Untitled

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 235

P.C.C.

1:4:8
RAIWIND AREA
Based:- 100
Description Qty. Unit Rate
Cement 9.47 Bag 1100.00
Sand 47.38 Cft 50.00
Crush Sargodha 94.76 Cft 145.00
Total
Wastage/T & P 3
Labour 100 Cft 28.00

Total
O.H + Profit + I.Tax 0
Total
Rate Per Cft . 301.22 / Cft.
Rate Per Cu.m . 10,639.00 /Cu.m

P.C.C. 1:4:8 Mouse Duct


ICP
Based:- 100
Description Qty. Unit Rate
Cement 9.47 Bag 1100.00
Sand 47.38 Cft 50.00
Crush Sargodha 94.76 Cft 145.00
Total
Wastage 3
Labour 100 Cft 75.00
Curing
Total
O.H + Profit + I.Tax
Total
Rate Per Cft . 348.22 / Cft.
Rate Per Cu.m . 12,299.00 /Cu.m

Shuttering Rate Analysis (Slab and Beams)


Unit of Measurement 100x100
Detail of Particulars QTY UOM Rate
Steel Plate weight 37174 kgs 300
Pipes 36300 Rft 250
Joint 6000 No 300
Girder 2.25kgs/rft 3100 Rft 675
Wooden Planks/battons Total Need 3500 x 2= 7000 Rft
(assuming 2 time required in 40 time life span) Salvage "0" 7000 Rft 280
Pakens (Wedges) Total Need 1600*3=4800 No
(assuming 3 time required in 40 time life span) Salvage "0" 4800 No 12
Miscellaneous (Ribs etc.) 1 LS 50000
Total Cost of Material
Less 50% salvage value will apply on first 4 items
Cost of material after deduction of Salvage Value
Useful life 40 times ( Cost of Material for 10,000 Sft one time)
Cost of Material for Per Sq.ft
Add Labour super structure
Add oiling/ Greasing
Cost of Labour and Material for One Sft

Cost per Sq.M (Slab and beams)

Shuttering Rate Analysis (Columns)


Unit of Measurement 100x100
Detail of Particulars QTY UOM Rate
Steel Plate weight 37174 kgs 300
Pipes 36300 Rft 250
Joint 6000 No 300
Miscellaneous Planks, wedges etc 1 LS 50000
Total Cost of Material
Less 50% salvage value will apply on first 3 items
Cost of material after deduction of Salvage Value
Useful life 40 times ( Cost of Material for 10,000 Sft one time)
Cost of Material for Per Sq.ft
Add Labour super structure
Add oiling/ Greasing
Cost of Labour and Material for One Sft

Cost per Sq.M (Slab and beams)

Shuttering Rate Analysis (Columns FFL)


Unit of Measurement 100x100
Detail of Particulars QTY UOM Rate
Steel Plate weight 37174 kgs 300
Pipes 36300 Rft 250
Joint 6000 No 300
Miscellaneous Planks, wedges etc 1 LS 50000
Total Cost of Material
Less 50% salvage value will apply on first 3 items
Cost of material after deduction of Salvage Value
Useful life 40 times ( Cost of Material for 10,000 Sft one time)
Cost of Material for Per Sq.ft
Add Labour super structure
Add oiling/ Greasing
Cost of Labour and Material for One Sft

Cost per Sq.M (Slab and beams)


Steel
ICP
Based:- 100
Description Qty. Unit Rate
Steel 1.03 240.00
B.W 0.008 kgs 300.00
Total
Labour 1 M.Ton 9.00
resale 1.5% 0.015 -120.00
Total
O.H + Profit + I.Tax 0
Total
Steel one Tons 256800.00 M.Tons

R.C.C. 1:2:4 in Foundation


ICP
Based:- 100
Description Qty. Unit Rate
Cement 17.6 Bags 1100.00
C.Sand 22.00 Cft 50.00
L. Sand 22.00 Cft 145.00
Crush 88.00 Cft 145.00
Total
Wastage 3
Labour 100 32.00
Curing 100 Cft 0.00
Total
O.H + Profit + I.Tax 0
Total
Rate Per Cft . 407 / Cft. w/o shutt
Rate Per Cu.m . 14,376.00 /Cu.m oh

R.C.C. 1:2:4 in R.A ducts


ICP
Based:- 100
Description Qty. Unit Rate
Cement 17.6 Bags 1100.00
C.Sand 22.00 Cft 50.00
L. Sand 22.00 Cft 145.00
Crush 88.00 Cft 145.00
Total
Wastage 3
Labour 100 40.00
Curing 100 Cft 0.00
Total
O.H + Profit + I.Tax 0
Total
Rate Per Cft . 415 / Cft. w/o shutt
Rate Per Cu.m . 14,659.00 /Cu.m oh

R.C.C. 1:2:4 ( Slab )


ICP
Based:- 100
Description Qty. Unit Rate
Cement 17.6 Bag 1100.00
C.Sand 22.00 Cft 50.00
L. Sand 22.00 Cft 145.00
Crush 88.00 Cft 145.00

Total
Wastage 3
Labour 100 CFT 45.00
L.S
Curring Charges 100 CFT 0.00
Total
O.H + Profit + I.Tax
Total

Rate Per Cft . 420 / Cft. w/o shutt


Rate Per Cu.m . 14,835.00 /Cu.m oh

R.C.C. 1:2:4 (Beam and Lintel)


ICP
Based:- 100
Description Qty. Unit Rate
Cement 17.6 Bag 1100.00
C.Sand 22.00 Cft 50.00
L. Sand 22.00 Cft 145.00
Crush 88.00 Cft 145.00

Total
Wastage 3
Labour 100 45.00
Curring Charges L.S
Shuttering 100 Cft 0.00

Total
O.H + Profit + I.Tex 0
Total

Rate Per Cft . 420 / Cft. w/o shutt


Rate Per Cu.m . 14,835.00 /Cu.m oh

R.C.C. 1:2:4 Slab S.A ducts


ICP
Based:- 100
Description Qty. Unit Rate
Cement 17.6 Bag 1100.00
C.Sand 22.00 Cft 50.00
L. Sand 22.00 Cft 145.00
Crush 88.00 Cft 145.00

Total
Wastage 3
Labour 100 45.00
Curring Charges L.S
Shuttering 100 Cft 0.00

Total
O.H + Profit + I.Tex 0
Total

Rate Per Cft . 420 / Cft. w/o shutt


Rate Per Cu.m . 14,835.00 /Cu.m oh

R.C.C. 1:2:4 columns and over head water tank


ICP
Based:- 100
Description Qty. Unit Rate
Cement 17.6 Bag 1100.00
C.Sand 22.00 Cft 50.00
L. Sand 22.00 Cft 145.00
Crush 88.00 Cft 145.00

Total
Wastage 3
Labour 100 45.00
Curring Charges L.S
Shuttering 100 Cft 0.00

Total
O.H + Profit + I.Tex 0
Total

Rate Per Cft . 420 / Cft. w/o shutt


Rate Per Cu.m . 14,835.00 /Cu.m oh

R.C.C. 1:1-1/2:3 ( Columns )


ICP
Based:- 100
Description Qty. Unit Rate
Cement 22.4 Bag 1100.00
C.Sand 21.00 Cft 50.00
L. Sand 21.00 Cft 145.00
Crush 84.00 Cft 145.00

Total
Wastage 3
Labour 100 45.00
Curring Charges L.S
Curing 100 cft 0.00

Total
O.H + Profit + I.Tex 0

Total
Rate Per Cft . 466 / Cft. w/o shutt
Rate Per Cu.m . 16,474.00 /Cu.m oh

R.C.C. 1:1-1/2:3 ( Columns )


ICP
Based:- 100
Description Qty. Unit Rate
Cement 22.4 Bag 1100.00
C.Sand 21.00 Cft 50.00
L. Sand 21.00 Cft 145.00
Crush 84.00 Cft 145.00

Total
Wastage 3
Labour 100 50.00
Curring Charges L.S
Curing 100 Cft 0.00
Total
O.H + Profit + I.Tex

Total
Rate Per Cft . 471 / Cft. w/o shutt
Rate Per Cu.m . 16,651.00 /Cu.m oh

R.C.C. 1:1-1/2:3 ( water tank )


ICP
Based:- 100
Description Qty. Unit Rate
Cement 22.4 Bag 1100.00
C.Sand 21.00 Cft 50.00
L. Sand 21.00 Cft 145.00
Crush 84.00 Cft 145.00

Total
Wastage 3
Labour 100 50.00
Curring Charges L.S
Curing 100 Cft 0.00
Total
O.H + Profit + I.Tex

Total
Rate Per Cft . 471 / Cft. w/o shutt
Rate Per Cu.m . 16,651.00 /Cu.m oh

R.C.C. 1:1:2 ( Columns ) Upto F F L


ICP
Based:- 100
Description Qty. Unit Rate
Cement 30.8 Bag 1100.00
C.Sand 19.25 Cft 50.00
L. Sand 19.25 Cft 145.00
Crush 77.00 Cft 145.00

Total
Wastage 3
Labour 100 46.00
L.S
Curring Charges 100 Sft 0.00

Total
O.H + Profit + I.Tex 0

Total

Rate Per Cft . 549 / Cft. w/o shutt


Rate Per Cu.m . 19,378.00 /Cu.m oh

R.C.C. 1:1:2 ( Columns ) S/S


ICP
Based:- 100
Description Qty. Unit Rate
Cement 30.8 Bag 1100.00
C.Sand 19.25 Cft 50.00
L. Sand 19.25 Cft 145.00
Crush 77.00 Cft 145.00

Total
Wastage 3
Labour 100 50.00
L.S
Curring Charges 100 cft 0.00
Total
O.H + Profit + I.Tex 0

Total

Rate Per Cft . 553 / Cft. w/o shutt


Rate Per Cu.m . 19,519.00 /Cu.m oh

P.C.C. 1:3:6
ICP
Based:- 100
Description Qty. Unit Rate
Cement 12.32 Bag 1100.00
Sand 46.2 Cft 50.00
Crush Sargodha 92.4 Cft 145.00
Total
Wastage 3
Labour 100 Cft 28.00
Curing 100 Cft 0.00
Total
O.H + Profit + I.Tax 0
Total
Rate Per Cft . 329.38 / Cft. w/o shutt
Rate Per Cu.m . 11,634.00 /Cu.m oh

Brick Work ( 1:4 ) C.S.M UP TO F.F.L

ICP
Based:- 100
Description Qty. Unit Rate
Bricks 1350 Nos. 14.00
Cement 4.8 Bags 1100.00
Sand 24 Cft 50.00

Total
Wastage 0
Labour 100 Cft 47.00
Curring Labour 100 Cft 0

Total

O.H + Profit + I.Tax


Total
Rate for per CFT 301 / CFT
Rate for per Cu.m 10,624.00 / Cu.m
A) 460 mm Thick 4887 / Sq.m
B) 345 mm Thick 3665 / Sq.m
C) 230 mm Thick 2444.00 / Sq.m
Brick Work ( 1:4 ) C.S.M UP TO F.F.L (115mm)

Based:- 100
Description Qty. Unit Rate
Bricks 1350 Nos. 14.00
Cement 4.8 Bags 1100.00
Sand 24 Cft 50.00

Total
Wastage 0
Labour 100 Cft 63.00
Curring Labour 100 Cft 0

Total

O.H + Profit + I.Tax


Total

cft 316.8
Cu.m 11186.208
Sq.M 1286 115mm

Brick Work 1:4 C.S.M F.F.L


460 mm Thick Mouse duct
Based:- 100
Description Qty. Unit Rate
Bricks 1350 Nos. 13.00
Cement 4.8 Bags 700.00
Sand 24 Cft 33.00

Total
Wastage 0
Labour 100 Cft 74.00
Curing 100 Cft 1

Total

O.H + Profit + I.Tax 0


Total

B.work 460 mm Thick 292 Cft


10311
B.work 460 mm Thick 4743 / Sq.m

Brick Work 1:4 C.S.M F.F.L


345 mm Thick Mouse duct
Based:- 100
Description Qty. Unit Rate
Bricks 1350 Nos. 13.00
Cement 4.8 Bags 700.00
Sand 24 Cft 33.00

Total
Wastage 0
Labour 100 Cft 72.00
Curing 100 Cft 1

Total

O.H + Profit + I.Tax 0


Total

B.work 345 mm Thick 290 Cft


10241
B.work 345 mm Thick 3533 / Sq.m

Brick Work 1:4 C.S.M F.F.L


230 mm Thick (Mouse Ducts)
Based:- 100
Description Qty. Unit Rate
Bricks 1350 Nos. 13.00
Cement 4.8 Bags 700.00
Sand 24 Cft 33.00

Total
Wastage 0
Labour 100 Cft 74.00
Curing 100 Cft 1

Total

O.H + Profit + I.Tax 0


Total

B.work 230 mm Thick 292 Cft


10311
B.work 230 mm Thick 2372 / Sq.m

DPC of PCC (1:2:4) 40 mm thick

Based:- 100
Description Qty. Unit Rate
Cement 2.2 Bag 1100.00
C.Sand 5.50 Cft 50.00
Crush 11.00 Cft 145.00
primer + total 11.612 kgs per 100 sft Bitumen 11.62 kgs 150.00

polythin sheet 100.00 Sft 5.00


Pudlo 1 kgs per bag of cement 2.20 kgs 200.00

Total
Wastage 3
Labour 100 Sft 30.00

Total

Total

102 / Sft. w/o shutt


1096 /Sq.m oh

Brick Work 1:4 C.S.M Above F.F.L


345 mm Thick
Based:- 100
Description Qty. Unit Rate
Bricks 1350 Nos. 14.00
Cement 4.8 Bags 1100.00
Sand 24 Cft 50.00

Total
Wastage 0
Labour include folding 42+4 100 cft 56.00
Curing 100 cft 0

Total

O.H + Profit + I.Tax 0


Total

B.work 345 mm Thick 310 cft


10939 c.m
B.work 345 mm Thick 3774 S.m

Brick Work 1:4 C.S.M Above F.F.L (S/S)


230 mm Thick S/S
Based:- 100
Description Qty. Unit Rate
Bricks 1350 Nos. 14.00
Cement 4.8 Bags 1100.00
Sand 24 Cft 50.00

Total
Wastage 0
Labour 100 cft 58.00
Curing 100 cft 0
Total

O.H + Profit + I.Tax 0


Total

B.work 230 mm Thick 312 cft


11010 c.m
B.work 230 mm Thick 2532 S.m
Brick Work ( 1:4 ) C.S.M S/S (115mm) G.F

Based:- 100
Description Qty. Unit Rate
Bricks 1350 Nos. 14.00
Cement 4.8 Bags 1100.00
Sand 24 Cft 50.00

Total
Wastage 0
Labour 100 Cft 96.00
Curring Labour 100 Cft 0

Total

O.H + Profit + I.Tax


Total

349.80
12351.438
1420

Brick Work ( 1:4 ) C.S.M S/S (115mm) 1st floor

Based:- 100
Description Qty. Unit Rate
Bricks 1350 Nos. 14.00
Cement 4.8 Bags 1100.00
Sand 24 Cft 50.00

Total
Wastage 0
Labour 100 Cft 106.00
Curring Labour 100 Cft 0

Total

O.H + Profit + I.Tax


Total

359.80
12704.538
1461

Cement Plaster ( 1:4 ) 20 mm Thick in Trenches FFL

Based:- 100
Description Qty. Unit Rate
Cement 1.3104 Bags 1100.00
Sand 6.55 Cft 50.00

Total
Wastage 5

Labour 100 22.00


Scaffolding 100 L.S 0
Curing Cagrges 100 0
Total

O.H + Profit + I.Tax 0


Total
Rate for 20 mm Thick Cement Pilaster 41 / Sft
Rate for 20 mm Thick Cement Pilaster 437 / Sq.m

Cement Plaster ( 1:4 ) 20 mm Thick G.F (S/S)

Based:- 100
Description Qty. Unit Rate
Cement 1.31 Bags 1100.00
Sand 6.55 Cft 50.00

Total
Wastage 5

Labour 100 23.00


Scaffolding 100 L.S 0
Curing Cagrges 100 0
Total

O.H + Profit + I.Tax 0


Total
Rate for 20 mm Thick Cement Pilaster 42 / Sft
Rate for 20 mm Thick Cement Pilaster 447 / Sq.m

Cement Plaster ( 1:4 ) 20 mm Thick G.F (S/S) Outer surfaces

Based:- 100
Description Qty. Unit Rate
Cement 1.31 Bags 1100.00
Sand 6.55 Cft 50.00

Total
Wastage 5

Labour 100 25.00


Scaffolding 100 L.S 0
Curing Cagrges 100 0
Total

O.H + Profit + I.Tax 0


Total
Rate for 20 mm Thick Cement Pilaster 44 / Sft
Rate for 20 mm Thick Cement Pilaster 469 / Sq.m

Cement Plaster (NEARO) 20 mm Thick in R.A Ducts (Mouse)

Based:- 100
Description Qty. Unit Rate
Cement 1.925 Bags 1100.00
Sand 6.55 Cft 50.00

Total
Wastage 5
Labour 100 L.S 23.00
T&P 100 L.S 0

Total

O.H + Profit + I.Tax 0


Total
Rate for 20 mm Thick Cement Plaster 49 / Sft
Rate for 20 mm Thick Cement Plaster 524 / Sq.m

Cement Plaster (NEARO) 40 mm Thick in R.A Ducts (Mouse) in 2 layers

Based:- 100
Description Qty. Unit Rate
Cement 3.85 Bags 700.00
Sand 13.10 Cft 33.00

Total
Wastage 5
Labour 100 L.S 28.00
T&P 100 L.S 0
Total

O.H + Profit + I.Tax 0


Total
Rate for 20 mm Thick Cement Plaster 61 / Sft
Rate for 20 mm Thick Cement Plaster 655 / Sq.m

Cement Plaster (NEARO) 20 mm Thick in R.A Ducts

Based:- 100
Description Qty. Unit Rate
Cement 1.925 Bags 1100.00
Sand 7.22 Cft 50.00

Total
Wastage 5
Labour 100 L.S 20.00
T&P 100 L.S 0

Total

O.H + Profit + I.Tax 0


Total
Rate for 20 mm Thick Cement Plaster 46 / Sft
Rate for 20 mm Thick Cement Plaster 495 / Sq.m

Cement Plaster (NEERO) 20 mm Thick in S.A Ducts

Based:- 100
Description Qty. Unit Rate
Cement 1.925 Bags 1100.00
Sand 7.22 Cft 50.00

Total
Wastage 5
Labour 100 L.S 21.00
T&P 100 L.S 0

Total

O.H + Profit + I.Tax 0


Total
Rate for 20 mm Thick Cement Plaster 47 / Sft
Rate for 20 mm Thick Cement Plaster 506 / Sq.m

Pointing (1:3)
Based:- 100
Description Qty. Unit Rate
Cement 1.092 Bags 1100.00
Sand 4.10 Cft 50.00
Red Oxide 1.28 Kg 400.00
Total
Wastage 3

Labour 100 SF 21.00


Scufffolding 100 SF 0

Total

O.H + Profit + I.Tax 0


Total
Rate for 20 mm Thick Cement Pilaster 41 / Sft
Rate for 20 mm Thick Cement Pilaster 439 / Sq.m

Angle
Based:- 1
Description Qty. Unit Rate
Angle 1 kgs 235.00
Waistage 0.03 Kgs 235.00
Red Oxide
Total
Wastage 0

Labour 1 Kgs 50.00

Total

O.H + Profit + I.Tax 0


Total

Pit Snad (Kassoo)


Based:- 1
Description Qty. Unit Rate
Kassu 1.2 Cft 30.00

Total
Wastage 3

Labour 1 Cft 9.00

Total

O.H + Profit + I.Tax 0


Total

Rate in Cu.M 1624

P.C.C. 1:4:8
RAIWIND AREA
Based:- 100
Description Qty. Unit Rate
Cement 9.47 Bag 1100.00
Sand 47.38 Cft 50.00
Crush Sargodha 94.76 Cft 145.00
Total
Wastage/T & P 3
Labour 100 Cft 32.00

Total
O.H + Profit + I.Tax 0
Total
Rate Per Cft . 305.22 / Cft.
Rate Per Cu.m . 10,780.00 /Cu.m
135mm 1,455.30
150mm 1,617.00

Flooring 65 mm Thick ( 1:1:3 )

Based:- 100
Description Qty. Unit Rate
Cement 5.20 Bags 1100.00
Sand 3.25 Cft 50.00
Sand LP 3.25 Cft 145.00
Crush 19.40 Cft 145.00

Total
Wastage 3
Labour 100 L.S 25.00
curing 100 L.S 0

Total
O.H + Profit + I.Tax 0
Total
Rate for 65 mm Thick Flooring 119 / Sft
Rate for 65 mm Thick Flooring 1285 / Sq.m

Flooring 65 mm Thick ( 1:2:4 )

Based:- 100
Description Qty. Unit Rate
Cement 3.66 Bags 1100.00
Sand(3.67) 4.58 Cft 50.00
Sand LP(3.67) 4.58 Cft 145.00
Crush 18.30 Cft 145.00

Total
Wastage 3
Labour 100 L.S 25.00
0 100 L.S 0

Total

O.H + Profit + I.Tax 0


Total
Rate for 65 mm Thick Flooring 103 / Sft
Rate for 65 mm Thick Flooring 1108 / Sq.m

Flooring TERRAZZO (Margalla Crush) 25mm+125mm (1:2:4)

Based:- 100
Description Qty. Unit Rate
25mm topping
Cement 3.408 Bags 1100.00
Margalla 8.52 CFt. 145.00
125mm base (1:2:4)
Cement 1;2:4 7.22 Bags 1100.00
Snad 9.022 CFt. 50.00
Sand LP 9.022 CFt. 145.00
Crush 36.088 CFt. 145.00

Total
Wastage 3
Labour 100 L.S 50.00

Total
O.H + Profit + I.Tax 0
Total
Rate for Terrazzo Flooring 255 / Sft
Rate for Terrazzo Flooring 2745 / Sq.m

Flooring TERRAZZO (Margalla Crush) 25mm+100mm (1:2:4)

Based:- 100
Description Qty. Unit Rate
25mm topping
Cement 3.408 Bags 1100.00
Margalla 8.52 CFt. 145.00
100mm base (1:2:4)
Cement 1;2:4 5.86 Bags 1100.00
Snad 7.325 CFt. 50.00
Sand LP 7.325 CFt. 145.00
Crush 29.3 CFt. 145.00

Total
Wastage 3
Labour 100 L.S 50.00

Total

O.H + Profit + I.Tax 0


Total
Rate for Terrazzo Flooring 226 / Sft
Rate for Terrazzo Flooring 2434 / Sq.m

Flooring TERRAZZO (Margalla Crush) 25mm+75mm (1:2:4)

Based:- 100
Description Qty. Unit Rate
25mm topping
Cement 3.408 Bags 1100.00
Margalla 8.52 CFt. 145.00
75mm base (1:2:4)
Cement 1;2:4 4.40 Bags 1100.00
Snad 5.5 CFt. 50.00
Sand LP 5.5 CFt. 145.00
Crush 22 CFt. 145.00

Total
Wastage 3
Labour 100 L.S 47.00

Total

O.H + Profit + I.Tax 0


Total
Rate for Terrazzo Flooring 192 / Sft
Rate for Terrazzo Flooring 2067 / Sq.m

Flooring TERRAZZO (Margalla Crush) 25mm+50mm (1:2:4)

Based:- 100
Description Qty. Unit Rate
25mm topping
Cement 3.408 Bags 1100.00
Margalla 8.52 CFt. 145.00
50mm base (1:2:4)
Cement 1;2:4 2.92 Bags 1100.00
Snad 3.652 CFt. 50.00
Sand LP 3.652 CFt. 145.00
Crush 14.608 CFt. 145.00

Total
Wastage 3
Labour 100 L.S 44.00

Total

O.H + Profit + I.Tax 0


Total
Rate for Terrazzo Flooring 158 / Sft
Rate for Terrazzo Flooring 1696 / Sq.m

S..B.R

For 2 Sq.M 1 Liter 450


Laboure 21.52 sft 1

Total for 2SM

For one SM
Ceramic Tiles ( On Floor ) with 1:3 40mm

Based:- 1
Description Qty. Unit Rate
Ceramic Tiles (Rs. 1500/sq.m.) 1.00 Sft 139.40
Cement 0.0325 Sft 1100.00
Cement 0.010 Bags 1100.00
Sand 0.121 Cft 50.00
Tile Bond 0.03 bags 500.00
Filer @ Rs. 3.00 per sft 1.00 LS 3.00
Total
Wastage 3
Labour 1 55.00
Total

O.H + Profit + I.Tex 0


Total
Rate for Ceramic Flooring 272 / Sft
Rate for Ceramic Flooring 2921 / Sq.m

Ceramic Tiles with 20mm Plaster (1:4)

Based:- 1
Description Qty. Unit Rate
Ceramic Tiles 1.00 Sft 139.40
Cement 0.013 Sft 1100.00
Cement 0.01 Bags 1100.00
Sand 0.07 Cft 50.00
Tile Bond 0.03 LS 500.00
Filer @ Rs. 3.00 per sft 1.00 LS 3.00
coverage 2.5 bags in 1bag cement
Total
Wastage 3
Labour 1 55.00
Total

O.H + Profit + I.Tex 0


Total
Rate for Ceramic Flooring 248 / Sft
Rate for Ceramic Flooring 2667 / Sq.m

Granito Tiles ( On Floor ) with 1:3 40mm

Based:- 1
Description Qty. Unit Rate
Granito Tiles(Rs. 2600/sq.m.) 1.00 Sft 241.64
Cement 0.0325 Sft 1100.00
Cement 0.010 Bags 1100.00
Sand 0.121 Cft 50.00
Tile Bond 0.03 LS 500.00
Filer @ Rs. 3.00 per sft 1.00 LS 3.00
Total
Wastage 3
Labour 1 55.00
Total

O.H + Profit + I.Tex 0


Total
Rate for Ceramic Flooring 377 / Sft
Rate for Ceramic Flooring 4054 / Sq.m

Granito Tiles with 20mm Plaster (1:4)

Based:- 1
Description Qty. Unit Rate
Granito Tiles(Rs. 2600/sq.m.) 1.00 Sft 241.64
Cement 0.013 Sft 1100.00
Cement 0.01 Bags 1100.00
Sand 0.07 Cft 50.00
Tile Bond 0.03 LS 500.00
Filer @ Rs. 3.00 per sft 1.00 LS 3.00
coverage 2.5 bags in 1bag cement
Total
Wastage 3
Labour 1 55.00
Total

O.H + Profit + I.Tex 0


Total
Rate for Ceramic Flooring 353 / Sft
Rate for Ceramic Flooring 3800 / Sq.m

Boticina 20mm ( On Floor ) with 1:3 20mm

Based:- 1
Description Qty. Unit Rate
Boticina Tiles 1.00 Sft 400.00
Cement 0.0163 Sft 1100.00
Cement 0.01 Bags 1100.00
Sand 0.07 Cft 50.00
Tile Bond 0.03 LS 500.00
Filer @ Rs. 3.00 per sft 1.00 LS 3.00
coverage 2.5 bags in 1bag cement
Total
Wastage 5
Labour 1 55.00
Total

O.H + Profit + I.Tex 0


Total
Rate for Ceramic Flooring 528 / Sft
Rate for Ceramic Flooring 5678 / Sq.m

Soling on Edge

Based:- 1
Description Qty. Unit Rate
Bricks 533.00 Sft 14.00
Sand 40mm 12.5000 Sft 55.00
Sang Grout 5.00 Cft 55.00
Total
Wastage 0
Labour 100 Sft 11.00
Total

O.H + Profit + I.Tex 0


Total
95 / Sft
1025 / Sq.m

Tile and mud over PU (1:4)

Based:- 100
Description Qty. Unit Rate
PU (To be Supplied by Client
Earth 16.00 Cft 13.00
Turi 15.00 Kgs 8.00
Cement 0.50 Bags 700.00
Sand 2.50 Cft 33.00
Brick Tiles 350.00 Nos. 9.50

Total
Wastage 3
Labour 100 L.S 18.00
Carriage L.S
Total

O.H + Profit + I.Tex 0


Total
60 / Sft
646 / Sq.m
Water Proofing with 30 Kg Bitumen

Based:- 100
Description Qty. Unit Rate
Bitumen 80/100 9.75 Kgs 100.00
Bitumen 10/20 20.25 Kgs 100.00
Kerocin Oil 3.00 Liters 120.00
Hesian Cloth 100.00 Sft 4.50
Polythene Sheet 200.00 Sft 3.00
Thermopor Sheet 40mm 25Kg 100.00 SFT 40.00
Earth 40.00 Cft 12.00
Cement 0.50 Bags 700.00
Sand 2.50 Cft 33.00
Brick Tiles 350.00 Nos. 9.50
Total
Wastage 0
Labour 100.00 L.S 21.00
Total

O.H + Profit + I.Tex 0


Total
147 / Sft
1587 / Sq.m

Water Proofing with 30 Kg Bitumen

Based:- 100
Description Qty. Unit Rate
Bitumen 80/100 9.75 Kgs 100.00
Bitumen 10/20 20.25 Kgs 100.00
Hesian Cloth 100.00 Sft 4.50
Polythene Sheet 200.00 Sft 3.00
Kerocin Oil 3.00 Liters 120.00
Earth 40.00 Cft 12.00
Cement 0.50 Bags 700.00
Sand 2.50 Cft 33.00
Brick Tiles 350.00 Nos. 9.50
Total
Wastage 0
Labour 100.00 L.S 21.00
Total

O.H + Profit + I.Tex 0


Total
107 / Sft
1156 / Sq.m
Water Proofing with 30 Kg Bitumen

Based:- 100
Description Qty. Unit Rate
Bitumen 80/100 9.75 Kgs 100.00
Bitumen 10/20 20.25 Kgs 100.00
Hesian Cloth 100.00 Sft 4.50
Sand 6.00 Cft 90.00
Kerocin Oil 3.00 Liters 120.00

Total
Wastage 0
Labour 100.00 L.S 16.00
Total

O.H + Profit + I.Tex 0


Total
60 / Sft
640 / Sq.m

Screeding 65 mm Thick ( 1:2:4 )

Based:- 100
Description Qty. Unit Rate
Cement 3.66 Bags 700.00
Sand(3.67) 4.58 Cft 33.00
Sand LP(3.67) 4.58 Cft 90.00
Crush 18.30 Cft 88.00
Groove bitumen 2.5 Kgs 100.00
sand 0.25 cft 90.00

Total
Wastage 3
Labour 100 L.S 16.00
0 100 L.S 5

Total

O.H + Profit + I.Tax 0


Total
Rate for 65 mm Thick Flooring 73 / Sft
Rate for 65 mm Thick Flooring 781 / Sq.m

Water Proofing 65 mm Thick ( 1:2:4 ) Screeding (PU by Client) .213 ft


Based:- 100
Description Qty. Unit Rate
Cement 0.03748 Bags 1100.00
Sand 0.04686 Cft 50.00
Sand LP 0.04686 Cft 145.00
Crush 0.18744 Cft 145.00
Bitumen Volume 0.00000 Kgs 150.00
Sand 0.00000 Cft 50.00
Wooden fuel 0.00000 Kgs 80.00
Sand over polythi 0.06314 Cft 33.00
Polythin sheet 1 sft 5.00
Total
Wastage 3
Labour 1 L.S 21.00
Making of Groove (1200x1200) and filling 0.6 Rft 15

Water Proofing 65 mm Thick ( 1:2:4 ) Screeding (PU by Client) .213 ft

Based:- 100
Op Cement Bags 3.74 1100.00
Sand Lawarnespure Cft 9.25 Rs.145.00
Crush Margala Cft 18.50 Rs.145.00
Steel Nail (For polythene fixing) Sft 100.00 Rs.1.00
Washer Sft 100.00 Rs.0.50
Bitumen 80/100 Kgs 0.50 Rs.150.00
Fire Wood Kgs 0.50 Rs.20.00
1/2" thick Sand Cousion Cft 5.00 Rs.50.00
Polythene Sheet Single Sft 100.00 Rs.4.50
Total
Add 3%
Total Material
Labour
Labour for Laying Polythene Sheet Sft
Labour for Laying 1/2" thick Sand Cousion Sft
Additional Labour for Fixing Steel lesser dia =1/4" Kgs
Labour for Laying and Finishing Concrete Sft
Labour Charges for Cutting of 5mmx 20mm Grove Rft
Labour for filling Bitumen and Sand in Joint Rft
Lift Charges Sft
Total Labour Sft 100 31
TOTAL 100 SF

One SF Cost
For One SM

SPD
Description Unit Resource Rate
Primer Liter 1.250 Rs.350.00
3 coats of Emulsion Paint Liter 2.500 Rs.215.00
putty Kg 4.000 Rs.90.00

Labor i/c Scaffolding Charges Sft 100.000 Rs.11.00

Weather Sheild

Description Unit Resource Rate


Primer Liter 1.250 Rs.350.00
3 coats of Weather Shield Paint Liter 3.000 Rs.650.00
putty Kg 4.000 Rs.90.00

Labor i/c Scaffolding Charges Sft 100.000 Rs.11.00

Plastic Emulsion
Description Unit Resource Rate
Primer Liter 1.250 Rs.360.00
3 coats of Plastic Shield Paint Liter 3.000 Rs.515.00
putty Kg 4.000 Rs.90.00

Labor i/c Scaffolding Charges Sft 100.000 Rs.12.00

White Wash
Description Unit Resource Rate

3 coats of Lime Wash Kg 2.000 Rs.20.00


Gillue Kg 0.250 Rs.350.00
Labor i/c Scaffolding Charges Sft 100.000 Rs.7.00

Enamel Paint on plasterd wall


Description Unit Resource Rate
Primer Liter 1.250 Rs.350.00
3 coats of Enamel Paint Liter 3.000 Rs.750.00
putty Kg 4.000 Rs.90.00

Labor i/c Scaffolding Charges Sft 100.000 Rs.12.00

C.Rubber Paint Paint on plasterd wall


Description Unit Resource Rate
Primer Liter 1.250 Rs.350.00
3 coats of Rubber Paint Liter 3.000 Rs.1,350.00
putty Kg 4.000 Rs.90.00

Labor i/c Scaffolding Charges Sft 100.000 Rs.15.00

Enamel Paint on steel


Description Unit Resource Rate
Red Oxide Liter 1.000 Rs.590.00
3 coats of Enamel Paint Liter 3.000 Rs.750.00
Steel putty Kg 0.150 Rs.590.00

Labor i/c Scaffolding Charges Sft 100.000 Rs.12.00

Expended Metal+Plaster 40mm SA Duct Walls


Ordinary Portland Cement Bag 2.600 Rs.1,100.00
Sand Cft 13.000 Rs.50.00
Expended Metal with Nail and Washeretc Sft 100.000 Rs.20.00
Wastage @3 %
Labour for Expended Metal Sft 100.000 Rs.5.00
Labour for Plaster Sft 100.000 Rs.30.00

UPVC Pipe 4" dia Class-B


UPVC Pipe 4" dia Class-B RFT 1.000 Rs.300.00
Salousion

Labour for Fixing Rft 1.000 Rs.70.00

MS Man Hole Cover 600x600


angle 3.725 Rs.235.00
Sheet 1.837 Rs.290.00
fabrication 5.562 Rs.50.00

carriage 2%

Labour fixing 1.000 Rs.120.00

Paint 2.500 Rs.43.00

For One SM

Angles Outer Frame 1 2.4 3.477


Angles Outer Frame 1 2.4 2.185
hold fasts
total angle
angle in one Sft4sft area

12 gauge shhet 0.36 20.41

sheet in one Sft4 sft

Grit 15mm + 20mm plaster


Based:- 100
Description Qty. Unit Rate
Cement 1.3104 Bags 1100.00
cement 1.705 Bags 1100.00
Sand 6.55 Cft 50.00
Grit / pan crush 4.246 cft 145
cement sullry 0.5 bags 1100
Total
Add 3%

Laboure w/o grinding 100 sft 45

cost one SF
Cost one SM
CFT
Amount
10417.00
2369.00
13740.20
26526.20
795.79
2800.00
0.00
30121.99
0.00
30121.99

CFT
Amount
10417.00
2369.00
13740.20
26526.20
795.79
7500.00
0.00
34821.99
0.00
34821.99
34821.99
0

10000
Amount
11,152,200.00
9,075,000.00
1,800,000.00 Sheet 50%, angle 50%
2,092,500.00 Angle 235

1,960,000.00 Sheet 310

57,600.00 Ave 272.5


50,000.00 Febrication 60
26,187,300.00 332.5
(12,059,850.00)
14,127,450.00
353,186.25
35.32
30.00
2.50
67.82
OR
729.73

10000
Amount
11,152,200.00
9,075,000.00
1,800,000.00
50,000.00
22,077,200.00
(11,013,600.00)
11,063,600.00
276,590.00
27.66
30.00
2.50
60.16
OR
647.31

10000
Amount
11,152,200.00
9,075,000.00
1,800,000.00
50,000.00
22,077,200.00
(11,013,600.00)
11,063,600.00
276,590.00
27.66
24.00
2.50
54.16
OR
582.75
CFT
Amount
247.20
2.40
249.60
9.00
-1.80
256.80
0.00
256.80
258.60
0

CFT
Amount
19360.00
1100.00
3190.00
12760.00
36410.00
1092.30
3200.00
0.00
40702.30
0.00
40702.30
40702.30
0

CFT
Amount
19360.00
1100.00
3190.00
12760.00
36410.00
1092.30
4000.00
0.00
41502.30
0.00
41502.30
41502.30
0

CFT
Amount
19360.00
1100.00
3190.00
12760.00

36410.00
1092.30
4500.00
0.00
0.00
42002.30
0.00
42002.30

42002.30
0

CFT
Amount
19360.00
1100.00
3190.00
12760.00

36410.00
1092.30
4500.00
0.00
0.00

42002.30
0.00
42002.30

42002.30
0

CFT
Amount
19360.00
1100.00
3190.00
12760.00

36410.00
1092.30
4500.00
0.00
0.00

42002.30
0.00
42002.30

42002.30
0

CFT
Amount
19360.00
1100.00
3190.00
12760.00

36410.00
1092.30
4500.00
0.00
0.00

42002.30
0.00
42002.30

42002.30
0

CFT
Amount
24640.00
1050.00
3045.00
12180.00

40915.00
1227.45
4500.00
0.00
0.00

46642.45
0.00

46642.45
46642.45
0

CFT
Amount
24640.00
1050.00
3045.00
12180.00

40915.00
1227.45
5000.00
0.00
0.00
47142.45
0.00

47142.45
47142.45
0

CFT
Amount
24640.00
1050.00
3045.00
12180.00

40915.00
1227.45
5000.00
0.00
0.00
47142.45
0.00

47142.45
47142.45
0

CFT
Amount
33880.00
962.50
2791.25
11165.00

48798.75
1463.96
4600.00
0.00
0.00

54862.71
0.00

54862.71

54862.71
0

CFT
Amount
33880.00
962.50
2791.25
11165.00

48798.75
1463.96
5000.00
0.00
0.00
55262.71
0.00

55262.71

55262.71
0

CFT
Amount
13552.00
2310.00
13398.00
29260.00
877.80
2800.00
0.00
32937.80
0.00
32937.80
32937.80
0

CFT
Amount
18900.00
5280.00
1200.00

25380.00
0.00
4700.00
0.00

30080.00

0.00
30080.00
CFT
Amount
18900.00
5280.00
1200.00

25380.00
0.00
6300.00
0.00

31680.00

0.00
31680.00

SFT
Amount
17550.00
3360.00
792.00

21702.00
0.00
7400.00
100.00

29202.00

0.00
29202.00

SFT
Amount
17550.00
3360.00
792.00

21702.00
0.00
7200.00
100.00

29002.00

0.00
29002.00

SFT
Amount
17550.00
3360.00
792.00

21702.00
0.00
7400.00
100.00

29202.00

0.00
29202.00

SFT
Amount
2420.00
275.00
1595.00
1742.55

500.00
440.00

6972.55
209.18
3000.00

10181.73

10181.73

SFT
Amount
18900.00
5280.00
1200.00

25380.00
0.00
5600.00
0.00

30980.00

0.00
30980.00

SFT
Amount
18900.00
5280.00
1200.00

25380.00
0.00
5800.00
0.00
31180.00

0.00
31180.00

CFT
Amount
18900.00
5280.00
1200.00

25380.00
0.00
9600.00
0.00

34980.00

0.00
34980.00

CFT
Amount
18900.00
5280.00
1200.00

25380.00
0.00
10600.00
0.00

35980.00

0.00
35980.00
L

SFT
Amount
1441.44
327.60

1769.04
88.45
1857.49
2200.00
0.00
0.00
4057.49

0.00
4057.49

SFT
Amount
1441.00
327.60

1768.60
88.43
1857.03
2300.00
0.00
0.00
4157.03

0.00
4157.03

rfaces

SFT
Amount
1441.00
327.60

1768.60
88.43
1857.03
2500.00
0.00
0.00
4357.03

0.00
4357.03

ouse)

SFT
Amount
2117.50
327.60

2445.10
122.26
2300.00
0.00

4867.36

0.00
4867.36

in 2 layers

SFT
Amount
2695.00
432.30

3127.30
156.37
2800.00
0.00
6083.67

0.00
6083.67

SFT
Amount
2117.50
361.00

2478.50
123.93
2000.00
0.00

4602.43

0.00
4602.43

SFT
Amount
2117.50
361.00

2478.50
123.93
2100.00
0.00

4702.43

0.00
4702.43
SFT
Amount
1201.20
204.75
512.00
1917.95
57.54
1975.49
2100.00
0.00

4075.49

0.00
4075.49

Kga
Amount
235.00
7.05
2.50
244.55
0.00
244.55
50.00
0.00

294.55

0.00
295.00

CFt
Amount
36.00
0.00

36.00
1.08
37.08
9.00
0.00

46.08

0.00
46.00

CFT
Amount
10417.00
2369.00
13740.20
26526.20
795.79
3200.00
0.00
30521.99
0.00
30521.99

SFT
Amount
5720.00
162.50
471.25
2813.00
0.00

9166.75
275.00
2500.00
0.00

11941.75
0.00
11941.75

SFT
Amount
4026.00
229.00
664.10
2653.50

7572.60
227.18
2500.00
0.00

10299.78

0.00
10299.78

2:4)

SFT
Amount

3748.80
1235.55

7938.70
451.10
1308.19
5232.76

19915.10
597.45
5000.00

25512.55
0.00
25512.55

2:4)

SFT
Amount

3748.80
1235.55

6446.00
366.25
1062.13
4248.50

17107.22
513.22
5000.00

22620.44

0.00
22620.44

2:4)

SFT
Amount

3748.80
1235.55

4840.00
275.00
797.50
3190.00

14086.85
422.61
4700.00

19209.45

0.00
19209.45

2:4)

SFT
Amount

3748.80
1235.55

3213.10
182.60
529.54
2118.16

11027.75
330.83
4400.00

15758.58

0.00
15758.58

450
21.52

471.52

235.76
Sq.m
Amount
139.40
35.75
11.00
6.05
15.00
3.00
210.20
6.31
55.00
271.51

0.00
271.51

Sq.m
Amount
139.40
14.30
11.00
3.25
16.25
3.00
0.00
187.20
5.62
55.00
247.82

0.00
247.82

Sq.m
Amount
241.64
35.75
11.00
6.05
15.00
3.00
312.44
9.37
55.00
376.81

0.00
376.81

Sq.m
Amount
241.64
14.30
11.00
3.25
16.25
3.00
0.00
289.44
8.68
55.00
353.12

0.00
353.12

Sq.m
Amount
400.00
17.93
11.00
3.25
15.00
3.00
0.00
450.18
22.51
55.00
527.69

0.00
527.69

Sq.m
Amount
7462.00
687.50
275.00
8424.50
0.00
1100.00
9524.50

0.00
9524.50

SFT
Amount

208.00
120.00
350.00
82.50
3325.00

4085.50
122.57
1800.00

6008.07

0.00
6008.07
SFT
Amount
975.00
2025.00
360.00
450.00
600.00
4000.00
480.00
350.00
82.50
3325.00
12647.50
0.00
2100.00
14747.50

0.00
14747.50

SFT
Amount
975.00
2025.00
450.00
600.00
360.00
480.00
350.00
82.50
3325.00
8647.50
0.00
2100.00
10747.50

0.00
10747.50
SFT
Amount
975.00
2025.00
450.00
540.00
360.00

4350.00
0.00
1600.00
5950.00

0.00
5950.00

SFT
Amount
2562.00
151.14
412.20
1610.40
250.00
22.50

5008.24
150.25
1600.00
500.00

7258.49

0.00
7258.49
SFT
Amount
41.23
2.34
6.79
27.18
0.00
0.00
0.00
2.08
5.00
84.63
2.54
21.00
9.00

117.17

0.00
117.17
10.76
1260.716528336

SFT
4114.00
1341.25
2682.50
100.00
50.00
75.00
10.00
250.00
450.00
9072.75
272.18
9344.93

3100
12444.93

124.449325
1339.074737

Amount Material
Rs.437.50
Rs.537.50 1,335.00
Rs.360.00

Rs.1,100.00 1,100.00

TOTAL 2,435.00
For One SF 24.35
For One SM 262.01

Amount Material
Rs.437.50
Rs.1,950.00 2,747.50
Rs.360.00

Rs.1,100.00 1,100.00

TOTAL 3,847.50
For One SF 38.48
For One SM 413.99

Amount Material
Rs.450.00
Rs.1,545.00 2,355.00
Rs.360.00

Rs.1,200.00 1,200.00

TOTAL 3,555.00
For One SF 35.55
For One SM 382.52

Amount Material

Rs.40.00 127.50
Rs.87.50
Rs.700.00 700.00

TOTAL 827.50
For One SF 8.28
For One SM 89.04

Amount Material
Rs.437.50
Rs.2,250.00 3,047.50
Rs.360.00
Rs.0.00
Rs.1,200.00 1,200.00

TOTAL 4,247.50
For One SF 42.48
For One SM 457.03

ll
Amount Material
Rs.437.50
Rs.4,050.00 4,847.50
Rs.360.00

Rs.1,500.00 1,500.00

TOTAL 6,347.50
For One SF 63.48
For One SM 682.99

Amount Material
Rs.590.00
Rs.2,250.00 2,928.50
Rs.88.50

Rs.1,200.00 1,200.00

TOTAL 4,128.50
For One SF 41.29
For One SM 444.23

Walls
Rs.2,860.00
Rs.650.00
5,510.00
Rs.2,000.00
165.30
Rs.500.00
3,500.00
Rs.3,000.00

TOTAL 9,175.30
For One SF 91.75
For One SM 987.26

Rs.315.00
Rs.20.00 335.00

Rs.70.00 70.00

TOTAL 405.00
For One RM 1,328.81

Rs.875.36 875.36
Rs.532.70 532.70
Rs.278.09 278.09
Total 1,686.16
33.72

Rs.120.00 120.00
Rs.0.00
Rs.107.50 107.50

Rs.1,947.38
For One SM Rs.20,953.81

8.3448
5.244
1.311
14.8998
3.72495

7.3476

1.8369
SFT
Amount
1441.44
1875.50
327.60
615.67
550
4810.21
144.3063
4954.52
5098.8226
10053.34
100.533389
1082
Ordinary Portland Cement Bag 2.150 Rs.0.00 Rs.0.00
Wastage 3%
Sand (Lawrence pur) Cft 5.280 Rs.0.00 Rs.0.00
Bulking & Wastage @20%
Crushed Aggregate (Margala) Cft 10.560 Rs.0.00 Rs.0.00

Pudlo 5Kg/per bag of Cement Kg 10.750 Rs.200.00 Rs.2,150.00


Bitumen Kg 0.000 Rs.150.00 Rs.0.00
Polythene Sheet Sft 100.000 Rs.4.50 Rs.450.00
P.C.C. 1:4:8
ICP
Based:- 100 CFT
Description Qty. Unit Rate Amount
Cement 9.47 Bag 600.00 5682.00
Sand 47.38 Cft 29.00 1374.02
Crush Sar 94.76 Cft 70.00 6633.20
Total 13689.22
3 Wastage 410.68
Labour
100 Cft 25.00 2500.00
100 Curing Cft 1.00 100.00
Total 16699.90
0 O.H + Profit + I.Tax 0.00
Total 16699.90
Ra 167.00 / Cft. w/o shutt 16599.90
Ra 5,898.00 /Cu.m oh 0
Remarks
Remarks

Remarks

Remarks
Remarks

Remarks

15+5
Remarks

Remarks
Remarks

Remarks
Remarks

Remarks

Remarks
Remarks

Remarks
Remarks

Remarks
Remarks

Remarks

Pit Snad (Kassoo)


Based:-
Remarks Description Qty. Unit
Angle 1.2 Cft

Total
3 Wastage

Labour
1 Cft

Total

0 O.H + Profit + I.Tax


Total

Rate in Cu.M 777

Remarks
Remarks

Remarks
Remarks

Remarks
Flooring TERRAZZO (Margalla Crush) 20mm+50mm (1:2:4)

Remarks Description Qty. Unit Rate


25mm topping
Cement 2.726 Bags 700.00
Margalla 6.82 CFt. 95.00
125mm base (1:2:4)
Cement 1;2:4 2.92 Bags 700.00
Snad 3.652 CFt. 33.00
Sand LP 3.652 CFt. 90.00
Crush 14.608 CFt. 88.00

Total
3
Wastage
Labour 100 L.S 47.00

Total

O.H0+ Profit + I.Tax


Total
Rate#DIV/0!
for Terrazzo
/ SftFlooring
Rate for1208
Terrazzo
/ Sq.m
Flooring
Based:-
Remarks Description Qty. Unit
PU (To be Supplied by Client
Earth 16.00 Cft
Turi 15.00 Kgs
Cement 0.50 Bags
Sand 2.50 Cft
Brick Tiles 350.00 Nos.

Total
3 Wastage
Labour
100 L.S
Carri L.S
Total

0 O.H + Profit + I.Tex


Total
59 / Sft
638 / Sq.m
Based:-
Description Qty. Unit
Remarks Bitumen 9.75 Kgs
Bitumen 20.25 Kgs
Hesian Clo 100.00 Sft
Kerocin Oil 3.00 Liters
Polythene 200.00 Sft
Thermopor 100.00 SFT
Earth 40.00 Cft
Cement 0.50 Bags
Sand 2.50 Cft
Brick Tiles 350.00 Nos.
Total
0 Wastage
100.00
Labour L.S
Total

0 O.H + Profit + I.Tex


Total
129 / Sft
1393 / Sq.m

Based:-
Description Qty. Unit
Remarks Bitumen 9.75 Kgs
Bitumen 20.25 Kgs
Hesian Clo 100.00 Sft
Polythene 200.00 Sft
Kerocin Oil 3.00 Liters
Earth 40.00 Cft
Cement 0.50 Bags
Sand 2.50 Cft
Brick Tiles 350.00 Nos.
Total
0 Wastage
100.00
Labour L.S
Total

0 O.H + Profit + I.Tex


Total
99 / Sft
1070 / Sq.m
Remarks

Remarks

0.0312 0.0312 0.00097344 0.194688


28.32
0.0275678208
100
2.75678208
1 CFt
Rate Amount
12.00 14.40
0.00

14.40
0.43
14.83
7.00 7.00
0.00

21.83

0.00
22.00
Previous analysis

Based:- 100 SFT


Description Qty. Unit Rate Amount Remarks Description
25mm topping 25mm topping
Cement 3.408 Bags 600.00 2044.80 Cement
Margalla 8.52 CFt. 85.00 724.29 Margalla
125mm base (1:2:4) 125mm base (1:2:4)
Cement 1;2:4 7.22 Bags 600.00 4330.20 Cement 1;2:4
Snad 9.022 CFt. 29.00 261.64 Snad
Sand LP 9.022 CFt. 65.00 586.43 Sand LP
Crush 36.088 CFt. 70.00 2526.16 Crush

Total 10473.51 Total


#REF!
Wastage #REF! Wastage
Labour 100 L.S 33.00 3300.00 Labour

Total #REF! Total


O.H0+ Profit + I.Tax #REF! O.H + Profit +
Total #REF!
Rate for
#REF!
Terrazzo
/ SftFlooring Rate for Terra
Rate for
#REF!
Terrazzo
/ Sq.m
Flooring Rate for Terra
Amount Remarks

1908.20
647.52

2044.70
120.52
328.68
1285.50

6335.12
190.05
4700.00

11225.17

0.00
11225.17
Ceramic Tiles ( On Floor ) with 1:3 40mm

Based:- 1 Sq.m
Description Qty. Unit Rate Amount
Ceramic Tiles 1.00 Sft 88.29 88.29
Cement 0.0325 Sq.m 600.00 19.50
Cement 0.010 Bags 600.00 6.00
Sand 0.121 Cft 29.00 3.51
Tile Bond 13.00
0.00
Total 130.30
3 Wastage 3.91
Labou L.S 40.00
Total 174.21

0 O.H + Profit + I.Tex 0.00


Total 174.21
Rate f 174 / Sft
Rate f 1874 / Sq.m

Ceramic Tiles with 20mm Plaster (1:4)

Based:- 1 Sq.m
Description Qty. Unit Rate Amount
Ceramic Tile 1.00 Sft 88.29 88.29
Cement 0.013 Sq.m 600.00 7.80
Cement 0.01 Bags 600.00 6.00
Sand 0.07 Cft 29.00 1.89
Tile Bond 0.03 LS 400.00 13.00

coverage 2.5 bags in 1bag cement 0.00


Total 116.97
3 Wastage 3.51
Labou L.S 40.00
Total 160.48

0 O.H + Profit + I.Tex 0.00


Total 160.48
Rate f 160 / Sft
Rate f 1727 / Sq.m
100 SFT
Rate Amount Remarks

12.00 192.00
8.00 120.00
600.00 300.00
29.00 72.50
9.50 3325.00

4009.50
120.29
18.00 1800.00

5929.79

0.00
5929.79
100 SFT
Rate Amount Remarks
80.00 780.00
80.00 1620.00
4.50 450.00
120.00 360.00
3.00 600.00
30.00 3000.00
11.00 440.00
600.00 300.00
29.00 72.50
9.50 3325.00
10947.50
0.00
20.00 2000.00
12947.50

0.00
12947.50

100 SFT Based:- 100 SFT


Rate Amount Remarks Description Qty. Unit Rate Amount
80.00 780.00 Bitumen 9.75 Kgs 80.00 780.00
80.00 1620.00 Bitumen 20.25 Kgs 80.00 1620.00
4.50 450.00 Hesian Clo 100.00 Sft 4.50 450.00
3.00 600.00 sand 5.00 Cft 65.00 325.00
120.00 360.00
11.00 440.00
600.00 300.00
29.00 72.50
9.50 3325.00
7947.50 Total 3175.00
0.00 0 Wastage 0.00
20.00 2000.00 100.00
Labour L.S 20.00 2000.00
9947.50 Total 5175.00

0.00 0 O.H + Profit + I.Tex 0.00


9947.50 Total 5175.00
52 / Sft
557 / Sq.m
Based:- 100 SFT
Qty. Unit Rate Amount Remarks

3.408 Bags 600.00 2044.80


8.52 CFt. 85.00 724.29
125mm base (1:2:4)
5.86 Bags 600.00 3516.00
7.325 CFt. 29.00 212.43
7.325 CFt. 65.00 476.13
29.3 CFt. 70.00 2051.00

Total 9024.64
#REF! #REF!
100 L.S 33.00 3300.00

Total #REF!
0 #REF!
Total #REF!
#REF! / Sft
#REF! / Sq.m
Remarks
Over head water tank

1 Cleanning 1 x 1 11.35 11.35

Total

2 Excavation 1500mm 1 x 1 11.35 11.35 1.5

Total

3 Excavation below 1500mm 1 x 1 11.35 11.35 0.3

Total

4 P.C.C 1 x 4 5.15 5.15 0.075


Plinth beam 1 x 1 24 0.4 0.075

Total
5 Form work
Col footings 4 x 4 5 0.25
PCC 4 x 4 5.15 0.075
Plinth beam 4 x 2 6 0.075

Total

Form work
Col FFL 4 x 4 0.7 2.125

Total

Form work
Col S/S 4M 4 x 4 0.6 4

Total

Form work
Col S/S 8M 4 x 4 0.6 4

Total

Form work
Col S/S 12M 4 x 4 0.6 4
Total

Form work
Col S/S 16M 4 x 4 0.6 4

Total

Form work
Col S/S 20M 4 x 4 0.6 4

Total

Form work
Col S/S 24M 4 x 4 0.6 4

Total

Form work
Col S/S 28M 4 x 4 0.6 4

Total

Form work
Col S/S 32.0 M 4 x 4 0.6 4

Total

Form work Plinth Beams


4 x 2 5.4 0.5

Total

Form Beams 4000


4 x 1 5.4 0.25
4 x 2 5.4 0.385
Lintels W1 4 x 1 1.8 0.23
4 x 2 2.7 0.45
4 x 2 0.23 0.45
Shades 4 x 1 2.7 0.45
4 x 2 3.6 0.137
D1 1 x 1 1 0.23
1 x 2 1.9 0.45
Shades 1 x 1 1.9 0.45
1 x 2 2.8 0.137

Total

Form Beams 8000


4 x 1 5.4 0.25
4 x 2 5.4 0.5

Total

Form Beams 12000


4 x 1 5.4 0.25
4 x 2 5.4 0.5

Total

Form Beams 16000


4 x 1 5.4 0.25
4 x 2 5.4 0.5

Total

Form Beams 20000


4 x 1 5.4 0.25
4 x 2 5.4 0.5

Total

Form Beams 24000


4 x 1 5.4 0.25
4 x 2 5.4 0.5
B4 1 x 1 9 0.25
1 x 2 9 0.5

Total
Form Beams 28000
4 x 1 11.2 0.6
4 x 2 11.2 0.87
1 x 2 5.4 0.25
2 x 2 5.4 0.5

Total

Form Beams 32000


4 x 1 11.2 0.6
4 x 2 11.2 0.415
1 x 2 5.4 0.25
2 x 2 5.4 0.415

Total

Form work Slab 4000


1 x 1 6.6 6.6
1 x 4 6.6 0.115

Total

Form work Slab 28000


1 x 1 11.2 11.2
1 x 4 11.2 0.23

Total

Form work for Slab 32000


1 x 1 11.2 11.2
1 x 4 11.2 0.115
man hole walls 2 x 4 0.6 0.2

Total

Form work for wall 28~32M


2 x 4 9.7 3.465

Beams Projection to tie


upper and lower beams 8 x 1 2.1 3.465

Total
RCC
Col footings 1 x 4 5 5 0.25
1 x 4 12.8042 0.55

Total

R.C.C
Col FFL 4 x 1 0.7 0.7 2.125

Total

R.C.C
Col S/S 4M 4 x 1 0.6 0.6 4

Total

R.C.C
Col S/S 8M 4 x 1 0.6 0.6 4

Total

R.C.C
Col S/S 12M 4 x 1 0.6 0.6 4

Total

R.C.C
Col S/S 16M 4 x 1 0.6 0.6 4

Total

R.C.C
Col S/S 20M 4 x 1 0.6 0.6 4

Total

R.C.C
Col S/S 24M 4 x 1 0.6 0.6 4

Total

R.C.C
Col S/S 28M 4 x 1 0.6 0.6 4

Total

R.C.C
Col S/S 32.0 M 4 x 1 0.6 0.6 4

Total

R.C.C bottom Slab of tank


Level 28000
1 x 1 11.2 11.2 0.23

Total

Concrete for wall 28~32M


1 x 4 9.7 0.23 3.465
Beams Projection to tie
upper and lower beams 8 x 1 0.75 0.6 3.465
Chamfer 0.5 x 4 9.7 0.1 0.1
0.5 x 4 3.465 0.1 0.1
Total

R.C.C Plinth Beams 4000


4 x 1 5.4 0.25 0.5

Total

R.C.C Beams 4000


4 x 1 5.4 0.25 0.385
Lintels W1 4 x 1 2.7 0.23 0.45
Shades 4 x 1 2.7 0.45 0.075
4 x 1 3.6 0.075 0.1
D1 1 x 1 1.9 0.23 0.45
Shades 1 x 1 1.9 0.45 0.075
1 x 1 2.8 0.075 0.1

Total

R.C.C Beams 8000


4 x 1 5.4 0.25 0.5

Total

R.C.C Beams 12000


4 x 1 5.4 0.25 0.5

Total

R.C.C Beams 16000


4 x 1 5.4 0.25 0.5

Total

R.C.C Beams 20000


4 x 1 5.4 0.25 0.5

Total

R.C.C Beams 24000


4 x 1 5.4 0.25 0.5
B4 1 x 1 9 0.25 0.5

Total

R.C.C Beams 28000


4 x 1 11.2 0.6 0.87
1 x 2 5.4 0.25 0.5
Total

R.C.C Beams 32000


4 x 1 11.2 0.6 0.415

1 x 2 5.4 0.25 0.415

Total

R.C.C Slab 4000


1 x 1 6.6 6.6 0.115

Total

R.C.C Slab 32000


1 x 1 11.2 11.2 0.115

man hole walls 1 x 4 0.6 0.1 0.2

Total

Grit on walls and bed


1 x 1 9.7 9.7
1 x 4 9.7 3.465
Columns 4 x 4 0.6 3.465

Total

Applying S.B.R prior to Grit


1 x 1 9.7 9.7
1 x 4 9.7 3.465
Columns 4 x 4 0.6 3.465

Total

Water Stoper

1 x 4 9.7 3.465
Total

135 MM sub-floor

1 x 1 6 6

Total

Floor

1 x 1 6 6

Total

230mm walls

1 x 4 5.4 3.5
Less -1 x 3 1.2 1.2
-1 x 1 1 2.1
Total

Plaster on walls

1 x 4 5.4 3.5

Total

Filling
Total Excvated Vol 1 232
Less P.C.C -1 8
Less footings -1 53
Less Col -4 0.7 0.7 0.925
Under Floor 1 7.2 7.2 1.2

Total

Water Proofing
1 x 1 9.7 9.7

Total

White Wash 1 x 1 5.4 5.4


1 x 4 5.4 4

Total
129

129 SM

193

193 CM

39

39 CM

8
1
0
9 CM

20
6
4

30 SM

24
0

24 SM

38
0
0
38 SM

38
0

38 SM

38
0

38 SM

38
0

38 SM

38
0

38 SM

38
0

38 SM

38
0

38 SM

38
0

38 SM

22
0

22 SM

5
17
2
10
1
5
4
0
2
1
1

48 SM

5
22

27 SM

5
22

27 SM

5
22

27 SM

5
22

27 SM

5
22
2
9

38 SM
27
78
3
11

119 SM

27
37
3
9

76 SM

44
3

47 SM

125
10

135 SM

125
5
1

131 SM

269
0
0
58
0
0
327 SM
25
28 5 0.78
5 0.78
A1 A2 Av Area
53 CM 25 0.6084 12.8042

4
0

4 CM

6
0

6 CM

6
0

6 CM

6
0

6 CM

6
0

6 CM

6
0

6 CM
6
0

6 CM

6
0

6 CM

6
0

6 CM

29
0

29 CM

30.922
0
12.474
0.194
0.069
43.659 CM

2.7
0

2.7 CM

2.079
1.118
0.365
0.108
0.197
0.064
0.021

4 CM

2.7
0

2.7 CM

2.7
0

2.7 CM

2.7
0

2.7 CM

2.7
0

2.7 CM

3
1
0

4 CM

23
1
0

24 CM

11
0
1
0

12 CM

5
0

5 CM

14.426
0
0.048

14.474 CM

94.09
134.442
33.264

261.796 SM

94.09
134.442
33.264

261.796 SM

0
134.442
0

134.442 RM

0
36
0

36 SM

0
36
0

36 SM

0
75.6
-4.32
-2.1
69.18 SM

0
75.6
0
0
75.6 SM

232
-8
-53
-1.813
62.208
0

231.395 CM
94.09
0

94.09 SM

29.16
86.4

115.56 SM
DIN TEXTILE UNIT-05 AKBAR AND ASSOCIATES
O.H.WATER TANK BILL OF QUANTITIES
S.NO. Description Quantity. Unit. Rate. Amount.
CIVIL WORKS
CONTRACTORS ARE ADVISED IN THEIR OWN
INTEREST TO VISIT THE SITE & OBTAIN ALL
NECESSARY INFORMATION REGARDING ACCESS
TO SITE FROM MAIN ROAD, GROUND CONDITIONS
SUPPLY SOURCES OF AGGREGATE / BRICKS
SUB-SOIL WATER CONDITIONS ETC.

1 General cleaning of shrubs, dumped waste or any


other un-wanted material using showel, excavator,
tractors, dumpers including disposal of material
outside plot premises upto one Kilometer.
Measurements for payment will be made from outer
to outer side of external foundation. 129.00 sq.m. 50.00 6,450.00
### 50.00 6450
- 0
2 Excavate for columns, wall footings in all - 0
kind of soil, hard, average, soft, silt and clay, - 0
backfill and mechanically compact excavation - 0
with suitable excavated material on completion of - 0
the respective works. Deposit and mechanically - 0
compact surplus excavated material in plinth or - 0
dispose up to a lead of one kilometer. - 0
- 0
a. Upto 1500mm depth. 193.00 cu.m. 424.00 81,832.00
### 424.00 81832
- 0
b. Below 1500mm upto 3000mm depth. 39.00 cu.m. 454.00 17,706.00
### 454.00 17706
- 0
3 Trim foundation of columns, wall and Ducts - 0
and mix, place, compact oversite - 0
concrete in the volumetric mix (1:4:8). 9.00 cu.m. 10,639.00 95,751.00
### 988.68 8898.12
- 0
4 Arrange steel plates, pipes, joints, runners, - 0
wood, nails and all other necessary material - 0
required for fabricate and fix in position, - 0
steel plate finish, watertight formworks for - 0
categories as mentioned below including - 0
true alignment, leveling, cleaning, and - 0
oiling of forms to produce smooth clean - 0
surface, at any height. - 0
- 0
a. Column foundation, ducts & trenches - 0
bases and walls. (Fair face finish). 30.00 sq.m. 500.00 15,000.00
### 500.00 15000
- 0
b. Plinth Beams 22.00 sq.m. 610.00 13,420.00 610.00 13420
- 0
b. Columns of any shape & size upto finish - 0
floor level (Fair face finish) 24.00 sq.m. 610.00 14,640.00
### 610.00 14640
- 0
c. Columns of any shape & size in Super - 0
structure (Fair face finish). - 0
- 0
i) Upto +4000mm 38.00 sq.m. 650.00 24,700.00
### 650.00 24700
- 0
ii) From +4000mm to +8000mm 38.00 sq.m. 670.00 25,460.00
### 670.00 25460
- 0
iii) From +8000mm to +12000mm 38.00 sq.m. 683.00 25,954.00
### 683.00 25954
- 0
iv) From +12000mm to +16000mm 38.00 sq.m. 696.00 26,448.00
### 696.00 26448
- 0
v) From + 16000mm to +20000mm 38.00 sq.m. 709.00 26,942.00 709.00 26942
- 0
vi) From 2000mm to +24000mm 38.00 sq.m. 722.00 27,436.00 722.00 27436
- 0
vii) From 24000mm to 28000mm 38.00 sq.m. 735.00 27,930.00 735.00 27930
- 0
viii) From 28000mm to 32000mm 38.00 sq.m. 748.00 28,424.00 748.00 28424
- 0
d. Beams and Lintels (Fair face finish) - 0
- 0
i) +4000mm 48.00 sq.m. 730.00 35,040.00
### 730.00 35040
- 0
ii) +8000mm 27.00 sq.m. 752.00 20,304.00
### 752.00 20304
- 0
iii) +12000mm 27.00 sq.m. 767.00 20,709.00
### 767.00 20709
- 0
iv) +16000mm 27.00 sq.m. 781.00 21,087.00
### 781.00 21087
- 0
v) +20000mm 27.00 sq.m. 796.00 21,492.00 796.00 21492
- 0
vi) 24000mm 38.00 sq.m. 810.00 30,780.00 810.00 30780
- 0
e. Wall, Beams and Slab - 0
- 0
i) slab at 4000mm 47.00 sq.m. 730.00 34,310.00 730.00 34310
- 0
ii) slab, walls and beams - 0
from 28000mm up to 32000mm 788.00 sq.m. 832.00 655,616.00 832.00 655616
- 0
5 Supply, straight, cut, bend, place in position at - 0
any level and height and tie steel - 0
reinforcement bars using 16 SWG binding - 0
wire complete. - 0
- 0
a. Deformed steel bars having tensile strength of - 0
4250 kg/sq.cm. 46.00 M.ton. 256,800.00 11,812,800.00
### 9,000.00 414000
- 0
b. Mild steel bars having tensile strength of - 0
2800 kg/sq.cm. - M.ton. -### 0
- 0
6 Supply, mix, place, compact, remove formwork - 0
and cure 250.0 Kg/sq.cm. concrete of minimum - 0
volumetric mix 1:2:4 at any height using - 0
approved quality sand and crush. - 0
- 0
a. Columns foundations. 53.00 cu.m. 14,376.00 761,928.00
### 1,129.00 59837
- 0
b. Plinth Beams 2.70 cu.m 14,659.00 39,579.30 2,033.95 5491.665
- 0
c. Beams, walls and lintels. - 0
- 0
i) +4000mm 4.00 cu.m 14,835.00 59,340.00
### 1,588.95 6355.8
- 0
ii) +8000mm 2.70 cu.m 15,280.00 41,256.00
### 2,033.95 5491.665
- 0
iii) +12000mm 2.70 cu.m 15,577.00 42,057.90
### 2,330.95 6293.565
- 0
iv) +16000mm 2.70 cu.m 15,873.00 42,857.10
### 2,626.95 7092.765
- 0
v) +20000mm 2.70 cu.m 16,170.00 43,659.00 2,923.95 7894.665
- 0
vi) +24000mm 4.00 cu.m 16,467.00 65,868.00 3,220.95 12883.8
- 0
vii) +28000mm 24.00 cu.m 16,764.00 402,336.00 3,517.95 84430.8
- 0
viii) +32000mm 12.00 cu.m 17,060.00 204,720.00 3,813.95 45767.4
- 0
d. Slab and walls - 0
- 0
i) +4000mm 5.00 cu.m 14,835.00 74,175.00 1,588.95 7944.75
- 0
ii) +32000mm 14.47 cu.m 17,060.00 246,926.44 3,813.95 55203.1123
- 0
7 Supply, mix, place, compact, remove - 0
formwork and cure 315.0 Kg / sq.cm concrete - 0
of minimum volumetric mix 1:1½:3 at any - 0
height using approved quality sand and crush. - 0
- 0
a. Column top of foundation upto finish - 0
floor level. 4.00 cu.m. 16,474.00 65,896.00
### 1,589.00 6356
- 0
b. Columns and walls in super structure . - 0
- 0
i) +4000mm 6.00 cu.m 16,651.00 99,906.00
### 1,765.50 10593
- 0
ii) +8000mm 6.00 cu.m 17,151.00 102,906.00
### 2,265.50 13593
- 0
iii) +12000mm 6.00 cu.m 17,484.00 104,904.00
### 2,598.50 15591
- 0
iv) +16000mm 6.00 cu.m 17,817.00 106,902.00
### 2,931.50 17589
- 0
v) +20000mm 6.00 cu.m 18,150.00 108,900.00 3,264.50 19587
- 0
vi) +24000mm 6.00 cu.m 18,483.00 110,898.00 3,597.50 21585
- 0
vii) +28000mm 6.00 cu.m 18,816.00 112,896.00 3,930.50 23583
- 0
viii) +32000mm 6.00 cu.m 19,149.00 114,894.00 4,263.50 25581
- 0
c. Bottom slab and walls from +28M to +32M 72.66 cu.m. 18,982.00 1,379,213.14 4,263.50 309781.6465
- 0
8 Supply and lay solid brick masonry in walls - 0
above finished floor level set in 1:4 cement - 0
sand mortar complete (See SP-01 for base Price) - 0
- 0
a. 230mm thick. 69.18 sq.m. 2,532.00 175,163.76 468 32376.24
- 0
9 Supply, mix and apply 20mm thick plaster in - 0
(1:4) cement sand mortar smoothly finished - 0
with steel trowel on internal surfaces of - 0
walls / ceiling etc. including splays, jambs, - 0
recesses, grooves etc. at any height. 75.60 sq.m. 447.00 33,793.20 247 18673.2
- 0
10 Supply, fix in position steel hinged shutter - 0
doors of 1½" x 1½" x ¼" angle iron frame and - 0
shutter made of 1½" x 1½" x 3/16" angle iron - 0
with 18 gauge M.S moulded sheet including - 0
locking arrangement complete at any height - 0
including one coat of anti rust paint - 0
three coats of enamal paint. 2.10 sq.m. 10,921.00 22,934.10 860 1806
- 0
11 Supply, fix in position steel Windows/ventilators - 0
of 1¼" x 1¼" x 3/16" size " Z " sections - 0
including providing and fixing 5mm thick - 0
plain glass and supply of all the material - 0
required for fixing of steel ventilators and glass - 0
complete at any floor and height including one coat - 0
of anti rust paint and three coats of enamal paint. 5.00 sq.m. 8,630.00 43,150.00 860 4300
- 0
12 Supply, place and mechanically compact in - 0
layers not exceeding 230mm thick using - 0
vibratory roller, pit sand ( kasso ) bought from - 0
sources outside the site complete in all - 0
respect. 231.40 cu.m. 1,624.00 375,785.48 318 73583.61
- 0
13 Supply, mix & spray anti-termite pestisides "Agenda" - 0
"Mirage"or "Fiprokil" obtained in sealed containers - 0
from approved sources and pressure sprayed in or on - 0
earth or wood (pressure 1.0 N/Sq.mm.) as per - 0
soecifications. 36.00 sq.m. 100.00 3,600.00 30 1080
- 0
14 Supply,
concrete mix, place
sub-floor usingandapproved
compactqualityplain
sand 1:4:8
and - 0
crush. - 0
- 0
a. 135mm thick 36.00 sq.m. 1,455.00 52,380.00 153 5508
- 0
15 Supply mix, place and compact smooth finish - 0
65mm thick concrete floor in ratio of 1:2:4 - 0
concrete in panels not exceeding 2000mm x - 0
2000mm complete. 36.00 sq.m. 1,108.00 39,888.00 270 9720
- 0
16 Supply and fixing in position over O.H.Water - 0
Tank M.S. manhole frame - 0
made of 1½" x 1½" x ¼" angle iron and - 0
cover made with 1¼" x 1¼" x 3/16" M.S - 0
angle iron including 12 gauge M.S. sheet on top - 0
with handle complete in all respect including one - 0
coat of antirust paint and three cats of enamal paint. 1.00 sq.m. 20,954.00 20,954.00
### 1,300.00 1300
- 0
17 Supply, lay bonding agent SBR or - 0
equivalent in between two layers of loom - 0
shed floor or elsewher for bonding of concrete - 0
to be laid as per manufacturers instructions - 0
complete. - sq.m. - - 0
- 0
18 Supply and lay smooth finish with steel trowel - 0
grit floor 15 mm. thick (1:2) over including - 0
hacking of R.C.C. base complete in all respect. 261.80 sq.m. 1,082.00 283,263.27
### 484.00 126709.264
- 0
19 Supply and fix in position PVC Water Stopper - 0
230mm wide complete in all respect 134.44 r.m. 800.00 107,553.60
### 100.00 13444.2
- 0
20 Providing all labour tools and plants for fixing - 0
Grouting of pipe sleves complete in all respect. 7.00 each 1,000.00 7,000.00
### 1,000.00 7000
- 0
21 Providing and laying water proofing and - 0
insulation treatment over roof in following - 0
manners. - 0
- 0
a. Laying of single layer polythene sheet - 0
weighing 100 germs per sq.m. - 0
over polyurethane insulation. - 0
- 0
b. Laying of 12mm thick layer of clean local sand - 0
Prior to lay steel mesh to provide a barrier - 0
to avoid doing damage the Polythin sheet - 0
- 0
c. Steel mesh using 1/4" dia of bar @ 300mm C/C -### 0
on both ways. - 0
- 0
d. Supply mix, place and compact smooth finish - 0
65mm thick screed in ratio of 1:2:4 concrete - 0
using one part Cement, two part sand and - 0
four part Margalla Crush. Steel trowel finish. - 0
- 0
e cutting and making groove 6mm x 20mm - 0
for panels 1200mm x 1200mm and groove - 0
filling with bitumen (80/100) and sand (1:2) - 0
material complete in all respect 94.09 sq.m. 1,473.00 138,594.57 500.00 47045
- 0
22 Supply, fabricating, welding and fixing in - 0
position M.S. stair complete with pipes, - 0
angles, plates, anchors bars, bolts etc. - 0
complete in all respect. 750.00 kg. 350.00 262,500.00
### 50.00 37500
- 0
23 Supply fabricate and fixing in position at any height - 0
hight & level 50mm M.S. Pipe railing 1.0 meter - 0
high complete in all respect. 45.00 R.M. 3,500.00 157,500.00
### 1,500.00 67500
- 0
24 Supply and fix in position M.S.galvanized 20mm dia - 0
rungs at any height as per drawing and specification - 0
and as per directed by the Engineer. 130.00 R.M. 1,000.00 130,000.00
### 1,000.00 130000
- 0
25 Supply and apply two coats of white - 0
wash at any floor & height including - 0
rubbing cleaning and base preparation of - 0
concrete / plastered surfaces. 115.56 sq.m. 89.00 10,284.84
### 50.00 5778
- 0
- 0
- 0
- 0
- 0
- 0
- 0
- 0
TOTAL AMOUNT OF CIVIL WORKS CARRIED TO SUMMARY Rs. 19,306,593.7 2,976,428.27
SPECIAL PROVISIONS

Note : All above items to be constructed as per drawings, specifications and directions of the Engineer
All quantities specified in B.O.Q are Estimated and may increase or decrease upto 20%.

SP-01 Base Price of Materials


1 Cement (Client's supply on fix Price) Rs, 22000 M.Ton Supply and deduction
2 Steel (Client's supply on fix Price) Rs, 240000 M.Ton Supply and deduction
3 Bricks (first Class burnt Bricks) Rs, 14000 per no.
4 Bricks Tiles Rs, 12000 per no.
5 Lawrence Pur Sand Rs. 145 Cu.ft.
6 Chenab Sand Rs, 50 Cu.ft.
7 Pit Sand ( Kasso) Rs, 30 Cu.ft.
8 Sargodha Crush Rs, 145 Cu.ft.
9 Margalla Crush/Toping Rs, 145 Kgs
10 M.S Angle and Channel Rs, 235 Kgs
11 M.S pipe Rs, 290 Kgs
12 GI corrugated sheet Rs, 290 Sq.m.
13 Ceramic Tile Rs, 1500 Sq.m.
14 Granito tile Rs, 2600 Sq.ft
15 Boticina Marble Rs, 400 Kg.
16 Polythen sheet Rs, 480 Kg.

SP-02 AGGREGATES AND MATRIALS

Approved Coarse and fine aggregates to be used in different parts of works as follows.

a. All reinforced cement concrete (RCC) sand and crush of approved quality.

b. All plain cement concrete floor (1:2:4 or 1:1½:3) sand and crush of approved quality.

c. All plain cement concrete (1:4:8, 1:3:6) sand and crush of approved quality.

d. Block (1:2:4) should proper size and shape.

e. Clean sand in Masonry mortar, plaster and pointing.

SP-03 Standard operating Procedure to Cope with Escalation:

There is high extent of uncertainty in Market due to Oil Prices. So the Parties of Contract will cope with
the Price variation in subsequent manners.
Up to 5% variation in Base Price, the Contractor will endure it on its own Risk and Cost. However,
variation in the Prices +/-5% shall be adjusted +/- from the IPC.The Contractor will provide the sufficient
evidence as per the S.O.P's to satisfy the Consultant and Client along with Claim.
The Claim Shall not be entertained and annulled otherwise.

SP-04 Standard operating Procedure to Cope with variations:

At any Stage, if the Contractor considers himself, is entitled to any additional payment because of
variation in Quantities. The Contractor will submit the claim immediately along with varied Quantities
incorporated with unit Price to get approval from Akbar and Associates.

CONTRACTOR'S SIGNATURE
GENERAL RATES LAHORE AND RAIWIND AREA 2022-2023
FOR NEW JOBS

S.NO. Description Quantity. Unit. Prime Rate. 2022 Prime Rate. 22-23 Percentage Change

Raiwind Area
Valid from ------------------- till end of -----------------------
CIVIL WORKS GROUND FLOOR:-

CONTRACTORS ARE ADVISED IN THEIR OWN


INTEREST TO VISIT THE SITE AND OBTAIN
ALL NECESSARY INFORMATION REGARDING
ACCESS TO SITE FROM MAIN ROAD,
GROUND CONDITIONS SUPPLY SOURCES OF
AGGREGATE / BRICKS AND SUB-SOIL WATER
CONDIITIONS ETC. HEIGHT BOTTOM OF SLAB
FOR DEPARTMENTS +4.2M TO +6.5M AND MAY
SLIGHTLY VARY AS PER FINAL DESIGN.

1 General cleaning of shrubs, dumped waste or any


other un wanted material using showel, excavator,
tractors, dumpers including disposal of materials
outside plot premises upto one kilometer.
Measurements for payment will be made from outer
outer to outer side of external foundation. - sq.m. 45.00 50.00 11.11 %

2 Excavate for columns, wall footings in all kind of


soil, hard, average, soft, silt and clay including dewatering
if required, backfill and mechanically compact excavation
with suitable excavated material on completion of
the respective works. Deposit and mechanically compact
compact surplus excavated material in plinth or dispose upto
a lead of one kilometer.

a. Upto 1500mm depth. - cu.m. 350.00 424.00 21.14 %

b. Below 1500mm depth - cu.m. 380.00 454.00 19.47 %

2a Excavate under floor for mouse ducts without dismantling


floor and dispose of excavated material upto a lead of one
a lead of one kilometer. - cu.m. 2,000.00 2,400.00 20.00 %

3 Trim foundation of columns, wall and ducts and


mix, place, compact (vibrate) oversite concrete in the
volumetric mix (1:4:8). - cu.m. 6,932.00 10,639.00 53.48 %

3a Trim foundation of Mouse ducts ducts and


mix, place, compact (vibrate) oversite concrete in the
volumetric mix (1:4:8). - cu.m. 8,310.00 12,746.00 53.38 %

4 Arrange steel plates, pipes, joints, runners,


wood, nails and all other necessary material
required for fabricate and fix in position,
steel plate finish, watertight formworks for
categories as mentioned below including
true alignment, leveling, cleaning, and
oiling of forms to produce smooth clean
surface, at any height.

a. Column foundation, ducts & trenches


bases and walls. (Ordinary). - sq.m. 485.00 500.00 3.09 %

b. Columns of any shape & size upto finish


floor level and Plinth beams (Ordinary) - sq.m. 585.00 610.00 4.27 %

c. Slab and walls for Drains, R.A. ducts


& cable trenches(Fair face finish). - sq.m. 585.00 610.00 4.27 %

d. Columns of any shape & size in Super


structure (Fair face finish). - sq.m. 630.00 650.00 3.17 %

e. Beams and Lintels (Fair face finish) - sq.m. 630.00 730.00 15.87 %

f. Slab, Projection and Pardi (Fair face finish). - sq.m. 630.00 730.00 15.87 %

g. Slab & walls supply air ducts, air


washers (Fair face finish). - sq.m. 630.00 730.00 15.87 %

h. Columns of any shape & size above roof


(Fair face finish). - sq.m. 630.00 730.00 15.87 %

j. Slab & walls and beams O. H. Water tank


(Fair face finish). - sq.m. 630.00 730.00 15.87 %

5 Straight, cut, bend, place in position at


any level and height and tie steel
reinforcement bars using 16 SWG binding
wire complete.

a. Deformed steel bars having tensile strength of


4250 kg/sq.cm. - M.ton. 182,740.00 256,800.00 40.53 %

b. Mild steel bars having tensile strength of


2800 kg/sq.cm. - M.ton. 182,740.00 256,800.00 40.53 %

6 Supply, mix, place, compact, remove formwork


and cure 250.0 Kg/sq.cm. concrete of minimum
volumetric mix 1:2:4 at any height using
approved quality sand and crush.

a. Column foundations. - cu.m. 9,202.00 14,376.00 56.23 %

b. Slab and walls for Drains and R.A. ducts. - cu.m. 9,343.00 14,659.00 56.90 %

c. Plinth Beams - cu.m. 9,343.00 14,659.00 56.90 %

d. Beams and lintels. - cu.m. 9,590.00 14,835.00 54.69 %

e. Slab, Projection and Pardi (steel trowel finish). - cu.m. 9,590.00 14,835.00 54.69 %

f. Slab & walls supply air ducts and air washers - cu.m. 9,626.00 14,835.00 54.11 %
g. Columns of any shape & size above roof. - cu.m. 9,626.00 14,835.00 54.11 %

h. O. H. Water tank. - cu.m. 9,626.00 14,835.00 54.11 %

7 Supply, mix, place, compact, remove formwork


and cure 315.0 Kg / sq.cm concrete
of minimum volumetric mix 1:1½:3 at any
height using approved quality sand and crush.

a. Column top of foundation upto finish


floor level. - cu.m. 10,569.00 16,474.00 55.87 %

b. Columns and walls in super structure. - cu.m. 10,640.00 16,651.00 56.49 %

c. O. H. Water tank. - cu.m. 10,675.00 16,651.00 55.98 %

8 Supply, mix, place, compact, remove formwork


and cure concrete of minimum volumetric
mix 1:3:6 at any floor and hight using approved
quality of sand and crush. - cu.m. 7,568.00 11,634.00 53.73 %

9 Supply and lay solid brick masonry in walls


upto finished floor level set in 1:4 cement
sand mortar complete. (See SP-01 for base Price)

a. 460mm thick. - sq.m. 4,176.00 4,887.00 17.03 %

b. 345mm thick. - sq.m. 3,132.00 3,665.00 17.02 %

c. 230mm thick. - sq.m. 2,088.00 2,444.00 17.05 %

d. 115mm thick. - sq.m. 1,105.00 1,286.00 16.38 %

9a Supply and lay solid brick masonry in Mouse ducts walls


upto finished floor level set in 1:4 cement
sand mortar complete (See SP-01 for base Price)

a. 460mm thick. - sq.m. 4,718.00 5,522.00 17.04 %

b. 345mm thick. - sq.m. 3,540.00 4,141.00 16.98 %

c. 230mm thick. - sq.m. 2,360.00 2,762.00 17.03 %

10 Supply and lay 40mm thick damp proof


course of (1:2:4) concrete with an admixture
PUDLO or equivalent. The quantity of
admixture to be as specified by the
manufacturer, including a flood coat of 10/20
bitumen on top @ 1.25 Kg. per sq.m. and a
layer of polythene sheet weighing 100 germs
per sq.m. - sq.m. 796.00 1,096.00 37.69 %

11 Supply and lay solid brick masonry in walls


above finished floor level set in 1:4 cement
sand mortar complete (See SP-01 for base Price)
a. 345mm thick. - sq.m. 3,204.00 3,774.00 17.79 %

c. 230mm thick. - sq.m. 2,136.00 2,532.00 18.54 %

d. 115mm thick. - sq.m. 1,157.00 1,420.00 22.73 %

e. 115mm thick above roof. - sq.m. 1,186.00 1,461.00 23.19 %

12 Supply, mix and apply 20mm thick plaster in


(1:4) cement sand mortar smoothly finished
with steel trowel on internal surfaces of
walls / ceiling etc. including splays, jambs,
recesses, grooves etc. at any height. - sq.m. 332.00 447.00 34.64 %

with steel trowel on external surfaces of walls,


projection including splays, jambs, recesses,
grooves, water drips, edges, rebates, at any
floor & height. - sq.m. 343.00 469.00 36.73 %

14 Supply, mix and apply 20mm thick neero


plaster (1:4) smoothly finished with steel
trowel on the walls and
bottom of supply air ducts including
making chamfers, corners complete. - sq.m. 384.00 506.00 31.77 %

15 Supply, mix and apply 20mm thick neero


plaster (1:4) smoothly finished with steel
trowel on walls and bottom of R/A ducts
including making chamfer corners complete. - sq.m. 373.00 495.00 32.71 %

15a Supply, mix and apply 20mm thick neero


plaster (1:4) smoothly finished with steel
trowel on walls and bottom of Mouse R/A ducts
including making chamfer corners complete. - sq.m. 424.00 560.00 32.08 %

15b Supply, mix and apply 40mm thick neero


plaster (1:4) smoothly finished with steel
trowel existing sub floor bottom/ Mouse R/A ducts slab
in 2 layers including making chamfer corners complete. - sq.m. 655.00 865.00 32.06 %

16 Supply, mix and apply 20mm thick plain


plaster (1:4) smoothly finished with steel
trowel on walls and bottom of ducts &
trenches including making chamfer corners
complete in all respect. - sq.m. 311.00 437.00 40.51 %

17 Supply, mix, and apply deep groove


pointing in (1:3) cement sand mortar on the
exterior surface of the wall including one
coat of red oxide complete in all respect. - sq.m. 300.00 439.00 46.33 %

18 Supply, fix in position steel sliding shutter


doors of 2" x 2" x ¼" angle iron frame and 16
gauge M.S. single corrugated sheet properly
braced to frame, including bottom & top rail,
locking arrangement and all the material
required for fixing complete in all respect, all
at any height including one coat of anti rust
paint and three coats of enamal paint. - sq.m. 9,716.00 12,665.00 30.35 %

19 Supply, fix in position steel hinged shutter


doors of 2" x 2" x ¼" angle iron frame and
shutter made of 1½" x 1½" x ¼" angle iron
with 16 gauge M.S. sheet including providing
a sliding wicket gate with locking arrangement
complete at any floor and height including one coat
of anti rust paint and three coats of enamal paint. - sq.m. 9,800.00 13,472.00 37.47 %

20 Supply, fix in position steel hinged shutter


doors of 1½" x 1½" x ¼" angle iron frame and
shutter made of 1½" x 1½" x 3/16" angle iron
with 16 gauge M.S moulded sheet including
locking arrangement complete at any height
including one coat of anti rust paint
three coats of enamal paint. - sq.m. 8,050.00 12,008.00 49.17 %

20a Supply, fix in position steel hinged shutter


doors of 1½" x 1½" x ¼" angle iron frame and
shutter made of 1½" x 1½" x 3/16" angle iron
with 18 gauge M.S moulded sheet including
locking arrangement complete at any height
including one coat of anti rust paint
three coats of enamal paint. - sq.m. 8,050.00 10,921.00 35.66 %

21 Supply, fix in position steel hinged louvered shutter


doors of 2" x 2" x ¼" angle iron frame and
shutter made of 1½" x 1½" x ¼" angle iron
1½" × ¼" Tee as divider with 2½" wide 16 gauge,
louver strips, locking arrangement and all respect at any
floor and height including one coat of anti rust paint
and three coats of enamel paint. - sq.m. 9,900.00 12,934.00 30.65 %

22 Supply, fix in position steel hinged louvered


ventilators made of 1½" x 1½" x ¼" angle iron frame and
1½" × ¼" Tee as divider with 2½" wide 16 gauge,
louver strips, locking arrangement and all respect at any
floor and height including one coat of anti rust paint
and three coats of enamel paint. - sq.m. 8,285.00 11,051.00 33.39 %

23 Supply, fix in position air tight doors (to be


supplied by Employer free fo cost) as per
drawings, specification, and upto the
satisfaction of Erector / Supplier. - sq.m. 660.00 800.00 21.21 %

24 Supply, fix in position steel ventilators


of 1¼" x 1¼" x 3/16" size " Z " sections
including providing and fixing 6mm thick
wired glass and supply of all the material
required for fixing of steel ventilators and glass
complete at any floor and height including one coat
of anti rust paint and three coats of enamal paint. - sq.m. 8,756.00 9,706.00 10.85 %
24a Supply, fix in position steel ventilators
of 1¼" x 1¼" x 3/16" size " Z " sections
including providing and fixing 5mm thick
wired glass and supply of all the material
required for fixing of steel ventilators and glass
complete at any floor and height including one coat
of anti rust paint and three coats of enamal paint. - sq.m. - 8,630.00 - %

25 Supply, fix in position bronze anodized


aluminium doors delux section of approved manufacturers
with locking arrangement, hydralic door closer of
approved make including 5mm thick approved quality
tinted glass complete with hardware etc.
(2.0mm section) at any floor and height. - sq.m. 11,500.00 16,000.00 39.13 %

26 Supply, fix in position bronze anodized


aluminium sliding windows in delux section of approved
manufacturers with locking arrangement including
5mm thick approved quality tinted glass complete
with hardware etc. ( 1.6mm section ) at any floor and hight. - sq.m. 8,200.00 12,374.00 50.90 %

27 Supply, fix in position bronze anodized


aluminium fixed windows in delux section of approved
manufacturers with locking arrangement including
5mm thick approved quality tinted glass complete
with hardware etc. (1.6mm section ) at any floor
and hight. - sq.m. 7,000.00 10,760.00 53.71 %

28 Supply, fix in position PVC doors of approved


quality and manufacturers complete with all hardware
at any floor and hight. - sq.m. 7,500.00 10,000.00 33.33 %

29 Supply, fabricate and fix in position at any floor


commercial ply veneered soild hinged shutters
38mm(1½")thick manufactured under power driven
hydraulic press of approved quality with galvanized
steel box frame of 50mm× 125mm (2" × 5") using
18 gauge Galvanized sheet, 50mm. × 12mm. Wood
beading on one sides, approved quality hardware,
approved quality imported Door Lock and 150mm.
wide stainless Steel kick plate and 150mm. ×
450mm. stainless Steel push plates on both faces,
spirit polishing on shutter.

a. 6"x2" box frame - sq.m. 10,500.00 15,750.00 50.00 %

b. 10½"x2" box frame - sq.m. 11,500.00 17,250.00 50.00 %

30 Supply, fix in position return air grill frame


(supplied by owner free of cost) complete in
all respect. - No. 500.00 600.00 20.00 %

32 Supply, fixing in position electric cable hanger in


in electric trenches complete in all respect. - Kg. 248.00 310.00 25.00 %

33 Suply, fix in position over R. A. Ducts


and Electric trenches M.S. manhole frame
made of 1½" x 1½" x ¼" angle iron and
cover made with 1¼" x 1¼" x 3/16" M.S
angle iron including 12 gauge M.S. sheet on top
with handle complete in all respect including one
coat of antirust paint and three cats of enamal paint. - sq.m. 10,500.00 20,954.00 99.56 %

34 Supply, place and mechanically compact in


layers not exceeding 230mm thick using
vibratory roller, pit sand ( kasso ) bought from
sources outside the site complete in all
respect. - cu.m. 812.00 1,624.00 100.00 %

35 Supply, mix & spray anti-termite pestisides "Agenda"


"Mirage"or "Fiprokil" obtained in sealed containers
from approved sources and pressure sprayed in or on
earth or wood (pressure 1.0 N/Sq.mm.) as per
soecifications. - sq.m. 75.00 100.00 33.33 %

36 Supply, lay in double layer best quality heavy


duty polythene sheet weighing 100 gms/sq.m under
floor including overlaps complete. - sq.m. 90.00 100.00 11.11 %

37 Supply, mix, place and compact plain 1:4:8


concrete sub-floor using approved quality sand and crush.

a. 135mm thick - sq.m. 936.00 1,455.00 55.45 %

b. 150mm thick - sq.m. 1,040.00 1,617.00 55.48 %

38 Supply, mix, place and compact smooth finish


65mm thick concrete floor in ratio of 1:1:3
concrete in panels not exceeding 2000mm x
2000mm complete. - sq.m. 841.00 1,285.00 52.79 %

39 Supply mix, place and compact smooth finish


65mm thick concrete floor in ratio of 1:2:4
concrete in panels not exceeding 2000mm x
2000mm complete. - sq.m. 729.00 1,108.00 51.99 %

40 Supply, mix, place and compact floor in panels


2000mm x 2000mm, at any floor, 25mm thick
(1:2) topping 1 cement to 2 Margalla crush aggregate
10mm uniform size over 1:2:4 concrete of
specified thickness as mentioned below in two
layers as per drawing ( bonding agent SBR
or equivalent to be used for binding of 1st & 2nd
layer of floor and to be paid under separate item ),
placing the top 25mm thick (1:2) within two hours of
laying of 2nd layer of RCC 1:2:4 floor complete
with grinding & chemical polishing ( mosaic finish)
complete in all respect.

a. Over 125mm. thick RCC 1:2:4 concrete - sq.m. 1,884.00 2,745.00 45.70 %

b. Over 100mm. thick RCC 1:2:4 concrete - sq.m. 1,668.00 2,434.00 45.92 %
c. Over 75mm. thick RCC 1:2:4 concrete - sq.m. 1,448.00 2,067.00 42.75 %

d. Over 50mm. thick RCC 1:2:4 concrete - sq.m. 1,203.00 1,696.00 40.98 %

41 Supply, lay bonding agent SBR or


equivalent in between two layers of loom
shed floor or elsewher for bonding of concrete
to be laid as per manufacturers instructions
complete. - sq.m. 200.00 236.00 18.00 %

42 Supply, lay 15mm (1:2) mosaic dado smooth finish with


steel trowel finish over 20mm thick plaster including
hacking of R.C.C. surface and macking chamfers and
corners complete in all respect. - sq.m. 850.00 1,082.00 27.29 %

43 Supply and fixing 300mm x 300mm or any approved


size of master glazed ceramics tiles including filling the
joints with neat cement slurry using matching pigments
leveling as per slope, curing, cleaning etc. complete in
all respect. (See SP-01 for base price.).

a. Over 40mm thick 1:3 on floor. - sq.m. 2,135.00 2,921.00 36.81 %

b. Over 20mm thick 1:4 plaster on walls. - sq.m. 1,963.00 2,667.00 35.86 %

44 Supply and fixing 400mm x 400mm Master Granito tiles


including filling the joints with ready made filing white/colour
leveling as per slope, curring, cleaning etc.
complete in all respect. (See SP-01 for base price.).

a. Over 40mm thick 1:3 on floor. - sq.m. 3,290.00 4,054.00 23.22 %

b. Over 20mm thick 1:4 plaster on walls. - sq.m. 3,118.00 3,800.00 21.87 %

45 Supply and fixing Boticina chemical polished marble


of approved quality including joint filling with
neat/colour cement slurry using matching pigments,
leveling as per slope, cleaning etc. complete in all
respect.

a. 20mm thick marble on shelves over 20mm thick


1:3 mortar (See SP-01 for base price.). - sq.m. 4,866.00 5,678.00 16.69 %

46 Supply and lay 115mm thick brick on edge soling


including grouting with chanab sand complete with
dressing of surface, compaction etc. sq.m. 948.00 1,025.00 8.12 %

47 Providing all labour tools and plants for making openings


in existing floor for grills and Manholes for Mouse ducts
and making good.

a) Grill openings upenings utpto (100mm x 1000mm ) - each 2,500.00 3,125.00 25.00 %

b) Manhole openings ( 600mm x600mm ) - each 2,800.00 3,500.00 25.00 %


48 Providing and fixing 20mm thick thermopore sheet
in expansion joints. - sq.m. 410.00 500.00 21.95 %

49 Supply and installation of approved quality gypsum


board false ceiling on aluminium Tee frame in
approved shade,colour and section with hanging
arrangement to RCC slab, Beams etc. at any floor
complete i/c making openings for tube lights etc. - sq.m. 1,076.00 1,500.00 39.41 %

50 Supply and laying water proofing and


insulation treatment over roof slab and S/A ducts slab
in following manners.

a. Supply and spray avg. 25-30 mm thick


polyurethane insulation from MASTER
CHEMICALS or equivalent including min 150mm
upturn with beams and parapet walls
(PU to be done by client).

c. Providing and laying 38mm thick burnt


clay tiles on 25mm thick mud mortar
(earth+tori) thick compacted earth and
grouting the burnt clay tiles with (1:4) cement
sand mortar smooth finish including making
of 125mm x 125mm chamfer in 1:4
cement sand mortar with beam and
walls complete in all respect. - sq.m. 0.00 %

51 Supply and laying water proofing and


insulation treatment over roof in following
manners.

a. Providing and applying primer coat of 80/100


bitumen @ 3.00 kg per % sq.ft. with mixture
3 liter of kerosene oil.

b. Providing and applying seal coat of 75% 10/20


bitumen & 25% 80/100 bitumen @ 12kg per % sft.

c. Providing and laying hassian cloth with


minimum 75mm overlap.

d. Providing and applying flood coat of 75% 10/20


bitumen & 25% 80/100 bitumen @ 15kg per % sft.
over hassian cloth.

e. Providing and laying polythene sheet 100 grams


per sq.m. over flood coat of bitumen.

f. Providing and laying 75mm thick


compacted earth over Polythin

g. Providing and laying 38mm thick burnt


clay tiles laid in mud mortar over 75mm
thick compacted earth and grouting the
burnt clay tiles with ( 1:4 ) cement sand
mortar smooth finish including making
of 125mm x 125mm chamfer in 1:4
cement sand mortar with beam and
supply air ducts walls complete in all
respect. - sq.m. 0.00 %

52 Supply and laying water proofing and


insulation treatment over roof in following
manners.

a. Providing and applying primer coat of 80/100


bitumen @ 3.00 kg per % sq.ft. with mixture
3 liter of kerosene oil.

b. Providing and applying seal coat of 75% 10/20


bitumen & 25% 80/100 bitumen @ 12kg per % sft.

c. Providing and laying hassian cloth with


minimum 75mm overlap.

d. Providing and applying flood coat of 75% 10/20


bitumen & 25% 80/100 bitumen @ 15kg per % sft.
over hassian cloth.

e. Providing and laying Thermopore sheet 40mm.


thick weighing one Kg. per Sq.m. density
wrapped in Polythene sheet (weighing 100
grams per Sq.m. bags).

f. Providing and laying 75mm thick


compacted earth over Polyurethane.

g. Providing and laying 38mm thick burnt


clay tiles laid in mud mortar over 75mm
thick compacted earth and grouting the
burnt clay tiles with ( 1:4 ) cement sand
mortar smooth finish including making
of 125mm x 125mm chamfer in 1:4
cement sand mortar with beam and
supply air ducts walls complete in all
respect. - sq.m. 0.00 - %

53 Supply and laying water proofing treatment


over roof in following manners.

a. Providing and applying primer coat of 80/100


bitumen @ 3.00 kg per % sq.ft. with mixture
3 liter of kerosene oil.

b. Providing and applying seal coat of 75% 10/20


bitumen & 25% 80/100 bitumen @ 12kg per % sft.

c. Providing and laying hassian cloth with


minimum 75mm overlap.

d. Providing and applying flood coat of 75% 10/20


bitumen & 25% 80/100 bitumen @ 15kg per % sft.
over hassian cloth.

e. Providing and spreading Lawrancepur sand on


coat of bitumen for blinding the surface. - sq.m. - - %

53a Providing and laying water proofing and


insulation treatment over roof in following
manners.

a. Supply and spray avg. 25-30 mm thick


polyurethane insulation from DIAMOND
CHEMICALS or equivalent including min 150
mm upturn with beams and parapet walls
( by client ).

b. Laying of single layer polythene sheet


weighing 100 germs per sq.m.
over polyurethane insulation.

c. Laying of 12mm thick layer of clean local sand


Prior to lay steel mesh to provide a barrier
to avoid doing damage the Polythin sheet

d. Steel mesh using 1/4" dia of bar @ 300mm C/C


on both ways.

e. Supply mix, place and compact smooth finish


65mm thick screed in ratio of 1:2:4 concrete
using one part Cement, two part sand and
four part Margalla Crush. Steel trowel finish.

f. cutting and making groove 6mm x 20mm


for panels 1200mm x 1200mm and groove
filling with bitumen (80/100) and sand (1:2)
material complete in all respect sq.m. 960.00 1,339.00 39.48 %

54 Supply mix, place and compact smooth finish


65mm thick screed over P.U. on roof in ratio of 1:2:4
concrete and making groove (10mmx10mm ) with cutter
for pannel 2000mm x 2000mm and groove filling with
bitumen sand (1:2) material complete in all respect. sq.m. - - %

55 Supply and apply three coats of approved


quality and shade SPD or vinyl emulsion paint
of Berger or ICI at any floor & height including
rubbing cleaning and base preparation of
plastered surfaces. - sq.m. 250.00 262.00 4.80 %

56 Supply and apply three coats of approved


quality and shade plastic emulsion paint
of Berger or ICI at any floor & height including
rubbing cleaning and base preparation of plastered surface - sq.m. 290.00 383.00 32.07 %

57 Supply and apply three coats of white/ chalk


wash to walls and ceiling etc. at any floor and
height complete in all respect including
preparation of surface at any floor and hight complete in
all respect. - sq.m. 68.00 89.00 30.88 %

58 Supply and apply three coats of approved


quality and shade weather shield paint
of Berger or ICI at any floor & height including
rubbing cleaning and base preparation of
plastered surfaces. - sq.m. 290.00 414.00 42.76 %

59 Supply and apply three coats of approved


quality and shade enamel paint of
Berger or ICI over ready made primer coat
and base preparation at any floor & height
including rubbing cleaning and preparing of
plastered surfaces. - sq.m. 360.00 457.00 26.94 %

60 Supply and apply three coats of approved


quality and shade enamel paint over one coat
of red oxide primer including preparation of
surface to be painted.

a. Steel doors, window and ventilators. - sq.m. 360.00 444.00 23.33 %

61 Supply and apply three coats of approved


quality and shade of chlorinated rubber paint of
Berger or equilent on walls and ceiling of A/C shower
chamber as per manufacturer instructions at any height. - sq.m. 650.00 683.00 5.08 %

63 Supply and fixing of P.V.C. pipe of in floor as electrical


electrical conduit complete in all respect.

a. 100mm dia. - r.m. %

b. 75mm dia. - r.m. %

c. 50mm dia. - r.m. %

64 Supply and fixing in position Return air or Supply air


fans (to be supplied by Employer free fo cost)
including fixing of formwork, providing and
laying of 1:2:4 concrete, plastering the surface
as per drawings, specification, and upto the
satisfaction of Erector / Supplier.

a. Supply air fans upto 1200mm dia - each 21,000.00 31,000.00 47.62 %

b. Return air fans upto 2000mm dia - each 29,000.00 43,000.00 48.28 %

65 Supplya and laying of insulation treatment to


supply air ducts walls and slab with fixing of expended
metal lathe over polyurethane spray ( done by client )
mix and apply 40mm thick 1:4 cement sand plaster smooth
finish over expended metal on external surface in all respect. - sq.m. 630.00 987.00 56.67 %

66 Supply and fixing in position RCC precast


rain water spout of approved design
complete i/c making & finishing of opening
in slab/purdi. - nos. 3,000.00 4,000.00 33.33 %

67 Supply and fixing in position at any level rain


water down pipes of approved make and
quality including fixing of tees, bends, elbows,
sockets etc. and cost of fixing arrangement
with columns, walls complete with paint in
approved colour.

a. 100mm. dia UPVC pipe - R.m. 1,250.00 1,329.00 6.32 %

68 Supply, lay, compact and cure 135mm thick


1:4:8 sub floor and 65mm thick 1:2:4 finish floor
laid in panels for plinth protection including
forming slopes. - sq.m. 1,654.00 2,563.00 54.96 %

69 Providing all labour tools and plants for


dismantling of concrete floor including
disposal of debris out side factory area. - cu.m. 2,200.00 2,530.00 15.00 %

70 Providing all labour tools and plants for


dismantling of reinforced concrete including
disposal of debris out side factory area. - cu.m. 4,150.00 4,750.00 14.46 %

71 Providing all labour tools and plants for


dismantling of brick masonry wall including
disposal of debris out side factory area. - cu.m. 1,375.00 1,580.00 14.91 %

72 Providing all labour tools and plants for


removing brick soling and stacking within factory area. - sq.m. 125.00 150.00 20.00 %

73 Providing all labour tools and plants for


removing doors/windows and stacking within factory - sq.m. 330.00 380.00 15.15 %
area.

74 Drilling and fixing of steel bar in existing structure i/c


chiping, drilling and steel fixing with SBR cleaning etc.
complete in all respect
a. #3 No 450.00 500.00 11.11 %
b. #4 No 500.00 550.00 10.00 %
c. #5 No 600.00 650.00 8.33 %
d. #6 No 750.00 850.00 13.33 %
e. #8 No 900.00 1,000.00 11.11 %

TOTAL PRIME COST OF CIVIL WORKS RS.

TOTAL COST OF CIVIL WORKS RS.


SPECIAL PROVISIONS

Note : All above items to be constructed as per drawings, specifications and directions of the Engineer
All quantities specified in B.O.Q are Estimated and may increase or decrease upto10%.
SP-01 Base Price of Materials
RAIWIND AREA
1 Cement (Client's supply on fix Price) M.Ton Rs, 22000
2 Steel (Client's supply on fix Price) M.Ton Rs, 240000
3 Bricks (first Class burnt Bricks) per 1000 Rs, 14000
4 Bricks Tiles per 1000 Rs, 12000
5 Lawrence Pur Sand Cu.ft. Rs. 145
6 Chenab Sand Cu.ft. Rs, 50
7 Pit Sand ( Kasso) Cu.ft. Rs, 30
8 Sargodha Crush Cu.ft. Rs, 145
9 Margalla Crush/Toping Cu.ft. Rs, 145
10 M.S Angle and Chenab Kgs Rs, 235
11 M.S pipe Kgs Rs, 310
12 GI corrugated sheet Kgs Rs, 310
13 Ceramic Tile Sq.m. Rs, 1500
14 Granito tile Sq.m. Rs, 2600
15 Boticina Marble Sq.ft Rs, 400
AKBAR AND ASSOCIATES
CONSULTING ENGINEERS

DIN TEXTILE MILLS LIMTED. UNIT-5 RAIWIND

CIVIL WORKS OF OVER HEAD WATER TANK

Date: August 04, 2022


B.O.Q.-S-01
S.NO. DESCRIPTION CAPACITY AMOUNT
GALLONS PRIME

CIVIL WORKS OF OVER HEAD WATER


TANK 60,000.00

TOP ELEVATION +32.00 M

TOTAL PRIME COST OF WORKS RS, 19,500,000.00

Note : All above items shall be executed as per drawings, specifications and directions of the Engineer
All quantities/cost specified in B.O.Q are/is estimated and may increase or decrease upto 20%.

C-406, 4th Floor, City Towers, 6-K, Gulberg-II, Lahore Ph. 042-5770033-4, Fax # 042-5770035
Email# aaalhe@wol.net.pk, aaalahore@yahoo.com
S.No. Description WATER TANKS Total Quantity. Unit.

CIVIL WORKS

1 General cleaning 0.000 sq.m.

1a Removing of soling i/c stacking 0.000 sq.m.

2 Excavation.

a. Upto 1500mm depth i.c. backfill/disposal. 0.000 cu.m.

b. Below 1500mm depth i.c. backfill/disposal. 0.000 cu.m.

3 C.C. 1:4:8 in foundations. 9.000 9.000 cu.m.

4 Supply,fabricate and fix formwork:

a. Column foundation,ducts & trenches bases

bases and walls. (Ordinary). 0.000 sq.m.

b. Columns of any shape & size upto finish

floor level (Ordinary) 0.000 sq.m.

c. Slab and walls for Drains, R.A. ducts, cable

trenches(Fair Face Finish). 0.000 sq.m.

d. Columns in Super structure (Fair face finish). 0.000 sq.m.

e. Roof Beams and lintels (Fair face). 0.000 sq.m.

f. Slab, Projection & Pardi (Fair face finish). 0.000 sq.m.

g. Slab & walls supply air ducts, air washers

(Fair Face Finish). 0.000 sq.m.

h. Columns above roof 0.000 sq.m.

j. O.H.Water Tanks 0.000 sq.m.

5 Supply and fix steel reinforcement.

a. Deform steel bars. 46.000 46.000 M.Ton.

b. Mild steel bars. 0.000 0.000 M.Ton.

6 Supply, mix & place 1:2:4 in:

a. Column foundations. 53.000 53.000 cu.m.

b. Drains, R/A ducts & cable trenches bases,

walls and slab. 0.000 cu.m.

c. Beams, lintels, air washer walls. 57.500 57.500 cu.m.

d. Slab, projection and pardi. 19.474 19.474 cu.m.

e. Slab and walls supply air ducts. 0.000 cu.m.

f. Columns above roof. 0.000 cu.m.

g. O.H.Water Tanks 0.000 cu.m.


7 Supply, mix & place 1:1½:3 in:

a. Columns from top of foundation upto FFL. 4.000 4.000 cu.m.

b. Columns in super structure. 120.659 120.659 cu.m.

c. O.H.Water Tanks 0.000 cu.m.

8 Supply, mix & place 1:3:6 0.000 cu.m.

9 Supply and lay solid brick masonry upto FFL.

a. 460mm thick. 0.000 sq.m.

b. 345mm thick. 0.000 sq.m.

c. 230mm thick. 0.000 sq.m.

d. 115 thick. 0.000 sq.m.

10 Supply and lay 40mm thick D.P.C. 0.000 sq.m.

11 Supply and lay solid brick masonry above FFL.

a. 460mm thick. 0.000 sq.m.

b. 345mm thick. 0.000 sq.m.

c. 230mm thick. 69.180 69.180 sq.m.

d. 115 thick. 0.000 sq.m.

e. 115mm thick above roof. 0.000 sq.m.

12 Supply and apply 20mm thick internal plaster. 75.600 75.600 sq.m.

13 Supply and apply 20mm thick external plaster. 0.000 sq.m.

14 S/A 20mm thick neero plaster S.A.Duct. 0.000 sq.m.

15 S/A 20mm thick neero plaster R.A.Duct. 0.000 sq.m.

16 Supply and apply 20mm thick plasterin electric trench. 0.000 sq.m.

17 S/A Deep groove pointing. 0.000 sq.m.

18 Supply & fix steel sliding shutter door. 0.000 sq.m.

19 Supply & fix steel hinged shutter door. (W/C) 2.100 2.100 sq.m.
20 Supply & fix steel hinged louvered shutter door. 0.000 sq.m.

21 Supply & fix steel hinged louvered ventilator. 0.000 sq.m.

22 Fixing of Fire proof door. 0.000 Set

23 Fixing in position air tight doors. 0.000 sq.m.

24 Supply and fix steel ventilators.

a. With 6mm thick wired glass. 0.000 sq.m.

b. With 5mm thick clear glass. 5.000 5.000 sq.m.

25 Supply and fix bronze aluminium doors. 0.000 sq.m.

26 Supply and fix bronze aluminium windows/vent. 0.000 sq.m.


27 Supply and fix bronze aluminium fixed glazing windows. 0.000 sq.m.

28 Supply and fix PVC doors. 0.000 sq.m.

29 Fixing return air grill frame. 0.000 No.

30 Supply and fix electric cable hanger. 0.000 KG.

31 Supply and fix M.S. manhole frame and cover. 0.000 sq.m.

32 S/C in plinth approved fill material. 231.395 231.395 cu.m.

33 Supply and lay antitermie proofing. 36.000 36.000 sq.m.

34 a. Supply lay 1:4:8 sub floor 135mm. thick 36.000 36.000 sq.m.

b. Supply lay 1:4:8 sub floor 150mm. thick 0.000 sq.m.

a. Supply lay 1:4:8 sub floor 100mm. thick 0.000 sq.m.

35 Supply, place and finish smooth 65mm 1:1:3. 0.000 sq.m.

36 Supply, place smooth finish 25mm 1:2 floor:

a. Over 125mm. thick 1:2:4 concrete 0.000 sq.m.

b. Over 100mm. thick 1:2:4 concrete 0.000 sq.m.

c. Over 75mm. thick 1:2:4 concrete 0.000 sq.m.

d. Over 65mm. thick 1:2:4 concrete 36.000 36.000 sq.m.

37 Supply and apply SBR (SBR 10ltr+water 5 ltr+cement 1 bag). 0.000 sq.m.

37a Shell godown water Proofing 0.000 sq.m.

water Proofing plain Area Screeding 65mm 94.090 94.090 sq.m.

38 Grit dado over 20mm thick plaster 261.796 261.796 sq.m.

39 Providing and fixing Glazed ceramic tiles:

a. Over 40mm thick 1:3 on floor. 0.000 sq.m.

b. Over 20mm thick 1:4 plaster on walls. 0.000 sq.m.

40 Providing and fixing Master Granito tiles.

a. Over 40mm thick 1:3 on floor. 0.000 sq.m.


b. Over 20mm thick 1:4 on walls. 0.000 sq.m.

c. Over 40mm thick 1:3 on treads, riser with 0.000 sq.m.

angle nosing.

41 Providing and fixing Booticina marble.

a. 20mm marble on 20mm thick 1:3 mortar. 0.000 sq.m.

42 P/L W.proofing without thermopore 0.000 sq.m.

43 P/L W.proofing and insulation treatment with PU. 94.090 94.090 sq.m.

44 P/L W.proofing with bitumen and L.P.sand spray 0.000 sq.m.

45 Supply and apply S. P. D. 0.000 sq.m.


46 Supply and apply plastic emulsion paint. 0.000 sq.m.
0 47 Supply & apply white/ chalk wash. 115.560 115.560 sq.m.

48 Supply and apply weather shield. 0.000 sq.m.

49 Supply and apply enamel paint to walls. 0.000 sq.m.

50 Supply & apply enamel paint.

a. Steel doors, windows and vents.. 14.725 14.725 sq.m.

51 Supply and apply rubber paint to slab and walls. 0.000 sq.m.

52 Steel embedded parts. 0.000 KG.

53 Providing and laying P.V.C. pipe.

a. 100mm dia. 0.000 R.M.

b. 75mm dia. 0.000 R.M.

c. 50mm dia. 0.000 R.M.

54 Fixing Return air or Supply air fans.

a. Supply air fans upto 1200mm dia 0.000 Each.

b. Return air fans upto 2000mm dia 0.000 Each.

55 P/L insulation treatment S.A.Duct wall. 0.000 sq.m.

P/L insulation treatment S.A.Duct wall. (with beam) 0.000 sq.m.

56 Supply & fix rain water down take pipe.

a. 100mm. dia UPVC pipe 0.000 R.M.

57 S/L 135mm 1:4:8 & 65mm 1:2:4 plinth protection. 0.000 sq.m.

58 Dismentling of existing floor. 0.000 cu.m.

59 Dismentling of C.C., R.C.C. 1:2:4 / 1:1½:3. 0.000 cu.m.

60 Dismentling of brick masonary. 0.000 cu.m.

61 Providing openings in existing florr

a. Grill openings upto 100x1000mm 0.000 Each.


b. Manhole openings 600x600mm 0.000 Each.

TOTAL ESTIMATED COST OF CIVIL WORKS.

Labour Cost

Material Cost

Total Cost of project


COST PRT SFT. #NAME? 88,572.000 #NAME?
###
1 P/F European WC. No.
2 P/F Asian WC. No.
3 P/F Wash hand basin No.
4 P/F urinals. No.
5 P/F Kitchen sink. (DOUBLE BOWL) No.
6 P/F Kitchen sink. (SINGLE BOWL) No.
7 P/F Hot and cold water mixer shower. No.
8 P/F bath room accessories sets. No.
9 P/F C.P.Bib-cock. No.
10 P/L G.I. pipe.
a. 15mm. Ø ( ½" ) R.M.
b. 20mm. Ø ( ¾" ) R.M.
c. 25mm. Ø ( 1" ) R.M.
d. 40mm. Ø ( 1½" ) R.M.
e. 50mm. Ø ( 2" ) R.M.
11 P/L C.I. pipe.
a. 50mm. Ø ( 2" ) R.M.
b. 75mm. Ø ( 3" ) R.M.
c. 100mm. Ø ( 4" ) R.M.
12 P/L R.C.C. pipe.
a. 100mm. Ø ( 4" ) R.M.
b. 150mm. Ø ( 6" ) R.M.
c. 230mm. Ø ( 9" ) R.M.
13 P/F floor trap 100mm. 4" dia. No.
14 Providing and making valve chamber. No.
15 Providing and fixin gully trap. No.
16 P/ making manhole upto 1200mm depth.
a. |600mm x 600mm. (inside dimension) No.
TOTAL BID PRICE OF PLUMBING WORKS.

SUMMARY
TOTAL BID PRICE OF CIVIL WORKS.

TOTAL BID PRICE OF PLUMBING WORKS.

TOTAL BID PRICE

LESS REABATE

TOTAL BID PRICE AFTER REBATE

% FROM LOWEST BIDDER


FAISAL SPINNING MILLS LIMITED UNIT - 2
SHEIKHUPURA - FAISALABAD ROAD
13-Apr-23

|APPROXIMATE QUANTITY OF
|MATERIAL REQUIRED AS PER B.O.Q.

1 Cement.

2 Pit sand

3 Chanab sand

4 L.P.Sand

5 Crush.

6 Floor crush.

7 Bricks

9 Tor steel

10 Mild steel
Rate Amount Tor Steel Mild Steel Binding Wire Cement L.P.Sand

- 30.195

- 47.380 460.000

- 0.000 0.000

- 336.905 421.131

- 0.000 0.000

- 365.510 456.888

- 123.790 154.738

- 0.000 0.000

- 0.000 0.000

- 0.000 0.000
- 32.490 30.459

- 980.047 918.794

- 0.000 0.000

- 0.000 0.000

- 0.000

- 0.000

- 0.000

- 0.000

- 0.000 0.000

- 0.000

- 0.000

- 32.307

- 0.000

- 0.000

- 13.018

- 0.000

- 0.000

- 0.000

- 0.000

- 0.000

- 0.000

- 0.225
- 0.000

- 0.000

- 0.000

- 0.000

- 0.310

- 0.000

- 0.000
- 0.000

- 0.000

- 0.000

- 0.000

- 0.000

- 16.305

- 0.000

- 0.000

- 0.000 0.000

- 0.000 0.000

- 0.000 0.000

- 0.000 0.000

- 27.612 14.303

0.000

- 215.982

- 0.000 0.000

- 0.000 0.000

- 0.000 0.000
- 0.000 0.000

- 0.000 0.000

- 0.000 0.000

- 37.946 47.421

- 0.00

-
-

- 0.000

- 0.000 0.000

- 0.000 0.000

- 0.000 0.000

- 0.000 0.000

- 0.000 0.000

-
-

47.380 0.000 460.000 2,212.643 2,043.734

7,331,232.00

#NAME?

#NAME?

Tor Steel (tons) Mild Steel (tons) Binding Wire (kg) Cement (bags) Lwarancepur
Sand (cu.ft.)
47.38 0.00 460.00 2,212.64 2,043.73

47.00 0.00 460.00 2,213.00 2,044.00


Covered area
Chanab Sand Floor Crush Crush White Cement SBR Kerri Polish

150.975 301.950

421.131 1,684.526

0.000 0.000

456.888 1,827.551

154.738 618.952

0.000 0.000

0.000 0.000

0.000 0.000
30.459 121.837

918.794 3,675.175

0.000 0.000

0.000 0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

169.612

0.000

0.000

68.346

0.000

0.000

0.000

0.000

0.000 0.000

0.000

0.843
0.000

0.000

0.000

0.000

1.628

0.000

0.000
0.000

0.000

0.000

0.000

0.000

81.527 177.930

0.000 0.000

0.000 0.000

0.000

0.000 0.000 0.000

0.000 0.000 0.000

0.000 0.000 0.000

14.303 32.634 28.606

0.000

247.659 142.417

0.000

0.000

0.000
0.000

0.000

0.000

99.237 189.685
0.000

0.000

0.000

0.000 0.000

2,816.139 175.051 8,626.212 0.000 0.000 0.000 0.000

Chanab Sand (cu.ft.) Floor Crush Crush (cu.ft.) White Cement SBR (ltr.) Kerri (bag) Polish
(cu.ft.) (bags)
2,816.14 175.05 8,626.21 0.00 0.00 0.00 0.00

2,816.00 175.00 8,626.00 0.00 0.00 0.00 0.00


Booticina Marble Glazed Tiles Glazed Tiles Bricks Brick Tiles Kassu Sliding Door
0.000

0.000

0.000

0.000

0.000

0.000

7,609.800

0.000

0.000

0.000
9,806.057

0.000

0.000

0.000
0.000

0.000

0.000 0.000

0.000
0.000

0.000

0.000 0.000 0.000 7,609.800 0.000 9,806.057 0.000

Booticina marble Master Granito Glazed Tiles Bricks ( Numbers ) Brick Tiles (No.) Kassu (Cu.ft.) Sliding Door
(sq.ft.) Tile ( sq.ft.) ( sq.ft.) (sq.ft.)
0.00 0.00 0.00 7,609.80 0.00 9,806.06 0.00

0.00 0.00 0.00 7,610.00 0.00 9,806.00 0.00


Hinged Door Louv. Door Louv. Vent. Hinged Door Air Tight Fire Proof Steel WIndow Steel vent.
22.604
0.000

0.000

0.000

0.000

0.000

53.800
22.604 0.000 0.000 0.000 0.000 0.000 0.000 53.800

Hinged Door Louv. Door Louv. Vent. Hinged Door Air Tight Fire Proof Steel WIndow Steel vent.
wicket gate(sq.ft.) (sq.ft.) (sq.ft.) (sq.ft.) Door (sq.ft.) Door (sq.ft.) (sq.ft.) (sq.ft.)
22.60 0.00 0.00 0.00 0.00 0.00 0.00 53.80

23.00 0.00 0.00 0.00 0.00 0.00 0.00 54.00


Wired Glass Plain Glass Structural steel Aluminium Aluminium Aluminium Cable Manhole
0.000

53.800

0.000

0.000
0.000

0.000

0.000

0.000
0.000 0.000

0.000 53.800 0.000 0.000 0.000 0.000 0.000 0.000

Wired Glass Plain Glass Structural Aluminium Aluminium Aluminium Cable Manhole
(sq.ft.) (sq.ft.) Steel (kg) Door (sq.ft.) Window (sq.ft.) Fixed Glazing Hanger Frame & Cover
(sq.ft.) ( each ) (sq.ft.)

0.00 53.80 0.00 0.00 0.00 0.00 0.00 0.00

0.00 54.00 0.00 0.00 0.00 0.00 0.00 0.00


Rubber Paint SPD Paint Plastic Paint Enamel Paint Weather shield Paint Primer Paint Filling Bitumen 10/20
0.000

0.000

0.000

0.000

0.000 0.000
0.000 0.000 0.000

0.000 0.000

0.000 0.000

9.483

0.000 0.000

0.000 0.000 0.000 9.483 0.000 0.000 0.000 0.000

Rubber paint SPD Paint Plastic Paint Enamel Paint Weather shield Paint Primer Paint Filling Bitumen
(Liters) (Liters) (Liters) (Liters) (Liters) (sq.ft.) (sq.ft.) 10/20 (kg)
0.000 0.00 0.00 9.48 0.00 0.00 0.00 0.00

0.00 0.00 0.00 9.00 0.00 0.00 0.00 0.00


Bitumen 80/100 Polythene Polyurothene Jute cloth 40mm. 20mm. PVC Pipe PVC Pipe
0.000
0.000 0.000 0.000

0.000 0.000

5.062 1,042.781 1,012.785

0.000 0.000 0.000


0.000

0.000

0.000

0.000 0.000

0.000

5.062 1,042.781 1,012.785 0.000 0.000 0.000 0.000 0.000

Bitumen Polythene Polyurothene Jute Cloth 40mm. 20mm. PVC Pipe PVC Pipe
80/100 (sq.ft.) (sq.ft.) (sq.ft.) (sq.ft.) thermopore thermopore 100mm. (Rft.) 75mm.(Rft.)
(sq.ft.) (sq.ft.)

5.06 1,042.78 1,012.78 0.00 0.00 0.00 0.00 0.00

5.00 1,043.00 1,013.00 0.00 0.00 0.00 0.00 0.00


PVC Pipe PVC Pipe Red Oxide Labour Wood fuel Steel Putty

2.00

2.00

2.00

2.50

4.00

3.50

4.00

5.00

5.50

5.50

5.50

5.50

5.50

5.50

1,650.00

1,650.00

4.50

5.25

6.00

6.00

6.00

6.00

6.00
5.50

7.00

7.00

5.50

6.00

5.00

4.50

3.50

3.50

6.00

5.50

5.00

4.00

4.50

3.25

3.25

3.25

3.00

3.25

3.50

0.000 20.00

0.617 15.00
0.000 15.00

0.000 15.00

0.000

20.00

0.000 15.00

15.00

15.00

15.00
15.00

15.00

125.00

7.50

20.00

1.50

2.00

2.00

2.00

2.00

3.50

9.00

9.00

8.50

8.00

2.00

8.00

11.00

11.00

11.00
11.00

15.00

11.00

5.50

5.50 0.5062042

5.50 0

1.75
2.00

1.00

1.75

2.00

1.576 2.00 0.2356

2.00

7.50

15.00

12.00

0.000 10.00

2,000.00

2,500.00

8.00

8.00

25.00

5.00

3.50

20.00

5.00

0.000 0.000 2.193 0.506 0.236

PVC Pipe C.I pipe Red Oxide wood fuel Steel Putty
50mm. (Rft.) 100mm. (Rft.) (Liters) kgs Kgs
0.00 0.00 2.19 0.51 0.24

0.00 0.00 2.00 0.00 0.51 0.24


AKBAR AND ASSOCIATES
CONSULTING ENGINEERS
DIN TEXTILE MILLS UNIT-05
(Capacity 60,000.00 Gallons approx.)
THE QUANTITIES MAY VARIES +/- 20.% ESTIMATED QUANTITY OF MATERIALS

The stated below material list is estimated to set maximum upper limit only for the reference of client. However, client needs to get purchase requisition by the contractor for
actual execution. We will provide a list at final stage or intermediate stage at the request of client in accordance with actual work done Quantities.

August 16,2022
VS VS
Planned
S.NO. Description Unit Rate Amount
QTY Purchased QTY Actaual QTY

1 Steel bars 47 Tons 235,000.00 11,134,300.00


2 Binding Wire 460.00 Kg. 300.00 138,000.00
3 Cement 2,212.64 Bags 1,050.00 2,323,275.00
4 Lwarancepur sand 2,043.73 Cft. 100.00 204,373.00
5 Chanab Sand 2,816.14 Cft. 40.00 112,646.00
6 Floor Crush 175.05 Cft. 100.00 17,505.00
7 Crush 8,626.21 Cft. 100.00 862,621.00
8 Bricks 7,609.80 No. 14.00 106,537.00
9 Ghassu 9,806.06 Cft. 30.00 294,182.00
10 Sliding Door Sft. 1,000.00 -
11 Hinged shtter doors 22.60 Sft. 800.00 18,084.00
12 Steel Ventilator 53.80 Sft. 375.00 20,175.00
13 Plain Glass 53.80 Sft. 200.00 10,760.00
14 Enamel Paint 9.48 Ltr. 750.00 7,112.00
15 Red Oxide paint 2.19 Ltr. 590.00 1,294.00
16 Steel Putty 0.24 Kgs 590.00 139.00
17 Bitumen 10/20 Kg. 150.00 -
18 Bitumen 80/100 5.06 Kg. 150.00 759.00
19 Polyurothane Sft. -
20 Polythene sheet 1,042.78 Sft. 5.00 5,214.00
21 Jute Cloth Sft. 5.50 -
22 Fire wood 0.51 Kgs 25.00 13.00
23 C.I. Pipe 100mm Rft. -
24 UPVC pipe 100mm Rft. -
25 SBR floor - Liter 450.00 -
26 Man hole top slab 10.76 Sft. 1,600.00 17,216.00
27 Water Stopper 441.10 Rft. 213.00 93,955.00
28 Stair material 750.00 kgs 290.00 217,500.00
29 Railling 45.00 R.m. 2,500.00 112,500.00
30
Misc.small items, plumbing, electrical works etc. not included therein. -
Total estimated cost of material Total 15,698,160.00

Total Material Cost Rs. 15,698,160.00

Note : All above items shall be executed as per drawings, specifications and directions of the Engineer
All quantities/cost specified in B.O.Q are/is estimated and may increase or decrease upto 20%.
C-406, 4th Floor, City Towers, 6-K, Gulberg-II, Lahore Ph. 042-5770033-4, Fax # 042-5770035
Email# aaalhe@wol.net.pk, aaalahore@yahoo.com

You might also like