General communication
For use with ECSC4

Project No. #760060081 Client Aisha Butt

Project Title Belmopan Roof Works Purchase Order PNU1001444

Location BHC Belmopan, North Ring Contractor Union Infrastructure


Road/Melhado Parade, PO Box
91, Belmopan, Belize Client Contract No. XLY/120/166/22TP

GC NO 005 Contractor to Client

Reason for communication: (Identify the appropriate box(es) with an ‘X’)

Certificate Other Submission


Proposal Record Acceptance
Reply

Evidence of onsite Health & Safety Protocols

UNION INFRASTRUCTURE have prepared this General Communication to evidence the ongoing Health &
Safety protocols implemented on site.

Scaffolding principal access tower complete, inspected and certified prior to use and inspected
every morning to ensure the scaffolding remains operationally safe

Principal scaffold access tower to main roof Additional base support to principal access tower

Ref: UI.CONS.453.FCDO.BRW.GC003
OFFICIAL
OFFICIAL

Scaffolding Certification Tags Scaffolding safe to use notification

Scaffolding tied back to structure Internal stars with double hand rail
3# scaffolding towers to form safe working access to parapet structure

General photo Photo 01

Handrails

Additional lateral angled braced supports

Toe boards Additional handrails


Hazardous material store for paints

General Photo Photo of COSH sign & Hazardous material sign

Stainless Steel mansafe system

Ref: UI.CONS.453.FCDO.BRW.GC003
OFFICIAL
OFFICIAL

Attachment: Yes No.


Description of attachment;.

N/A

Signed David Francis Rogers Date 06/03/2023


(Contractor)

Issued to

Client Contractor File Other


Attachment One

- End -

Ref: UI.CONS.453.FCDO.BRW.GC003