Professional Documents
Culture Documents
Projek Penswastaan Lebuhraya Bertingkat Sungai Besi - Ulu Kelang (Suke)
Projek Penswastaan Lebuhraya Bertingkat Sungai Besi - Ulu Kelang (Suke)
METHOD STATEMENT
PRECAST PARAPET
Document No. :
**
Revision :
00
Date Issued :
23 July 2018
REVISION ISSUE
DETAILS OF REVISION
NO. DATE
00 23/07/2018 First submission
TABLE OF CONTENTS
1.1 Purpose
This method statement is issued to describe the procedure to be carry out for parapet
construction works to ensure that the work is planned and performed in accordance with technical
specification and drawings.
2.1 Abbreviations
Abbreviation Definition
PLSUSB Projek Lintasan Sungai Besi – Ulu Kelang Sdn. Bhd.
Employer Turnpike Synergy Sdn. Bhd.
SUKE Sungai Besi – Ulu Kelang Elevated Expressway
SC Supervising Consultant
SMPP Syarikat Muhibbah Perniagaan & Pembinaan Sdn. Bhd.
2.2 Definitions
Terms Definition
Project Sungai Besi – Ulu Kelang Elevated Expressway
Work Package Contractor Syarikat Muhibah Perniagaan & Pembinaan Sdn. Bhd.
Sub-contractor China Communications Construction Company (M) Sdn Bhd
Table 2.1: Table of Definitions
3.0 References
3.1 Project Documents
Document Number Document Title
SUKE-SMPP-CA3-QMS-PQP-000001 Project Quality Plan
SUKE-SMPP-CA3-QMS-PSP-000001 Safety & Health Plan
SUKE-SMPP-CA3-QMS-EMP-000001 Environmental Management Plan
SUKE-SMPP-CA3-ITP-CIVS-00000** Inspection & Test Plan
3.2 Standards
Document Number Document Title
Section 9 Concrete Works (JKR/SPJ/2008)
Section 15 Parapet (JKR/SPJ/2013)
Table 3.2: List of References - Standard
4.0 Resources
4.1 Plant and Machineries
No Type Quantity Remark/ Purpose
1 Gantry crane-10t 2 To do lifting works
2 Mixing plant-1.5m3 2 To batch Concrete.
3 Bar Bending Machine 1 To bend steel bar.
4 Bar Cutting Machine 1 To cut the steel reinforcement as per drawing.
5 Concrete Mixer Truck 2 Transportation and casting of concrete
6 Concrete Pump 1 To pump concrete into the mould.
7 Concrete Vibrator 2 To mix concrete, Concrete compaction
8 Genset 3 To generate/supply electricity
Table 4.1: List of Plant and Machineries
4.2 Manpower
No Description Quantity Remark/ Purpose
1 Construction Manager 1 To decide and delegate works
2 Site Engineer 2 Supervision during the whole process
3 Testing Supervisor 1 To monitor of the cube making
4 Safety Supervisor 1 To enforce the safety precaution on site.
5 Environmental officer 1 To enforce DOE requirement on site.
6 QA/QC Engineer 1 To monitor the quality of the precast parapet.
7 Bar bender 8 Cutting, bending and fixing of rebar
8 Form worker 4 To prepare and erection of formwork
9 Concreter 4 To execute the concrete works.
11 Crane Operator 2 To operate the crane.
12 Repairman 1 Mechanical and electrical repair
13 General worker 3 To execute work assigned.
Total 29
Table 4.2: List of Manpower
4.3 Material
No Description Remark/ Purpose
1 M.S. Galvanized post To be fixed in the parapet structure.
2 Cement mortar 10mm in thick.
Dia.20mm m.s. galvanized bolt completed with nuts and
3 U-shape bolt
washes.
3 uPVC duct 82mm (Dia) (Embedded at the cast in-situ part of parapet).
16mm (Dia) x 250mm(L),Grade 4.6 complete with nuts
4 Bolt
(check IFC drawing (klu ada) sbb biasa pkai gred 8.8)
5 Concrete(G40/20) To be used to concrete parapet.
7 Rebars To be used in the structure.
8 Axel 905D To be used as a curing compound.
Table 4.3: List of Materials
Material lain dh submit utk approval x..klu x submit utk approval dlu
d) The shop drawing for the details measurement or dimension of the steel formwork may
refer to the attachment in Appendix A
e) The inspection of steel formwork will be conducted during pre-concreting work to ensure
assemble of steel formwork is according to the submitted shop drawing.
f) The surface of the steel formwork should be clean from any debris or leftover concrete
before proceed with concreting work.
g) Temperature of concrete mix at the time of placing shall be monitored randomly and shall
not exceed 36° C referring to specification clause 9.5.6 placement temperature clause (b).
a) The periods of time for formwork should be remove is as per technical specification under
the section 9 for concreting with the sub-clause 9.8.4 which is removal of forms.
b) Formwork will be remove without such shock or vibration which might cause damaged to
the formwork or the precast parapet structure.
c) Upon the removing of formwork, no further loads should imposed to the precast parapet
until at least the curing periods complete or until such later time in as in the opinion of
consultant which the precast parapet attained sufficient strength to safety withstand loads.
b) Roughened surface shall be covered with damp absorbent material (gunny sack) or other
approved concrete retarder before proceeding the next level .
Please refer to the Appendix D for details of construction sequence on parapet works.
Fire
Electric Hazard,
Accident due to Equipment Failure
Major traffic accident when mobilization & demobilization of
equipment/machineries
Lifting failure
Escape of Combustible or Toxic Material
7.4 Housekeeping
Housekeeping is an essential part of safety for the daily routine. Housekeeping would
include the following items:
Maintain access/egress to all working area.
Store and stack all construction materials in safe and orderly manner.
No littering around the site.
Refer to Inspection and Test Plan as per attached for Quality Control Inspection Checklist
SUKE-SMPP-CA3-ITP-GEO-000006.
RFIs and respective Permit to Work shall be submitted prior execution of any construction
activities. In additional to this requirement weekly walk-about will be conducted to measurement,
analysis and propose for improvement as construction activities are on-going.
Appendix A
Appendix B
Appendix C
Appendix D
Construction Sequences for Parapet Work
Stage 1
Ensure the dimension & usage of parapet
confirmed as per construction drawing
Stage 2
Inspect the cleanliness, dimension &
embedded item as per construction
drawing
Not okay
Stage 4
Sample to be taken for cube compressive
Placement of fresh concrete and concrete
strength test
vibration works
Stage 5
Dismantle of steel formwork
Stage 6
Apply curing compound on parapet
Stage 7
Transport to the provide yard storage
Stage 8
Stacking properly at storage yard before
transport to the usage location