Sr. Item System Provided by NEWTRONIC Other Manufacturers Remarks


No.
1. Chamber Operations  Chamber Operations based on  Relying on traditional  ECOtronic System has led to significant gains in
ECOtronic system incorporating methods of controlling Power & Water Consumption compared to
the principles of Dew Point Temperature & Rh traditional methods
Control as per the
Psychrometric Chart leading to
90% saving in water & 70%
saving in Power Supply

 A Dew Point is the temperature


to which air must be cooled in
order to be saturated with the
water vapour already in the air
ie. temperature at which dew
will form

 Operations fine-tuned to work


perfectly well for Indian
conditions
2. Humidity System  Humidity is primarily  In other-makes, Humidity is  Humidity generation through steam-based
controlled through the generated through steam- humidifiers leads to an endless cycle wherein
principles of Dew Point as per based humidifiers through Cooling System & Humidity System have to work
boiler tank. As a result hot continuously in tandem. As a result, there is
the Psychrometric Chart.
Rh is generated in the significant Water & Power consumption
Walk-In leading to rise in
Temperature

 This rise in Temperature


leads to the requirement of
additional cooling

 Additional cooling leads to


condensation on the cooling
coil thereby requiring
additional humidity
Page 1 of 9
Last Modified Date: 1-Jul-2019
Sr. Item System Provided by NEWTRONIC Other Manufacturers Remarks
No.
requirement
3. Refrigeration  As per the new ECOtronic  Cooling System continues to  Technical details such as flow rate, Δt of cooling
System system, the cooling coil remain ON throughout the coils, auto-changeover upon failure of pump, etc
temperature is controlled as Chamber operations are not clear
per the Dew Point
 The claimed Chilling System  Chances of breakdown thereby increase
 Rh Conditions are therefore
achieved from ambient is more of a water-bath
with no definitive numbers  Additionally, breakdowns cannot be anticipated
humidity itself since moisture
absorption is minimal. on power & water well-in-advance & their preliminary diagnosis also
reduction pose a challenge
 It has also ensured the cooling
system is not ON continuously  It also leads to higher AHU
but rather switches ON only on requirements due to heat
a need-basis
dissipation inside the room
 The ON time of the cooling
system is required for only  No safety feature in the
approx. 8 hours in a time event of water-freezing or
period of 24 hours overflow of makeup tank

4. Further Advantages  No Utility area (of 800-  No such advantages  Absence of utility area has led to greater storage
of ECOtronic System 1000mm) on the back-side area within the Walk-In

 No deviations during short term  Less excursions has led to lesser filing of deviations
events of door opening &
power failure  Lesser failure of components & lesser breakdown of
Chamber
 Components operate only on a
need-basis
5. PLC-based Control  Complete Chamber Operations  The PLC is not of an  PLC is an advanced, reliable & real-time way of
System (for all Walk-Ins & Stand-alone established brand & executing the chamber operations
Humidity Chambers) are program logic is not very  It acts quickly to achieve & maintain the set
controlled via a PLC of very robust conditions
high-quality & reputed make  It has immunity to electrical noise, resistance to
 Also, there is no facility to vibrations and impact & facility for extensive
 There is a strong program logic send an email directly in input/output (I/O) arrangements
Page 2 of 9
Last Modified Date: 1-Jul-2019
Sr. Item System Provided by NEWTRONIC Other Manufacturers Remarks
No.
to ensure high performance case of deviations  An in-built memory within the PLC avoids additional
standards hardware & better data reliability

 An email alert directly from


the PLC in case of deviations

 To ensure Data Integrity, there  In other-makes, the HMI


is tamper-proof flow of data Display has an external
from PLC to Software. storage device port (such as
USB Port for Pen Drive)
thereby making the data
vulnerable to theft and
manual intervention. This is
a potential violation to
Data Integrity principles
6. Accurate  Temp Uniformity: ±1ºC  Temp Uniformity: ±2ºC  Very important documentary evidence for
determination of justification of sensor positioning in Walk-Ins. The
T/RH Uniformity  T/RH uniformity in Walk-Ins is  No such corresponding same is provided as part of PQ documents.
ensured through establishing features
an accurate air-pattern. This,  Auditors are increasingly asking for sensor
in turn, is established placement justification
scientifically from an air-flow
stimulation software

 Not only uniformity of


conditions are established but
also, Hot & Cold Zones, Dry &
Humid Zones are identified in
the Walk-Ins

7. Software  A server-based, web browser-  Currently no other software  Software ensures user team is real-time updated
based Software that ensures in the area of Stability with all events in your Stability & Micro
ease-of-access Chamber Management departments
offers so many features

Page 3 of 9
Last Modified Date: 1-Jul-2019
Sr. Item System Provided by NEWTRONIC Other Manufacturers Remarks
No.
 Robust design incorporating all  Operations ensure user team is ready for any
the requirements of 21 CFR surprise audits
Part 11
 Eliminate need of daily print outs & reduce
 Bouquet of additional features Operational Costs
for ease of operations. Refer
table below for complete
feature list

 Significant emphasis on Data


Integrity
8. Safety Measure  If there is a Temperature  The entire Walk-In or  When the entire chamber shuts down, the excursion
during Temp. Overshoot or Undershoot then Standalone chamber shuts period is significantly high leading to filing of
Overshoot / it will lead to the supply cut- down greater number of deviation reports & justification
Undershoot off of only that specific of the downtime
component which is faulty
9. Humidity Overshoot  A Hygrostat is provided to cut-  Not provided  If sample safety for high humidity is not available
safety off the humidifier at a value then it becomes difficult to comply with GMP safety
greater than 5%RH of set value. requirements.
10. Alarms  Separate recordings for alarms  No separate recording of  Full traceability not available
and events as and when they alarms & events. Also, user  Partial compliance with 21 CFR part 11
occur, with user comments. cannot enter any comments
Same is tracked in audit trails  No feature of additional  Additional alarms quickly provide the exact reason
 Additional alarms on circuit alarms of breakdown
failure & thermostat trips
11. Mobile Alert System  Only one modem and SIM card  Individual modem and SIM  An effective Mobile Alert System provides accurate
between all connected card for each chamber information, minimizes the need of user
chambers.  Message showing only intervention as well as additional hardware.
 Alert message with full prefixed message as
information having “Scanner alert”
 Name of chamber
 Alarm detail
 Sensor id &
 Present Value
12. Booster Cooling  If the chamber temperature  No such system provided  Efficient control of temperature leads to minimal
deviation is at least 2°C more excursion periods, effective stability tests &

Page 4 of 9
Last Modified Date: 1-Jul-2019
Sr. Item System Provided by NEWTRONIC Other Manufacturers Remarks
No.
than the set value then both reduced consumption of power
the primary Cooling system &
standby cooling system switch
on together to bring the
temperature within range
11. Surge Arrester  Surge Arrester is provided to  No such system provided  Electrical noise can interfere with the function of
filter electrical noise in-line other instruments in the lab. They go through
and noise generated by disturbance and may get damaged on long term
chambers. basis.
12. Component Working  Calculation of Working Hours  No such feature  Facilitates prompt Preventive Maintenance for
Hours for all major components better life

 Avoids maintenance related NCs

13. Standby Cooling Switchover to Standby systems is  Manual switchover requires  Requires additional documentation in SOPs & may
System  Automatic upon detection of change in the control void the validation
fault system wiring  Not an efficient way to execute manual switchover
 Scheduled (via Touchscreen)  Increases dependency on service team &
 Manual (via Touchscreen) engineering department
14. Standby Humidity Switchover to Standby systems is The switchover is only  Not providing scheduled or manual switchover will
System a. Automatic upon detection of automatic lead to unnecessary burden on the primary system
fault  Auditor can raise NCs on the operations of the
b. Scheduled (via Touchscreen) standby system and its usefulness
c. Manual (via Touchscreen)
15. Power Supply  Single phase for up to 30,000  3 phase even for Walk-Ins  Electrical load will be higher & it leads to higher
Litre capacity (& up to 70,000 as small as 4,000 Litres consumption of power
Litres in case of Walk-In
Humidity (Stability) Chambers

16. Service Engineers  NEWTRONIC also ensures  Knowledge of engineers are  In the event of a breakdown, the preliminary
engineers are well-trained with silo-based diagnosis & subsequent resolution are generally
all-round knowledge on handled by a single contact point. This decreases
important aspects of the breakdown time leading to lower excursion
refrigeration, humidity, period

Page 5 of 9
Last Modified Date: 1-Jul-2019
Sr. Item System Provided by NEWTRONIC Other Manufacturers Remarks
No.
electrical & software

Page 6 of 9
Last Modified Date: 1-Jul-2019
Introducing NEWTRONIC ICDAS v2.1 - A state-of-the-art Chamber Management Software

Page 7 of 9
Last Modified Date: 1-Jul-2019
S No Major Features Benefits
1 Server-based Installation, web browser-based 21 CFR Part 11 Requires no installation at Client-side
Ready Software Eliminates multiple software installations & qualifications
Ease-of-access: Accessible for any desktop/laptop

2 Perpetual License with unlimited no. of users Cost-effective requiring only one-time CAPEX expenditure

3 Restricted rights & privileges to access the system at user- Very Important from Data Integrity point of view
level

Flexibility of defining multiple user-groups such as Operator


Supervisor, Authorization, Admin, Super-Admin (at Plant-
level)

There is also Departmental segregation of chambers, data


and users

4 e-Review, e-Approval, e-Signature, e-Comments of: Make your plant paperless & eliminate the task of daily print-
 Data Logs outs
 Alarms
 Audit Trails
 Equipment Parameter Modifications
5 Comprehensive Audit Trails: Audit Trails are becomingincreasingly important from Auditor
 Alarms point of view
 Alarm Acknowledgement
 User Activity
 Equipment Activity
 email Audit Trail
 SMS Audit Trail

6 Customized SMS & Email Alarms to Engineering & Lab users Ensures the involvement of the correct team to attend to an
activity

Page 8 of 9
Last Modified Date: 1-Jul-2019
7 System generated proactive emails on pending activities: Staying audit-ready on a daily basis
 Data Pending for Review
 Data Pending for Approval
 Alarms Pending for acknowledgement
 Pending database archival

8 A real time window user can see status of all connected Very Important screen for ease-of-operations. User can
chambers in one window at same time attend to only those items that flash in RED, if any
9 Viewing I/O Status & Running Hours of all major components Leads to effective Preventive Maintenance activities
10 Automatic & Manual daily data backup facility. Automatic
data backup can be done both, remotely & locally
11 Online Diagnosis For faster resolution to any software/PLC matters
12 Harmonization of reporting format (header, footer, etc) &
other such operations throughout the plant
13 Various inbuilt security features such as 2-level
authentication, password aging, auto-logout, security
lockout, password re-confirmation, etc
14 Ability to calculate MKT (Mean Kinetic Temperature)
15 Possible to connect to all leading LIMS packages

Page 9 of 9