Professional Documents
Culture Documents
Starbucks OCS 2.0 - ENG - Pre-Requisite Guide v1.2
Starbucks OCS 2.0 - ENG - Pre-Requisite Guide v1.2
v1.2
1 / 16
2 / 16
3 / 16
= 260mm
= 100mm
4 / 16
650mm
1000mm
400mm
Concrete determined to 350Kg/m3 - Cement CPJ 45. Resistance of soil equal to or greater than 2
Bars. Dynamic pressure 162 daN / m²
5 / 16
B A
500mm
260mm
Conduit (A) is used for the electrical cable 110v/240v which is connected to the main power switch
board and must have:
• A draw string + a cable « RO2V 3G1.5 » (For France but to required local standards) from the
E.S to main power supply with 10A circuit breaker
Conduit (B) is used for audio/video and computer system cables and should go to the cash booth in
Hole B (see below) and must have:
• A draw string to pull Ethernet cable Cat.5 / 6 or VGA cable + audio cable + BNC cable (if
required)
Into Conduit A:
• 1 x Power line 220v
Into Conduit B:
• 2 x Audio Cable
• 1 x Audio Cable for Autoexit SSV
• 1 x Cat 5/6 Cable for the Player going to the Store Network Switch
• 1 x Cat 5/6 Cable for a direct connexion of the Barista IP Camera (going to the window)
• 1 x Cat 5/6 Cable for a direct connexion of the Customer IP Camera (going to the window)
• 1 x Cat 5/6 Network Cable as spare
6 / 16
The 2 conduits must be in a diameter of 100mm otherwise, they won’t fit into the foot.
100mm
7 / 16
In hot and sunny country (like in the Middle East) the order point location is already protected with a
canopy, a tunnel or else.
In the case of nothing has been installed to create a shade zone above the order point location, it is
requested to create a sun protection, like a mesh or a canopy, above the order point location.
8 / 16
On a tablet at 1.60m from the ground (used to put the battery charger)
• 1 Electrical outlet 2P+T 110v-220v /16A for the Battery Charger power
9 / 16
10 / 16
490mm
440mm
964mm
11 / 16
• 1 x 60mm hole (A) to be done Prior to the Installation (into the wall)
• 1 x 60mm hole (B) to be done Prior to the Installation (into the wall)
• 1 x 60mm hole (C) to be done During the Installation (into the wall)
• 1 x 50mm hole (D) to be done During the Installation (on the bottom rack)
A
D
12 / 16
13 / 16
14 / 16
AUDIO AND VIDEO CABLE MUST BE PASSED AT THE SAME TIME WITH THE CONDUIT.
It’s possible to ask the electrician or the person who pass the conduits to pass those cables.
Remember: conduit (B) is used for audio/video and computer system cables, it starts from the OCS
2.0 and end up at the cash / order booth into Hole (B)
CONDUIT B
15 / 16
• 2 x Audio Cable
• 1 x Audio Cable for Autoexit SSV
• 1 x Cat 5/6 Cable for the Player going to the Store Network Switch
• 1 x Cat 5/6 Cable for a direct connexion of the Barista IP Camera (going to the window)
• 1 x Cat 5/6 Cable for a direct connexion of the Customer IP Camera (going to the window)
• 1 x Cat 5/6 Network Cable as spare
They must go from the OCS (leave 3m of cables there) to the Hole (B) inside the restaurant (leave all
the remain cable there)
16 / 16