Rough Estimate of Boundry wall back side of Godown upto GM House total length = 100 R/mtr

Sr no. Description Measurment Qty Unit Rate Amount

A)- Construction of New Boundary Wall


1 Excavation by hand column foundation 34 1.200 0.450 1.000 18.360 Cu.m 424 7,785
2 Excavation by hand Balance length 1 100.000 0.330 1.000 33.000 Cu.m 424 13,992
3 Less column footings. -34 0.450 0.650 1.000 -9.945 Cu.m 424 (4,217)
4 P.C.C 1:4:8 under column foundation 34 1.200 0.450 0.050 0.918 Cu.m 10639 9,767
5 P.C.C 1:4:8 under balance length 1 100.000 0.330 0.050 1.650 Cu.m 10639 17,554
6 Less column footings. -34 0.125 0.330 0.050 -0.070 Cu.m 10639 (746)
7 R.C.C 1:2:4 in column foundation 34 1.100 0.350 0.150 1.964 Cu.m 14376 28,227
8 R.C.C 1:1.5:3 in column upto Plinth top level 34 0.125 0.250 0.850 0.903 Cu.m 16474 14,878
9 d/d Plinth beam -34 0.125 0.125 0.250 -0.133 Cu.m 16474 (2,188)
10 R.C.C 1:2:4 in Plinth Beam 1 100.000 0.125 0.250 3.125 Cu.m 14659 45,809
11 R.C.C 1:1.5:3 in column above Plinth beam 34 0.250 0.125 2.500 2.656 Cu.m 16651 44,229
12 P.C.C 1:2:4 in coping 230x50mm thick 1 100.000 100.000 Rm 170 17,000
13 Form work in column foundation 100x350 34 2.900 0.150 14.790 Sq.m 500 7,395
14 Form work in column upto bottom of plinth beam 34 0.750 0.850 21.675 Sq.m 610 13,222
15 Form work in plinth beam 2 100.000 0.250 50.000 Sq.m 610 30,500
16 Form work in column above plinth beam 34 0.750 2.500 63.750 Sq.m 650 41,438
17 Brick work 230mm thick upto bottom of plinth beam 1 100.000 0.600 60.000 Sq.m 2444 146,640
18 d/d column -34 0.125 0.600 -2.550 Sq.m 2440 (6,222)
19 Brick work 115mm thick above plinth beam 1 100.000 2.150 215.000 Sq.m 1420 305,300
20 d/d column -34 0.125 2.150 -9.138 Sq.m 1420 (12,975)
21 Steel Reinforcement 1500 Kg 256.8 385,200
22 P/F of Angle iron in column 34 no 2"x2"x3/16" 150 Kg 329 49,350
23 P/F GI barbed wire (concertina Razor type) 1 100.000 100.000 Rm 1200 120,000
Total 1,271,938
Add 10% for additional. 127,194
Net Total 1,399,132
Dismantling of R.C.C Floor 400x200

Dismantling of R.C.C Floor for excavation 1 0.900 1.200

Dismantling of Brick Work 1 0.900 0.900

Excavation 1 11.730 1.760

P.C.C 1:4:8 1 11.730 1.360

Brick work 2 11.730


1 0.900

20 mm thick nerro plaster 2 11.270


1 11.270 0.900

40 mm thick nerro plaster in ceiling 1 11.270 0.900

Steel
5 No

0.200 0.216 Cu.m

0.230 0.186 Cu.m

1.050 21.677 Cu.m

0.150 2.393 Cu.m

0.900 21.114
0.900 0.810
Total 21.924 Sq.m

0.900 20.286
10.143
Total 30.429 Sq.m

10.143 Sq.m

50.000 Kg