SITE ACCEPTANCE TEST - GENERIC

Test procedure: Video recording

Testing Company: Client:


Site Representative(s): Client Representative(s):

Project: Client Representative(s) title(s):

1 MECHANICAL COMPLETION Accepted Comments Initials Date

Machine is assembled as per Vention design


Yes No N/A
1.1

Machine main frame and motion components are


rigidly assembled and secured. Yes No N/A
1.2

All axes are properly aligned


Yes No N/A
1.3

All pneumatic connections are secured and there is no


leak when holding the required pressure in the Yes No N/A
1.4 pneumatic system for 60 sec

2 ELECTRICAL COMPLETION Accepted Comments Initials Date

System wired and connected according to the


Automation System Diagram (ASD) Yes No N/A
2.1

Cable management is properly secured and does


not impede axes movement. Yes No N/A
2.2

All drives and devices power up without fault when


machine is turned on. Yes No N/A
2.3

All sensors (inductive, proximity & retro-reflective)


have been individually tested and are triggered Yes No N/A
2.4 when intended.

FUNCTIONAL & PERFORMANCE


3 Accepted Comments Initials Date
COMPLETION
The machine sequence starts when the operator
starts the program Yes No N/A
3.1

The machine sequence was able to successfully


execute the motion commands with the FAT Yes No N/A
3.2 samples

Workpieces of up to 100kg can be handled by the


machine Yes No N/A
3.3

Vention.io
4767 Rue Dagenais, Suite 104
Montreal, Quebec
H4C 1L8
The machine sequence can work in a loop, with no
stops without the assistance of an operator. Yes No N/A
3.4

Values can be input in both imperial and metric in


Yes No N/A
the user interface.
3.5

The machine can accommodate a throughput of X


Yes No N/A
workpieces per minute
3.6

Overall noise level during machine operation is


under 75 dB Yes No N/A
3.7

The machine is anchored to the ground


Yes No N/A
3.8

Integration Guide & User Manual have


been shared with the client Yes No N/A
3.9

Basic training has been conducted with operators


Yes No N/A
3.10

Maintenance guidelines have been shared


with the client Yes No N/A
3.11

4 SAFETY Accepted Comments Initials Date

Risk Assessment is completed and shared with the


client Yes No N/A
4.1

All E-stop buttons are individually tested and stops


the machine when pressed. Yes No N/A
4.2

E-stop activation immediately halts axes and


conveyor movement. Yes No N/A
4.3

Full safety enclosure is installed and


anchored to the ground Yes No N/A
4.4

The machine workspace zone is limited to operate


via a safety-rated zone limitation Yes No N/A
4.5

The machine goes back to standard operational


speed only when the fault is cleared and reset. Yes No N/A
4.6

Has the machine passed all validation and functionality tests: No