Professional Documents
Culture Documents
Erection Methodology-Solar Access Staircase
Erection Methodology-Solar Access Staircase
Erection Methodology-Solar Access Staircase
REVISION NO. : 00
LOCATION : TAMILNADU
DATE : 12-04-2023
Prepared By Approved By
M/s URC M/s Gleeds / M/s ANSELL LTD
ERECTION METHODOLOGY
CONTENTS
S.No. DESCRIPTION
I. PURPOSE
II. SCOPE
III. REFERENCES
IV. RESPONSIBILITY
I.PURPOSE:
To ensure the erection work at M/S Ansell Safety, Correctly &Comply with Ansell &
Gleeds.
II.SCOPE:
This Method statement shall applicable for the PEB structure work for erection at
Construction of Factory – M/s ANSELL LTD as per the Technical specification & BOQ.
III.REFERENCE:
Project Manager: Shall be responsible for control, supervision and Direction for
Implementation of this procedure as per erection schedule and sequence of work on safe
manner.
Site Engineer: Shall give the necessary guideline for required activity.
Safety In charge: Shall facilitate to maintaining a good safe working Condition.
Site Supervisor: Responsible for the day to day supervision if site activities, site personnel
and to ensure that all personnel work in a safe manner also ensure that all daily and weekly
plan and PPE Register /inspections are carried out.
Erection Team: shall be responsible for erection progress as per erection schedule and
erection procedure with safe manner.
Ensure that client and other agencies are informed about the start of the erection.
Ensure proper housekeeping at site prior to commence the work.
Erection member must be comprised of steel wire rope of 12, 14 & 16 mm dia. with turn
buckle.
Erection member must securely tie up with rigid support like in opposite direction of the load
line.
Before starting the erection activities, handover of site (with checking all dimension as per
Civil/Mech. standard) should be done from Civil to mechanical with appropriate
Documentation.
Survey for wind direction &roof material storage for installation direction.
Check for pathway for truck movement, crane capacity as per procedure and list of equipment
register.
o Purpose: - PEB works material unloading for ANSELL LTD site storage yard.
o Scope: - PEB works of ANSELL LTD PEB building.
o Manpower: - As per site requirement manpower shall be engaged for unloading at
storage yard. Man power involved as supervisor, riggers, Signal Man and Crane
operator.
o Tools & Equipment Machinery: - Cranes & trailer truck based on the site
conditions.
Job steps:-
All the material to be QC Checked before dispatch from yard and to be informed 24 hours
arrival at site.
Trailer loaded with PEBs material shall be entered from ANSELL LTD enter gate.
Vehicle entry shall be recorded at gate with client Material inward procedure.
Entry of vehicle shall be entered at designated location.
Supervisor will place trailer at unloading Area. And take work permit for unloading of
material.
Placing of crane nearby trailer.
Rigger shall issue slings from store and use for material unloading as per safety and rigging
supervisor approval.
All material shall be unloaded at designated location.
All material shall be kept on wooden plank.
Gap between each material at least 300mm space as per packing list
Site supervisor shall be checked all material as per packing list.
ERECTION METHODOLOGY
Receiving of documents shall be given to trailer operator after unloading and material
checking.
Control measures:-
Site supervisor shall ensure material inward at site. Required PPEs shall be given to trailer
operator and helper at gate.
Site supervisor shall ensure vehicle shall reach safely at designated storage yard.
Trailer operator shall ensure he will drive safely to designated location in space limit 20kmph.
Site safety norms shall be followed during unloading of material.
Riggers shall use ANSELL LTD approved Tools and tackles. Supervisor shall ensure the
same.
All PPE’s shall be worn by riggers as per job requirement, i.e. hand gloves etc.
As per the site requirement tagline shall be fixed and used by rigger on the both end of
material.
All material shall be kept on wooden planks below 1.5 meter height.
Good lighting condition shall be available during job. Over loading of material is strictly
prohibited.
Experienced &Approved riggers shall be used for material unloading and shifting works as per
Ansell Work permit procedure.
o Purpose: - Material shifting for erection works at ANSELL LTD factory building
from site storage yard to erection Grid line Area.
o Scope: - PEB works of ANSELL LTD PEB building.
o Manpower: - As per site requirement manpower shall be engaged for shifting of PEB
material from storage yard to erection work Area
o Man power involved: - Man power involved as supervisor, riggers, Signal Man and
Crane operator.
o Tools & Equipment Machinery: - Crane & trailer truck based on the site condition.
Job steps:-
Identification of required material by job supervisor and riggers.
Arrangement of required tools and machinery at storage yard Area.
ERECTION METHODOLOGY
Entry of tire mounted crane at storage yard at required Area. Supervisor shall ensure
proper placing of tire mounted crane at material shifting job.
Take work permit for material shifting.
Rigger shall issue slings from store and use for material unloading. Material shall be
fixed with webbing slings/slings equally.
Material shall be kept on wooden plank. And ensure tag line fixed by riggers.
Site supervisor /foreman shall signal to operator for shifting of material at erection grid.
Supervisor and rigger shall ensure during shifting vehicle movement shall be slow and as per
site safety norms.
Material needs to be kept separate storage for column, Stringers, handrail, chequered plate.
Site engineer shall ensure the pathway for shifting of material shall be providing well
compacted by client side.
Control measures:-
Site supervisor shall ensure webbing slings shall be fixed properly with packing of tube or
some other good packing material.
Required PPEs shall be given to all riggers and helpers during works.
Site supervisor shall ensure vehicle shall reach safely at designated erection grid line.
Pathway shall be check by operator before shifting of material.
Operator shall ensure he will drive safely to designated location. Site safety norms shall be
followed during shifting of material.
Riggers shall use ANSELL LTD approved Tools and tackles. Supervisor shall ensure the
same.
All PPEs shall be worn by riggers as per job requirement, i.e. hand gloves etc.
6 meter tagline shall be fixed and used by rigger on the both end of material .All material
shall be kept on wooden planks below 1.5 meter height.
Good lighting condition shall be available during job. Over loading strictly prohibited.
Building parameters :
Width, W = 2.2 m C/C Length, L = 5.05 m C/C Height, H = 15 m
ERECTION METHODOLOGY
Job steps:-
Identification of required material by job supervisor and riggers and erection grid line Area.
Assemble the Column and stringer in the ground floor
Approved lift plan should be ensured before starting the work.
Loading to be done as per crane loading chart and should not exceed 70% of SWL.
Check for quality of paint and touch up paint should be matching the approved color code
(RAL).
Take erection / height work permit by Ansell/Gleeds.
Check the ground condition of the before start of erection work. Client has to provide good
compacted ground for erection works and machinery movement. No water stagnation allowed
at site.
Arrangement of required tools and machinery at erection yard Area.
Riggers shall use ANSELL LTD approved slings from store for erection work. Slings shall
be fixed with proper packing strut tube and bracing structure.
Barricade the work Area and put warning sign of do not enter.
Ensure the tag line at both end of and bracing of the column during erection works.
Foreman / Signal man shall signal to operator for erection of column at erection grid.
Supervisor shall ensure smooth erection of portal and bracing works, Release the sling from
the strut tube and bracing with help of ladder.
Team of 2-4 person shall pull girts with the help of rope tied on the both ends .No person
shall cross or enter the miscellaneous erection Area during erection works.
Riggers shall guide the material on clits and do the nut bolting with help of ladder at 6 meter
height and above six meter rigger shall stand on the man lift & fixed girts.
Miscellaneous fixing i.e. h a n d r a i l a n d c h e q u e r e d p l a t e shall be done as per PEB
work procedure and method statement.
Maximum Weight of Staircase is 08MT
ERECTION METHODOLOGY
Control measures:-
Site engineer shall ensure the ground condition and satisfy himself that ground condition is
satisfactory for side wall frame erection works.
Check all machinery and tools and tackles issued for erection is ANSELL LTD approved.
Webbing slings shall be fixed properly with packing of tube or some other good packing
material in erection activity.
Required PPEs shall be given to all riggers and helpers during works.
Site supervisor shall ensure vehicle shall reach safely at designated erection grid line.
Ground shall be check by operator before erection works.it should be well compacted and side
no excavation.
Signal man shall give proper signal to Crane operator during erection works.
All PPEs shall be worn by riggers as per job requirement i.e. hand gloves etc.
Align and level the column, if there is any gap between the bottom of the base plate and top
of R.C.C Column place the M.S. shim plates.
6 meter tagline shall be fixed on the bottom of the column and used by rigger to guide the
column on erection grid line Area.
No person shall come under side wall framing work, ensure Area soft barricading.
Good lighting condition shall be available during job.
Erection will start from side wall column of designated Grid Area.
Bring the particular column designated Area as per drawing and part mark to the GRID.
Attach connection clips for eaves strut and girt with the main columns at ground only.
Tie one end of column top with wire sling by providing packing underneath.
Lift the column designated AREA with the help of crane gradually.
Erect the column on pedestal. Take care about threads of anchor bolts while inserting base
plate in to this. There should not be damage to threads.
Immediately tighten the nuts of anchor bolts using proper washers using Spanner.
Verticality & Tightening of anchor bolt shall be checked by Execution Engineer & QC
Engineer of ANSELL LTD as per Quantum of Check mentioned in ITP.
Calibration certificate of all Tightening and Alignment instruments used to check, shall be
submitted to the client.
Note: The crane should be released slowly only after placing the Guy Ropes and
full tightening of bolts.
Same procedure has to be followed for erecting other columns from applicable grid line.
Install the connection member between the two columns.
Install the girt and flange braces in same manner.
POINTS TO BE NOTED:
Attachment:-
1. GA Drawing