HOMEKRAFT PIOUS HIDEAWAYS – MARCH.

’2023
PROGRESS STATUS
DATED 31.03.2023
PIOUS HIDEAWAYS
8 ACRES 749 HOMES 12 TOWERS
TARGETS -PLAN OF
TOWER STATUS
Mar’2023

T1 TO T6 N/A Tower completed

T-7 N/A Tower completed

T-8 N/A Tower completed

T-9 N/A Tower completed

T-10 N/A Tower completed

T-11 N/A Tower completed

PIOUS HIDEAWAYS 3
T-12 N/A Tower completed
TARGETS -PLAN OF
TOWER STATUS
Mar’2023

T1 TO T6 N/A B/W Completed

T-7 N/A B/W Completed

T-8 N/A B/W Completed

T-9 N/A B/W Completed

T-10 N/A B/W Completed

T-11 N/A B/W Completed

PIOUS HIDEAWAYS 4

T-12 N/A B/W Completed


TARGETS -PLAN OF
TOWER STATUS
Mar’2023

T-1 TO T-6 N/A Tower completed

T-7 N/A Tower completed

T-8 N/A Tower completed

T-9 N/A Tower completed

T-10 N/A Tower completed

T-11 N/A Tower completed

T-12
PIOUS HIDEAWAYS
N/A Tower completed 5
TARGETS -PLAN OF
TOWER STATUS
Mar’2023

BASEMENT 1 POURS 1 POUR

PODIUM 2 POURS 2 POUR

PIOUS HIDEAWAYS 6
TARGETS -PLAN OF
TOWER STATUS
Mar’2023

T-1 TO T-6 N/A Tower completed

T-7 26TH TO 28TH Not Achieved

T-8 26TH TO 28TH


Achieved

T-9 N/A
Tower completed

T-10 30TH Comp. till 29th

T-11 N/A Tower completed

T-12 N/A Tower completed


PIOUS HIDEAWAYS 7
TARGETS -PLAN OF
TOWER STATUS
Mar’2023

T-1 TO T-5 N/A Tower completed

T-6 N/A Tower completed

T-7 N/A
Tower completed

T-8 N/A
Tower completed

T-9 30TH Achieved

T-10 21ST TO 25TH


Achieved

T-11 N/A
Tower completed

T-12 N/A
Tower completed
PIOUS HIDEAWAYS 8
TARGETS -PLAN OF
TOWERs STATUS
Mar’2023

T-1 TO T6 N/A Tower completed

T-7 N/A Tower completed

T-8 N/A Tower completed

T-9 N/A Tower completed

T-10 14TH TO 20TH Achieved

T-11 1ST TO 10TH WIP

T-12
PIOUS HIDEAWAYS 1ST TO 10TH WIP 9
TOWER-1

32ND FLOOR ROOF – Done


Terrace Structure Work - All structure work done
TOWER-2

30TH FLOOR ROOF – DONE


Terrace Structure Work - All structure work done
TOWER-3

30TH FLOOR ROOF – DONE


Terrace Structure Work - All structure work done
TOWER- 4

30TH FLOOR ROOF – Done


Terrace Structure Work - All structure work done
TOWER-5

30TH FLOOR ROOF – Done


Terrace Structure Work - All structure work done
TOWER-6

30TH FLOOR ROOF – Done


Terrace Structure Work - All structure work done
TOWER-7

30th FLOOR ROOF – Done


Above Terrace works- WIP
TOWER-8

30th FLOOR ROOF – Done


Above Terrace works- WIP
TOWER-9

30TH FLOOR ROOF – DONE


Above Terrace works- WIP
TOWER-10

30th FLOOR ROOF – Done


Above Terrace works- WIP
TOWER-11

30th FLOOR ROOF – Done


Above Terrace works- WIP
TOWER-12

27th FLOOR ROOF – Done


Above Terrace works- WIP
NON-TOWER

LAST MONTH PROGRESS- Feb’23 THIS MONTH PROGRESS – Mar’23