Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 18

SYARIKAT MUHIBAH PERNIAGAAN & PEMBINAAN SDN. BHD.

PROJEK PENSWASTAAN LEBUHRAYA


BERTINGKAT SUNGAI BESI – ULU KELANG (SUKE)

METHOD STATEMENT
PRECAST PARAPET

CONSTRUCTION AND COMPLETION OF MAINLINE


AND OTHER ASSOCIATED WORKS
PACKAGE: CA3
(CH. 4200 TO CH. 7800)

Document No. :
**

Revision :
00
Date Issued :
23 July 2018

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 1 of 18


**
REVISION HISTORY

REVISION ISSUE
DETAILS OF REVISION
NO. DATE
00 23/07/2018 First submission

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 2 of


18
**
PRECAST PARAPET Revision: 00

TABLE OF CONTENTS

1.0 General Introduction...................................................................................................5


1.2 Purpose...........................................................................................................................5
1.2 Location of Precast Yard................................................................................................5
2.0 Abbreviations and Definitions.....................................................................................5
2.1 Abbreviations.................................................................................................................5
2.2 Definitions......................................................................................................................6
3.0 References.........................................................................................................................6
3.1 Project Documents.........................................................................................................6
3.2 Standards........................................................................................................................6
4.0 Resources..........................................................................................................................6
4.1 Plant and Machineries....................................................................................................6
4.2 Manpower.......................................................................................................................7
4.3 Material..........................................................................................................................7
5.0 Precast Parapet Work Procedure...................................................................................7
5.1 Steel Parapet Mould (Formwork)...............................................................................7-8
5.2 Reinforcement Work......................................................................................................8
5.3 Placing Concrete............................................................................................................8
5.4 Compacting Concrete.....................................................................................................9
5.5 Precaution for concreting during heavy rain..................................................................9
5.6 Erections / Dismantle of Steel Formwork......................................................................9
5.7 Curing Work.............................................................................................................9-10
5.8 Lifting, Handling and Stacking of Precast Members...................................................10
5.9 Construction Sequences for Parapet Works.................................................................10
6.0 Safety and Health Requirement...................................................................................11
6.1 Job Safety Analysis......................................................................................................11
6.2 Information to Personnel..............................................................................................11
6.3 Emergency Arrangements.......................................................................................11-12
6.4 Permit Requirement......................................................................................................12
7.0 Environmental Issue......................................................................................................13
7.1 Environmental Aspects, Impacts & Control Measures................................................13

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 3 of 18


**
PRECAST PARAPET Revision: 00

7.1 Air Quality and Noise..................................................................................................13


7.2 Waste Management......................................................................................................13
7.3 Temporary Drainage System........................................................................................13
7.4 Housekeeping...............................................................................................................13
8.0 Quality Assurance and Quality Control
8.1 Contractual Requirements
8.2 Inspection and Testing
8.3 Follow up and Evaluation
Appendix A : Shop Drawing Precast Parapet Steel Mould (Formwork)
Appendix B : Construction Drawing for Parapet Work
Appendix C : Concrete Curing Compound
Appendix D : Construction Sequences for Parapet Works

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 4 of 18


**
PRECAST PARAPET Revision: 00

1.0 General Introduction


This method statement serves as guidelines and explaining the procedures for all the
necessary works to be carried out for precast parapet for the Construction and Completion of
Proposed Sungai Besi – Ulu Kelang Elevated Expressway (SUKE).

1.1 Purpose
This method statement is issued to describe the procedure to be carry out for parapet
construction works to ensure that the work is planned and performed in accordance with technical
specification and drawings.

1.2 Location of Precast Yard

Figure 1: Location of Precast Yard

2.0 Abbreviations and Definitions

2.1 Abbreviations

Abbreviation Definition
PLSUSB Projek Lintasan Sungai Besi – Ulu Kelang Sdn. Bhd.
Employer Turnpike Synergy Sdn. Bhd.
SUKE Sungai Besi – Ulu Kelang Elevated Expressway
SC Supervising Consultant
SMPP Syarikat Muhibbah Perniagaan & Pembinaan Sdn. Bhd.

Table 2.1: Table of Abbreviations

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 5 of 18


**
PRECAST PARAPET Revision: 00

2.2 Definitions
Terms Definition
Project Sungai Besi – Ulu Kelang Elevated Expressway
Work Package Contractor Syarikat Muhibah Perniagaan & Pembinaan Sdn. Bhd.
Sub-contractor China Communications Construction Company (M) Sdn Bhd
Table 2.1: Table of Definitions

3.0 References
3.1 Project Documents
Document Number Document Title
SUKE-SMPP-CA3-QMS-PQP-000001 Project Quality Plan
SUKE-SMPP-CA3-QMS-PSP-000001 Safety & Health Plan
SUKE-SMPP-CA3-QMS-EMP-000001 Environmental Management Plan
SUKE-SMPP-CA3-ITP-CIVS-00000** Inspection & Test Plan

Table 3.1: List of References ~ Contractual Documents

3.2 Standards
Document Number Document Title
Section 9 Concrete Works (JKR/SPJ/2008)
Section 15 Parapet (JKR/SPJ/2013)
Table 3.2: List of References - Standard

4.0 Resources
4.1 Plant and Machineries
No Type Quantity Remark/ Purpose
1 Gantry crane-10t 2 To do lifting works
2 Mixing plant-1.5m3 2 To batch Concrete.
3 Bar Bending Machine 1 To bend steel bar.
4 Bar Cutting Machine 1 To cut the steel reinforcement as per drawing.
5 Concrete Mixer Truck 2 Transportation and casting of concrete
6 Concrete Pump 1 To pump concrete into the mould.
7 Concrete Vibrator 2 To mix concrete, Concrete compaction
8 Genset 3 To generate/supply electricity
Table 4.1: List of Plant and Machineries

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 6 of 18


**
PRECAST PARAPET Revision: 00

4.2 Manpower
No Description Quantity Remark/ Purpose
1 Construction Manager 1 To decide and delegate works
2 Site Engineer 2 Supervision during the whole process
3 Testing Supervisor 1 To monitor of the cube making
4 Safety Supervisor 1 To enforce the safety precaution on site.
5 Environmental officer 1 To enforce DOE requirement on site.
6 QA/QC Engineer 1 To monitor the quality of the precast parapet.
7 Bar bender 8 Cutting, bending and fixing of rebar
8 Form worker 4 To prepare and erection of formwork
9 Concreter 4 To execute the concrete works.
11 Crane Operator 2 To operate the crane.
12 Repairman 1 Mechanical and electrical repair
13 General worker 3 To execute work assigned.
Total 29
Table 4.2: List of Manpower

4.3 Material
No Description Remark/ Purpose
1 M.S. Galvanized post To be fixed in the parapet structure.
2 Cement mortar 10mm in thick.
Dia.20mm m.s. galvanized bolt completed with nuts and
3 U-shape bolt
washes.
3 uPVC duct 82mm (Dia) (Embedded at the cast in-situ part of parapet).
16mm (Dia) x 250mm(L),Grade 4.6 complete with nuts
4 Bolt
(check IFC drawing (klu ada) sbb biasa pkai gred 8.8)
5 Concrete(G40/20) To be used to concrete parapet.
7 Rebars To be used in the structure.
8 Axel 905D To be used as a curing compound.
Table 4.3: List of Materials
Material lain dh submit utk approval x..klu x submit utk approval dlu

5.0 Precast Parapet Work Procedure

5.1 Steel Parapet Mould (Formwork)


a) Fabrication of steel formwork will be to the dimensions, shapes and sizes required to obtain
the accurate alignment, location and plumb of the finished structure.
b) Mould shall be placed on flat ground and shall be properly secure to avoid movement
during concrete. Mould shall be levelled and tight properly. Spirit level/plumb shall be used
to check the verticality and straightness of the mould.
c) The steel formwork should able to support the concrete during pouring works.

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 7 of 18


**
PRECAST PARAPET Revision: 00

d) The shop drawing for the details measurement or dimension of the steel formwork may
refer to the attachment in Appendix A
e) The inspection of steel formwork will be conducted during pre-concreting work to ensure
assemble of steel formwork is according to the submitted shop drawing.
f) The surface of the steel formwork should be clean from any debris or leftover concrete
before proceed with concreting work.

5.2 Reinforcement Work


a) Rebar cutting, bending and tying will be based on the contracts / shop drawings. Sketches
may be developed at site as identified by Site Engineer for better understanding of the rebar
installation sequence as per attached in the construction drawing at Appendix B.
b) Delivery notes, mill certificates, steel origin, supplier, manufacturer and other details of all
delivered steel consignments will be checked on site. The records will be available for
consultant reference or any future use.
c) Install rebar accurately in position and secure against displacement that might be caused
during concrete pouring.
d) Ensure all embedded items are fixed accurately at required locations and secure tightly
against any possible displacement. Any modification done during the installation and the
embedded items shall be indicated in the checklist as required.
e) Reinforcement sample test shall be carried out at the frequency as specified in the technical
specification.

5.3 Placing Concrete


a) Concrete placement can only commence upon approval of the Request for Inspection (RFI)
request by the Client / consultant. Request for inspection shall be submitted only upon
approval of QC Engineer and at least 24 hours before the casting schedule.
b) Ensure that all required inspections are performed.
c) Ensure that all embedded items required are installed and secured at their correct location
and levels.
d) Prior to placing of G40/20 concrete and concrete will be transported from the central
mixing plant and placed as rapidly as possible by using the concrete mixer truck.
e) Segregation and loss of ingredients shall be prevented.
f) The concrete vibrator will be use to ensure the concrete distribute evenly in the steel
formwork

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 8 of 18


**
PRECAST PARAPET Revision: 00

g) Temperature of concrete mix at the time of placing shall be monitored randomly and shall
not exceed 36° C referring to specification clause 9.5.6 placement temperature clause (b).

5.4 Compacting Concrete


a) All reinforcement concrete, where possible, be fully compacted by means of power driven
immersion type vibrators (poker vibrator).
b) Vibrators shall be placed vertically in the concrete, held in position until air bubbles cease
to come to the surface, and then slowly withdrawn, so that concrete can flow into the space
previously occupied by poker.
c) All exposed surfaces of concrete in contact with fresh in-situ concrete shall be roughed to
the exposed aggregates before receiving new concrete

5.5 Precaution for concreting during heavy rain


a) Concreting shall not be started if there is heavy rain prior to arrivals of concrete. The
concreting operation only to start after rain subside.
b) However, if heavy rain falls during the concreting operation, the following additional steps
have to be implemented:
 The top surface of parapet shall be covered with proper canvas.
 A polythene cover shall be placed over the mixer truck top hopper to prevent any rain
water going into the mixer drum which may affect the mix consistency.
c) Make rough concrete surface using wire brush following setting to broom finish surface for
construction joints.

5.6 Erection / Dismantle of Steel Formworks

a) The periods of time for formwork should be remove is as per technical specification under
the section 9 for concreting with the sub-clause 9.8.4 which is removal of forms.
b) Formwork will be remove without such shock or vibration which might cause damaged to
the formwork or the precast parapet structure.
c) Upon the removing of formwork, no further loads should imposed to the precast parapet
until at least the curing periods complete or until such later time in as in the opinion of
consultant which the precast parapet attained sufficient strength to safety withstand loads.

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 9 of 18


**
PRECAST PARAPET Revision: 00

5.7 Curing Work


a) For open surface, a curing compound (Refer to Appendix C) shall be applied equally by
hand pump or brush immediately upon removal of formwork to reduce incidence of plastic
cracking, shrinkage and dusting

b) Roughened surface shall be covered with damp absorbent material (gunny sack) or other
approved concrete retarder before proceeding the next level .

5.8 Lifting, Handling and Stacking of Precast Members


a) At all times, especially during transportation, members shall be secured in an upright
position.
b) To mention the minimum grade of concrete for lifting, minimum grade for stacking i.e
10kN for lifting, 40kN for stacking.
c) Members shall be handled, lifted and supported carefully at the positions and in the manner
intended to them. Always lift them vertically at the lifting hooks/points provided as
approved by SC.
d) Temporary supports for members shall be of timber. These bearers shall support the
members over their full width at the specified lifting points only. The ground or space
between the bearers supporting the members shall be carefully cleared and levelled so as to
prevent the member from being accidentally supported other than on the bearers. The
bearers themselves shall be supported on firm foundation, and every precaution shall be
made to prevent subsidence from occurring as per specification.
e) The members shall be transported on motorway by trailers, and are safeguarded against
tilting by means of suitable precaution.

5.9 Construction Sequences for Parapet Works

Please refer to the Appendix D for details of construction sequence on parapet works.

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 10 of 18


**
PRECAST PARAPET Revision: 00

6.0 Safety and Health Requirement

6.1 Job Safety Analysis


Job Safety & Health Analysis shall be carried on the project site. Traffic management shall
be approved and implemented at work areas. Safety awareness signs shall be established at location
of works. The hazards in a particular activity and the control measures implemented shall be
briefed to the workers during safety induction, tool box talk and JSA briefing.

6.2 Information to Personnel


a) All workers employed in the project site must have CIDB green card.
b) All new workers and staff to attend the Safety Training or Safety Induction Course Before
commencing works site and attendances shall be recorded in an induction list.
c) All site personnel shall wear proper Personnel Protective Equipment (PPE) such as safety
helmets, safety vest, safety boots, etc.
d) Activities may require additional PPE on top of the above such as Mask if necessary.
e) Monthly safety meetings shall be held with all the contractors related to the works.
f) All workers to attend the weekly toolbox meetings conducted by the safety officer held at
site and attendances shall be recorded.

6.3 Emergency Arrangements


a) The actual potential emergency situation may arise during the work are:

 Fire
 Electric Hazard,
 Accident due to Equipment Failure
 Major traffic accident when mobilization & demobilization of
equipment/machineries
 Lifting failure
 Escape of Combustible or Toxic Material

b) An Emergency Response and Communication Team shall be formed at the site.


c) The organization chart, list of emergency contact person and relevant authorities with their
contact numbers shall be showed in the Notice Board.
d) In the event of emergency, the site management staffs must evaluate the situation and
commence the necessary procedures as follow :

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 11 of 18


**
PRECAST PARAPET Revision: 00

 Raise the alarm.


 Stop works.
 Remain composed.
 Make sure notifications of emergency or evacuation are in place for
all workers surrounding the vicinity.
 Make sure all workers are assembled at designated assembly point.
 Make sure first aid kits are prepared at assembly point.
 All workers are told not to leave the assembly point until clear sign
is issued.
 Headcount shall be conducted.
 First aiders shall attend to the injured workers.
 Prepare assessment reports for the losses.

6.4 Permit Requirement


No. Descriptions Person In Charge Remarks

1 Work Permit Safety Officer, Construction Notify SC


Manager

2 Lifting Works Permit Safety Officer, Construction Attain permit and


Manager display

3 Outside Normal Working Authorities (TBA) Notify SC


Hours Works’ Permit

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 12 of 18


**
PRECAST PARAPET Revision: 00

7.0 Environmental Issue

7.1 Environmental Aspects, Impacts & Control Measures


The significant environmental impacts associated with the precast parapet works have been
identified of the related method of statements.

7.1 Air Quality and Noise


All construction machineries shall be in well maintain and in good working condition to
reduce emission of soot, smoke and noise. The following measures shall be implemented if the
above mentioned (soot, smoke and noise) is deteriorating:
 Increase maintenance frequency
 Replace to better equipment if necessary
 Switched-off equipment if not in used
 Supply workers on-site with proper PPE (i.e. ear plugs and mask)
 Temporary noise barrier will be installed to control the noise and vibration
if necessary

7.2 Waste Management


Scheduled waste from maintenance works of machineries, vehicles and tools will be placed
in designated areas. Proper oil tray or drum shall be placed to prevent the oil spillage all over the
place. Subsequent waste shall be collected and transfer to area as assigned. The schedule waste
storage area shall be placed in designated area with proper bund. Construction waste will be sent to
(location TBA). Schedule waste will be disposed at approved schedule waste dumpsite.

7.3 Temporary Drainage System


Drainage design should be adequate to ensure that no flooding occurs. Where necessary,
the actual drainage layout will be reviewed depending on the site terrain and condition. All runoff
from undisturbed areas should not be allowed to mix with runoff from the disturbed area.

7.4 Housekeeping
Housekeeping is an essential part of safety for the daily routine. Housekeeping would
include the following items:
 Maintain access/egress to all working area.
 Store and stack all construction materials in safe and orderly manner.
 No littering around the site.

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 13 of 18


**
PRECAST PARAPET Revision: 00

8.0 Quality Assurance & Quality Control

8.1 Contractual Requirements

Shall be implemented in accordance with submitted comprehensive Project Quality Plan


Ref. No. SUKE-SMPP-CA3-QMS-PQP-000001.

8.2 Inspection & Testing

Refer to Inspection and Test Plan as per attached for Quality Control Inspection Checklist
SUKE-SMPP-CA3-ITP-GEO-000006.

8.3 Follow Up & Evaluation

RFIs and respective Permit to Work shall be submitted prior execution of any construction
activities. In additional to this requirement weekly walk-about will be conducted to measurement,
analysis and propose for improvement as construction activities are on-going.

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 14 of 18


**
PRECAST PARAPET Revision: 00

Appendix A

Shop Drawing for Precast Parapet Steel


Mould(Formwork)

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 15 of 18


**
PRECAST PARAPET Revision: 00

Appendix B

Construction Drawing for Parapet

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 16 of 18


**
PRECAST PARAPET Revision: 00

Appendix C

Concrete Curing Compound

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 17 of 18


**
PRECAST PARAPET Revision: 00

Appendix D
Construction Sequences for Parapet Work

Stage 1
Ensure the dimension & usage of parapet
confirmed as per construction drawing

Stage 2
Inspect the cleanliness, dimension &
embedded item as per construction
drawing
Not okay

Stage 3 Inspection by consultant (SSP) and SMPP


Assemble the steel formwork
Okay

Stage 4
Sample to be taken for cube compressive
Placement of fresh concrete and concrete
strength test
vibration works

Stage 5
Dismantle of steel formwork

Stage 6
Apply curing compound on parapet

Stage 7
Transport to the provide yard storage

Stage 8
Stacking properly at storage yard before
transport to the usage location

SYARIKAT MUHIBAH PERNIAGAAN DAN PEMBINAAN SDN BHD Page 18 of 18


**

You might also like