of grabbing was of utmost importance for the construction of 60m deep D
wall for accommodating 43.5 m deep shaft. Also adjacent Diaphragm walls needed to be
accurately interlocked to avoid water ingress from upper water bearing strata during excavation.
There were two instances where diaphragm walls could not be constructed at desired spots due
to obstructions encountered during grabbing. As a mitigation measure for deviated diaphragm
walls, overlapping D walls were constructed to complete the box. Such mitigation attempts
cannot be ensured to meet the requirements perfectly and leaves behind chances of
imperfections leading to trouble during future activities such as excavation and lining wall
construction. The imperfections due to backup panels created problem of water ingress and was
mitigated by doing jet grout piles at strategic locations (figure 6).

d) Lower Confined Aquifer and Hydraulic Heave


As pointed out above under geology, the stiff clay is underlain by a very vast water bearing
(coarse sand) stratum deriving its water source from river Hooghly and through ground
recharges as this sandy stratum gradually opens up to the ground level quite away from the
location of ventilation shaft. Huge water sources available to this water bearing strata makes it a
mighty confined aquifer running at a very high pressure of 3 bars or above. Dedicated
piezometers were installed to measure the water pressure/water table of lower water bearing
strata. Seasonal variation of water table suggests that the water table varies to the tune of 3m,
peak observed during monsoon and lowest during summers. This translates into hydraulic uplift
pressure at the base of stiff clay layer varying between 3 bars to 3.3 bars respectively.

e) Deep Excavation
https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-th… 6/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

Excavation depth was very high (43.5m). The depth of soil cover above lower confined aquifer
after final excavation was left only 9.0m. Hence the weight of the soil cover after final excavation
against uplift pressure was only 38%. The factor of safety being less than 1 against hydraulic
heave was prohibitive of carrying out excavation without implementing some or another
mitigation measure.

f) Upper Confined Aquifer and Water Ingress


Upper water bearing stratum was initially considered as a discrete water bearing stratum based
on initial soil investigation. But, based on further soil investigations and data obtained from
piezometric observations throughout alignment it was confirmed that this water bearing stratum
is present throughout the alignment. The soil investigation carried out in river Hooghly indicates
that this stratum is opening up in the riverbed and taking recharge from the river. This stratum
also gradually comes up to the ground level approx. 10 Kms away from ventilation shaft location
and gets recharge during rainy season. This is the reason this layer consisting of fine sand and silt
has never depleting water source. Generally, this stratum is 4m to 6m thick throughout the
alignment, but at ventilation shaft location it is abnormally high and to the tune of 17m thick
(figure 7).

g) 3-Water Tables, One Location


This may sound weird that at one location there may exist as many as 3 distinct water tables.
Initially this notion was proposed to the designers and consultants. Our DDC and GC were
initially hesitant to accept this idea but water table monitoring data using standpipe piezometers
confirmed the existence of 3 distinct water tables. Standpipe piezometers were installed in the
lower confined aquifer and upper confined aquifer. Water table of soft organic clay (the topmost
soil stratum) was obtained from bore holes during soil investigations. Since Hydraulic Heave
phenomena was applicable to our case due to lower confined aquifer only, the water table data
recorded for this particular water bearing stratum (-14 mMsl) was used to calculate factor of
safety (FOS) against Hydraulic Heave. This out of box idea and verification of idea through
instrumentation saved us from considering a very high water table (+5.15 mMSl) for calculation
of FOS against Hydraulic Heave. Had this concept not been considered, the FOS would always
have been less than 1.0, prohibiting excavation of shaft without resorting to very expensive
measures (figure 8).
https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-th… 7/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

Initial Design Philosophy of Hydraulic Heave

a) Soil Parameters
Tables 1 and 2 show geological profile and design parameters for various soil strata found at
ventilation shaft location. This is based on geological investigations carried out for the project.

b) Hydraulic Heave
Confined aquifers run on pressure and exert pressure on overlying soil stratum. The pressure
exerted by aquifer is overcome by the weight of soil. As excavation progresses, the soil cover
above aquifer reduces and thereby the weight of soil goes down. The risk of hydraulic heave may
occur when the weight of soil cover (stabilising forces) reduces considerably such that it is less
than or equal to the pressure exerted by the underlying aquifer (destabilising forces).

This risk was associated with lower aquifer only. The upper water bearing strata was cut-off due

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-th… 8/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

to construction of diaphragm walls much below this stratum.

As per Euro code 7 for safety against hydraulic heave, destabilizing pore water pressure at
bottom of the column should be less than stabilizing total stress at the bottom of the column.

The recommended F.O.S against hydraulic heave is 1.5 (Euro code 7, Table A.17)[1].

For Vent shaft location, however, the Factor of safety without implementing any mitigation
measure is calculated as 0.38. Detailed calculation for this is shown in table 3.

The above calculation shows that the factor of safety is much lower than the recommended FOS
and there exists possibility of hydraulic heave due to deep excavation.

Initially, it was thought to implement a dewatering regime during excavation inside the shaft in
the lower water bearing strata to reduce the hydraulic pressure at the bottom of overlying stiff
clay to avoid the risk of hydraulic heave.

c) Dewatering Wells for Lowering Hydrostatic Pressure


PLAXIS, a finite element software package, was used to carry out the seepage analysis. Transient
(time dependent) analysis was carried out for 30-day time period, along with implementation of
drains to estimate the water inflow into the excavation (figure 9).

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-th… 9/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

The head was kept -38.5 mMSL and the flow was estimated in the PLAXIS model.

Total flow through wells provided in vent shaft = 8.71 m3/hr. As the Hooghly River is at 50-60m
from the Vent Shaft location it was expected that the inflow of water will be continuous. Hence it
was proposed to install two pumping wells with submersible pumps in Unit 3b Layer (or lower
water bearing stratum) for reducing the hydrostatic pressure at bottom of Unit 3a layer (or stiff
clay layer). Pumping wells in this layer shall be activated after the excavation reaches 20m below
the ground level. As the excavation progresses beyond 20m, the piezometric head shall be
maintained minimum of 1 meter below the excavation level by operating dewatering pimps.
Table 4 shows summary of the analysis results.

The PLAXIS analysis along with dewatering regime using two borewells showed achievement of
required FOS against Hydraulic Heave, but there were practical difficulties indicating that this
methodology may backfire.
The lower water bearing strata is very vast and connected to river. Actual water flow
quantum may be far more than estimated through analysis, and borewells may go out of
control before the excavation will reach its final level.
There was odd experience of such dewatering regime under similar circumstances at
Howrah Station. Due to enormity of water associated with lower water bearing strata there

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 10/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

was hardly any long term impact on water head due to dewatering and operation of
borewells.
With the progress of excavation, the discharge of borewells was found increasing drastically
during excavation at Howrah Station, indicating the borewells may fail here too due to
excessive discharge. It was also feared that the water may even seep into shaft from the
periphery of borewell due to small left out soil plug at the end of excavation.

Considering above it was necessary to revisit the design philosophy pertaining to hydraulic heave
and/or workout alternate mitigation measures for ensuring safety against hydraulic heave.

Revised Design Philosophy of Hydraulic Heave

a) Plug and Shaft Friction


The stiff clay cover (unit 3a) above lower water bearing strata (unit 3b or confined aquifer) had
very low permeability (10-9) and high undrained cohesion of 180 Kpa. Laboratory experiments
conducted by some researchers suggests that even a small cohesion requires very high hydraulic
gradients to lead to the failure of soil structure. With such a high strength clay cover combined
with excavation in a very small plan area of the shaft will not lead to hydraulic failure. The stiff
clay cover will function as a plug and the friction between clay plug and shaft walls will resist the
uplift pressure exerted by the confined aquifer. This was a revolutionary solution and turning
point for design and construction of the shaft. This kind of concept was going to be implemented
in the field for the first time for underground construction work.

It is evident that the depth of soil cover was very important for revised design consideration. In
order to ascertain the extent of stiff clay stratum at Vent Shaft location, confirmatory soil
investigation was done. The details are given in the table 5.

Final Excavation Level of Vent shaft is -38.0 mMSL and Diaphragm toe level is -50.0 mMSL. Based
on the boreholes data presented, top of Sand layer/Bottom of clay (as presented in the table
above) was considered at -47 mMSL for calculation purpose.

b) Safety Check Calculations

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 11/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

• Adhesion factor α
Average undrained cohesion of clay plug encountered between -38 mMSL and -47 mMSL is
around 180 kPa. Various literature is published by different authors correlating Adhesion factor
(α) and undrained cohesion (Cu) for bored piles. Based on these published works, it is found that
for an average cohesion of 180 kPa, α ranges between 0.35 and 0.6 has been proposed by
various authors (table 6).

• Factor of safety on Ultimate shaft friction


Owing to the temporary nature of the work, a safety factor of 1.5 is considered on ultimate shaft
friction between the clay and the D-Wall to evaluate safe shaft friction.

Considering the level of piezometric head in lower water bearing stratum (Unit 3b) at -14 mMSL,
final excavation level as -38 mMSL and Bottom of clay layer as -47 mMSL, factor of safety against
uplift of bottom clay plug is checked and is found to be 1.11. Water pressure acting at bottom of
Unit 3a is considered as uplift force, Shaft skin friction between the D-Wall & Clay layer and self-
weight of clay are considered as resisting forces against this uplift force. A detailed calculation is
shown in figure 10.

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 12/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

The cohesive soils do not suffer liquefaction or erosion of soil continuum as is typical with sandy
soils. Soil structure failure for such a high cohesion as evident in the concerned clay layer is
highly improbable (We did face opinion difference among designers that the high pressure at the
bottom of stiff clay layer may lead to failure of soil structure and the clay plug will ultimately thin
down and weaken, the same was ruled out by the majority). Hence theoretically, clay plug was
found to be safe and there was remote possibility of hydraulic heave, set aside the possibility of
something happening suddenly without sufficient warning. However, to reduce the risk of failure
of clay plug due to uncertainties involved in ground variation, errors in geotechnical investigation
and variation in adhesion factors, additional preemptive and mitigation measures were necessary.
The mitigation measures adopted were very elaborate and designed and planned for taking
necessary action during any trigger of associated problems.

Preemptive Measures

a) Pumping Wells Outside the Shaft


To enhance the factor of safety of clay plug and shaft friction four 4 pumping wells outside the
shaft were recommended. The pumping wells were planned outside excavation area and outside
the shaft such that borewells do not suffer excessive flow when excavation progresses. The
vastness of water bearing stratum left very little chance of lowering the water bearing stratum.
The borewells were extended into the lower water bearing stratum with an intention to regulate
the water head to the design value or lower to the extent possible.

b) Estimation of flow
Flow through each pumping well in Unit 3B (deep) layer is estimated based on equations
presented in CIRIA 113 [4].

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 13/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

Total quantity of water from each pumping well within the shaft area is estimated based on
equation mentioned below:

Where,

Q is the quantity of flow from a partially penetrated well.

k is the permeability of the layer.

D is the thickness of the confined aquifer (estimated as 18m in current scenario);

h is the head to be lowered to at the well.

RO is radius of influence = 3000*h*√k.

rW is radius of well.

Permeability of the Unit 3b (Deep) layer is expected to be in order of 5 x 10-5 m/sec. To account
variability in the ground quantum of flow is estimated for two set of permeability of 5 x 10-5
m/sec and 7.5 x 10-5 m/sec.

In general, initial flow of water from pumping well is higher as compared to steady flow. Expected
quantity of flow under steady state condition is 400 to 500 lit/min per well. To account flow of
initial stage, pumping capacity should higher than steady state condition. Based on previous
dewatering experience on the project, it was suggested to install the pump which are having
capacity to pump the water 1000 lit/min.

c) Monitoring of standpipe piezometer head


In addition to dewatering, monitoring of piezometer head below clay plug during excavation was
carried out. As per the Monitoring data, levels of piezometric head in lower water bearing
stratum (Unit 3b) was lower than -14 mMSL at all the 4 standpipe locations during entire
excavation period. This was the design water head considered for FOS calculation. Dewatering
borewells outside the shaft were planned to be switched on when the water head in the
piezometers exceeded -14 mMSL. However, the water table never exceeded -14mMSL during
excavation of the shaft. Also the excavation was planned such that it finishes before onset of
monsoon which could cause water table to rise depending upon intensity of monsoon.

d) Monitoring of Heave
During excavation heave monitoring was necessary and very vital. The excavation was planned to
https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 14/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

be carried out in the lifts of 1.5m. During each lift of excavation the soil was expected to relax
resulting into elastic rebound. This elastic rebound could be misleading and create a notion of
hydraulic heave during various stages of excavation (table 7).

To eliminate the chances of confusion, the elastic heave during each stage of excavation was
estimated and used for comparing the actual heave recorded. The “linier elastic continuum
approach” has been used for estimation of heave due to removal of over burden soil at various
stages of excavation.

In a PLAXIS analysis the rebound due to excavation showed an uplift of 45mm which is quite
close to the above calculation. The comparison of box was presented in graph 1.

An FE analysis was carried out using GEOSTUDIO. SEEP/W module was used to carry out Steady
State Analysis and Transient Analysis to assess hydraulic condition at the excavation base. The
water inflow output at the base of excavation was negligeable. SIGMA/W module of GEOSTUDIO
was used to carry out Load – Deformation analysis to assess upward movement of soil mass at
excavation level. The upward movement value achieved was 125mm which was primarily
attributable to rebound of soil on account of stress relief due to unloading of soil post
excavation. The difference in upward movement values between PLAXIS analysis and the analysis
using GEOSTUDIO was due to the values of stiffness modulus used for modeling in PLAXIS (Eur)
and GEOSTUDIO (E50). PLAXIS uses Eur value which is 3 times the E50 value, and when
appropriate adjustments are made the elastic rebound values matched well. Hence all three
methods of estimating elastic rebound were consistent and closely matching (figure 11).

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 15/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

e) Monitoring of Soil Parameters


The strength of soil which was adopted as 180 Kpa (undrained shear strength, Cu) was key in
assessing FOS against hydraulic heave. The success of this concept was largely dependent on
consistency of the soil strength. In order to ascertain the soil strength and to keep watch of its
consistency, following measures were taken.
After each stage of excavation in situ strength of soil was measured with the help of pocket
penetrometer. The readings were taken at multiple locations and averaged out to find Cu
value. The soil strength was found quite consistent and most of the time exceeded the
assumed value (figure 12).

Also, the soil adhered to the shaft wall was poked manually to see the quality of adhesion.
We found that considerable effort was required to dislodge the adhered soil from the shaft
wall. This indicated that the shaft and clay cover friction will be adequately achieved. Such
field techniques enhanced confidence for carrying out further excavation.

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 16/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

Moisture content test of the soil was also tested and monitored after each stage of
excavation using rapid moisture meter and in the lab. It was assumed that the moisture
content of stiff clay will remain the same or reduce with the progress of excavation. The
trace of excess moisture compared to the moisture content of the soil from previous stages
of excavation would indicate water being forced into the soil from lower water bearing
stratum. The moisture content found was between 20% to 22% which represents a near dry
stiff clay soil.

f) Installation of CCTV Camera


CCTV cameras were installed at strategic locations to keep constant watch on excavation
activities. These camaras were also connected with mobiles phones of key persons through
Camera APP to see and review the situation inside the shaft at any instant. This arrangement
gave a good handle on watching and monitoring construction activities inside the shaft.

g) Other Observations
Some other observations were also carried out to keep complete track and capture any sign of
distress at the earliest. They may be summarized as follows.
Photographic observation of interface between D-wall and soil layer after excavation for
each lining wall from 20th lift onwards. The photographic observations provided excellent
record of soil wall interface conditions. These photographic observations were minutely
examined by the experts and consultants including TTAJV team.
Videography of shaft after excavation was also kept for records. This was helpful for
reviewing previous stages of excavation with current stage of excavation in case of
requirement.
Minute examine of D-wall face like any seepage, its locations, its directions of flow. It was
also necessary to see if there was any sign of seepage at the soil and wall interface.
Water content measurement report at site by Rapid Moisture Meter. Also, moisture content
was measured in the lab using samples collected from excavation.
UDS collection for strength test and water content measurement at laboratory by IIEST,
Shibpur.
DDC / GC / IIEST-Shibpur / TTAJV used to visit jointly to assess the physical condition at
each excavation stage.

Contingency Measures
Above preemptive measures were put in place to monitor and regulate the excavation work and
keep an eye on the triggers of hydraulic heave. It may also be noted that this phenomenon was
not expected to happen overnight and will provide sufficient warning for carrying out mitigation
measure to prevent or minimize the impact of hydraulic heave. Following measures were put in
place as part of contingency measures that could be run as per need in case of any contingent
situation demanding drastic action.

a) Maintaining Stock of Soil Near Shaft


Approx. 500 m3 of soil was stockpiled near shaft location. This soil was secured for backfilling the
shaft immediately upon notice of any trigger of hydraulic heave. A platform was fabricated
https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 17/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

suitably for placing of excavator such that the excavator could quickly push the stored soil into
the shaft within a short period of time. A couple of mockups were carried out to make sure that
in case of requirement backfilling of the shaft with stored soil can be done without any problem.

It is interesting to note that the excavation of the shaft came to a halt due to the nationwide
lockdown imposed during onset of pandemic. This stored soil was then put into the shaft during
lockdown period to ensure enhanced FOS of soil cover and eliminate any surprise. The soil was
again removed when the lockdown was relaxed and construction work started moving.

b) Storage of Water at Shaft Location


Approx. 4.5 Lakh liter water was stored at the site during excavation period of the shaft. This
water was stored in multiple water tanks along with multiple pumps. Appropriate pipeline
networks were arranged such that water from all the tanks could be pumped into the shaft
simultaneously in case of visible or measured trigger of hydraulic heave. The backfilling with soil
and water could be done simultaneously in case of such demand. There was a daily protocol to
check the functioning of all the pumps and pipelines so that pumping failures do not occur in
case of requirement.

c) Pumping Arrangement from Hooghly River


A pumping arrangement was established from Hooghly River with the help of government
authorities. This arrangement was able to pump water from river to the tune of ---- Liters/hour
into the shaft. This arrangement was made to address very critical situation requiring drastic
action to fill the shaft quickly. In case of distress taking place rapidly, high quantum pumping
would be the only solution to bring situation under control in minimum time (figure 13).

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 18/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

If backfilling of soil, pumping of stored water at shaft location and pumping of water from river
Hooghly run simultaneously, the shaft could be filled to the desired level within 4 hours from its
deepest level of excavation.

Finally, the Engineering Marvel Created Despite COVID-19 Pandemic


The problem of Hydraulic Heave aggravates with prolongation of construction time. This implies
that once the work enters critical zone, it should be completed in bare minimum time.
Construction of Shaft entered its criticality when the first Lockdown was imposed due to COVID-
19. The team developed strong protocol based on guidelines developed by HO to tackle the
pandemic and created a strong bubble for Vent Shaft workers. The workers were brought to the
site from their homes on dedicated buses and cars, quarantined for 7 days and RTPCR tested. The
negative tested workers were allowed for Vent Shaft construction work. The work area being very
tight, it was difficult to maintain social distancing and hence it was pertinent to isolate workers
from outside contacts. Any spread of virus at Vent Shaft location would have brought the work to
a halt, which, in turn, would have increased the risk of occurrence of Hydraulic Heave. With
extensive effort and implementation of tight protocol at site, COVID-19 cases could be
completely prevented and the construction of Vent Shaft completed successfully. The completion
of Vent Shaft was extensively covered by media and appreciated by the engineering fraternity.

Conclusion
Design and construction of India’s Deepest Ventilation cum Evacuation shaft came with unique
challenges. Several options for design and construction were worked out but were discarded on
some or another grounds. The finally chosen design and construction methodology was fitting
into our requirement but still was quite challenging due to its uniqueness and lack of precedence

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 19/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

requiring careful analysis and implementation. With this success story it can be concluded that
any challenge can be negotiated if we venture to challenge the status quo, follow the basics of
engineering and exercise utmost care and precaution. The team left no stone unturned to make it
a success with the strong support from our experts and seniors at Head Office.

About the Author:

Lakshmana Rao Mantri, a competent Civil Engineer, has over 18 years of experience in civil
engineering project coordination, design coordination of underground metro projects, design,
tendering, risk analysis, monitoring and execution of different project works, slope stabilization
works, geotechnical investigation works including onshore, nearshore/offshore, preparation of
scope of work, preparation of technical specifications, evaluation of factual and interpretative
reports, reinforced soil structures works, gabion walls works, raw water reservoir works,
temporary retaining structures such as cofferdams & sheet piling works, deformation of tunnels
& tunnel lining works, flood protection & river training works, diaphragm walls, deep
foundations, rockfall netting systems, flexible & rigid pavements, MSW landfills, hazardous waste
landfills, slope protection measures and ground improvement works for roads, rail, industrial,
residential, commercial, water supply, power plants, oil and gas projects in India and other
countries.

He has received the Industry Expert National Award 2020 from IRDP Group of Journals; Sir M V
Award from Smart Infra EST, Hyderabad in 2020; Sir M V Awards from Karnataka State

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 20/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

Engineering Association for providing innovative solutions for landfills in 2014; and Achievement
awards from NHAI in 2018 for providing solutions in sustainable Infrastructure in N-E Region.

He is a member of the Indian Geotechnical Society (IGS), Deep Foundation Institute (DFI), Indian
Road Congress (IRC) and International Society of Soil Mechanics and Ground Engineering
(MISSGE)

 NBM&CW June 2022    

 Prev Next 

Breakthrough by two 15.01m Slurry TBMs of CRCHI in two projects


On March 12th 2023, the breakthrough by the largest slurry TBM in China’s Hunan Province
marked the completion of the right line tunneling of the Xiangya Road river-crossing tunnel in
Changsha City. It represents the largest diameter shield machine tunnel
 Read more ...

Sela Tunnel Project - Overcoming The Impossible


The responsibility for construction and maintenance of Balipara-Charduar-Tawang (BCT) Road has
been entrusted to Border Roads Organisation (BRO). The 317.520 km long road connects West
Kameng and Tawang districts of Arunachal Pradesh to the rest
 Read more ...

Slurry TBM ‘Channel Express’ launched by CRCHI for working in Water Supply Tunnels
in Singapore
On February 1, 2023, CRCHI attended the launching ceremony of its Slurry TBM ‘Channel
Express’. It will be used in the construction of key water supply tunnel project TWRP Pipeline
Contract 1 in Singapore where it will bore 1.6km with the inner diameter
 Read more ...

China’s Largest TBM - With Panda Face Emerges From Tunnel

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 21/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

On 12 December 2022 ‘Jinxiu’ - China’s largest EPB TBM developed by CRCHI - marked the first
smooth breakthrough of the Jinxiu Tunnel, a key control project of the Chengdu-Zigong high-
speed railway. Jinxiu is China’s largest diameter EPB TBM with
 Read more ...

STRUCINSPECT Technology Transforms Inspection of Los Angeles Metro Tunnel


Network
With drones, multispectral optics, and AI, Austrian joint venture transforms tunnel inspection in
the US. The world’s first infrastructure lifecycle hub taps the rapidly growing global market for
infrastructure inspections. The remarkable thing about
 Read more ...

CRCHI showcases total solutions of Underground Engineering Equipment


China Railway Construction Heavy Industry Corporation Limited (CRCHI) brought the whole
industry chain products and solutions to bauma CONEXPO INDIA 2023. CRCHI exhibited TBMs,
drilling and blasting method equipment, cotton pickers, and other
 Read more ...

Sandvik sets up new factory; hands over first ‘made in India’ tunnelling jumbo to KSR
Group, Hyderabad
In a historic event held on 30th January, 2023 Sandvik proudly presented the key of the first
‘made in India’ DT820 Tunnelling Jumbo to Mrs. and Mr. Koneru of KSR Group, Hyderabad. The
machine was rolled out from Sandvik’s newly set-up state-of-the-art
 Read more ...

CRCHI Slurry TBM ‘Avni’ Helps Make a Breakthrough in Bangalore Metro Project
The 6.6m Slurry TBM developed by CRCHI exited the tunnel at Vellara Station, Phase II of
Bangalore Metro in India, becoming the first TBM to complete the breakthrough for the whole
line of the project. Avni is one of the four slurry TBMs provided by CRCHI
 Read more ...

The Bolter Miner - A Technology Revolution for Roadway Development in


Underground Coal Mining
In India, coal is still the primary source of energy; over the past few years, there has been
quantum jump in coal production level, but it was mostly due to the high percentage share from
the opencast sector. The country is witnessing a fast
https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 22/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

 Read more ...

CRCHI emerges as provider of total underground engineering equipment and


solutions
China Railway Construction Heavy Industry Corporation Limited (CRCHI) showcased its
comprehensive range of equipment and products at bauma that included solutions for the whole
industry chain in the field of
 Read more ...

Herrenknecht AG wins bauma Innovation Award 2022 for development of continuous


tunnelling
Herrenknecht AG won the highly coveted award bauma Innovation Award 2022 in the category
“Machine Technology” for the new development of continuous tunnelling. The award was given
for the next innovation boost in the mechanized
 Read more ...

The Genesis of Underground Engineering


Regardless of the tunnelling technology used, tunnel designers decide the future success or
failure at an early project stage. In fact, designers are the real managers of tunnel construction.
The choice of design together with selected contract model is
 Read more ...

Managing Geological Complexity in BVC and PAC of Tehri PSP, India - A case study
Tehri hydroelectric project is located on the left bank of River Bhagirathi in the state of
Uttarakhand. Tehri Pumped Storage Project (PSP) comprising 4 Nos of reversible pump-turbine
units of 250 MW each, involves construction of an underground Machine Hall
 Read more ...

TBM driving under low overburden by adopting innovative methodology

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 23/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

TBM mining in urban areas particularly under low overburden (less than 0.5D, D = tunnel Dia) is a
big challenge to design team as well as execution team. While working in a Lucknow metro
project, the metro authorities encountered a stretch where TBM had to cross
 Read more ...

Tunnel Ventilation System Basic Concepts and Designing Principles


The term ventilation combines several functions such as smoke extraction, pollution ventilation,
and ventilation for environmental purpose. The design of a ventilation system is usually based on
three scenarios: During construction: to provide external
 Read more ...

CRCHI Mega Slurry TBM ‘Jinghua’ Assists the First Tunnel Section Breakthrough of
Beijing East Sixth Ring Road Reconstruction Project
In September 2022, the Beijing East Sixth Ring Road Reconstruction Project reported another
good news: the CRCHI mega slurry TBM ‘Jinghua’ smoothly reached the intermediate air shaft,
marking the project’s achievement. The maximum excavation diameter
 Read more ...

TERRATEC EPBMs ready to tackle Kanpur Metro’s 1st Underground Section in India
TERRATEC celebrated the successful site acceptance testing of two 6.52m diameter Earth Pressure
Balance Tunnel Boring Machines (EPBMs) for Uttar Pradesh Metro Rail Corporation (UPMRC) for
Corridor-1 of Kanpur MRTS Project (KNPCC-05) in India. The two 6.52m
 Read more ...

Tunnelling Asia 2022 - International Conference on Underground Space


Tunnelling Asia 2022, organized by TAI, which took place in Mumbai during 27th and 28th June,
saw a huge gathering of delegates/engineers from all around the world. The theme of the
conference: ‘Underground Space: Need of the Day’ focused on
 Read more ...

Creating Zero-Carbon Tunnels


https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 24/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

Despite a daunting timeline set by the Paris Accord, zero-carbon tunnels are within reach,
provided the right solutions are implemented. Er. Vasileios (Bill) Paoulos, CMT, CMRL, L&T
Construction Heavy Civil Infrastructure
 Read more ...

NBM&CW

View Online Download

Previous Issues Subscribe Now

Concrete Construction

View Online Download

Previous Issues Subscribe Now

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 25/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

MGS Architecture

View Online Download

Previous Issues Subscribe Now

L&ST

View Online Download

Previous Issues Subscribe Now

II&TW

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 26/27
12/04/2023, 12:12 Hydraulic Heave Failure Mitigation Approach for the construction of the Deepest Metro Ventilation and Egress Shaft in India

View Online Download

Previous Issues Subscribe Now

About Us
Contact
Advertise
Subscribe
Terms & Conditions
Privacy Policy
Cancellation / Refund Policy
Disclaimer

To get latest updates on whatsapp, Save +91 93545 87773 and send us a 'Saved' message

Click Here to Subscribe to Our eNewsletter.

NBM Media Pvt. Ltd. | All rights reserved © 2023

https://www.nbmcw.com/article-report/infrastructure-construction/tunneling/hydraulic-heave-failure-mitigation-approach-for-the-construction-of-t… 27/27

You might also like