Professional Documents
Culture Documents
Some Important Points/Submissions by Contractor As Per Document of Somnath Station
Some Important Points/Submissions by Contractor As Per Document of Somnath Station
Some Important Points/Submissions by Contractor As Per Document of Somnath Station
2. 11.3
Whether MS for all construction
The Contractor shall, at least 15 (fifteen) days prior to the commencement activities submitted by
of any construction activity, submit to the Authority Engineer for Contractor in time.
review the Method Statement proposed to be adopted for executing
the Work, giving details of inspection checklist, quality parameters, Whether MS approved by AE in
equipment to be deployed, traffic management and measures for time.
ensuring safety. The Authority Engineer shall complete the review and
convey its comments, if any, to the Contractor within a period of 10 (ten) Whether Controlled copies of all
days from the date of receipt of the proposed method statement from the MS available at site office of AE
Contractor. and Contractor.
Others
9. ARTICLE 3
OBLIGATIONS OF THE CONTRACTOR
3.1.6(h)
keep, on the Site, a copy of this Agreement, publications named in Whether all documents
this Agreement, the Drawings, Documents relating to the Project, available at site?
Change of Scope Orders and other communications sent under this
Agreement, and provide access to all these documents at all reasonable
times to the Authority Engineer and its authorised personnel;
Schedule N
(1) The Contractor shall submit to the Engineer three copies of a MPR in proper format being
Monthly Progress Report (MPR), as described in Authority's submitted?
Requirements Appendix 3 of Part A of this Schedule, describing the
progress and status of the Works. The MPR shall address the matters set MPR being submitted timely?
out in the Works Programme.
(2) The MPR shall be submitted by the end of each calendar month. It
shall account for all works actually performed from twenty sixth day of the
last month and up to twenty fifth day of the current month.
(3) The MPR shall be divided into two sections. The first section shall
cover progress and current status relating to design and the second
section shall cover progress and current status relating to construction.
(5) The Contractor shall submit all new versions to the Engineer for
review at least 2 weeks prior to their installation.
The Contractor shall devise and utilise a PMIS such that all documents Link provided to Authority/AE?
generated by the Contractor can be transmitted to the Engineer by
electronic means (and vice versa) and that all documents generated by
either party are electronically captured at the point of origin and can be
reproduced later, electronically and in hard copy. A similar link shall also
be provided between the Engineer office at site and the Authority’s Office
by the Contractor.
(1) The Maintenance Report shall be submitted as part of the Inspection and maintenance
Definitive Design and shall include full details of the long term inspection manuals for the civil, structural
and maintenance operations for each major component of water supply, and building works provided?
sewerage system, water treatment & ETP cum STP plants etc.
(2) The Contractor shall provide inspection and maintenance manuals for For each area an inspection
the civil, structural and building works. checklist has been provided?
(3) For each area an inspection checklist shall be supplied giving
inspection frequency, items to be inspected, criteria for acceptance, All instruments necessary to
criteria for remedial works and details of the remedial works, including carry out the inspections and
proposed materials and method statements. The recommended regular monitoring provided?
maintenance regime of each area shall also be given including cleaning
methods and frequency for different surfaces; removal of leakage borne
salts from concrete surfaces; cleaning of drainage channels, sumps and
pipes; repainting of metallic items;
(4) All instruments necessary to carry out the inspections and
monitoring that are identified in the report shall be provided by the
Contractor.
SCHEDULE D, PART A-AUTHORITY'S REQUIREMENT PART – 2 FUNCTIONAL
19. 1(4) The Contractor shall be responsible for obtaining all necessary Has the Contractor obtained all
approvals from the relevant Public/Government/Local/Statutory or any the necessary approvals?
agencies in the design and construction of the works.
21. 15(3) The Contractor shall submit applications for permanent Applications for permanent
connections for utility services i.e. sewerage and drainage and water connections for utility services
supplies to relevant local authority/agencies. i.e. sewerage and drainage and
water supplies to relevant local
authority/agencies?
22. 15(4) Fire clearance applications shall be made by the Contractor to Applications for Fire clearance
relevant local authority/agencies. made by the Contractor to
relevant local Authority?
23. 15(5) Requests for temporary power supplies for the construction of Contractor submitted the
the Works must be submitted, by the Contractor to the relevant requests for temporary power
authority/agency. Alternatively separate power supplies may be arranged supplies for the construction of
by the Contractor independent of these agencies, subject to compliance the Works?
with any necessary statutes.
24. 15(6) In addition, a number of agencies are involved in the Are all the required relevant
reinstatement works, permanent road accesses, temporary road approvals in place?
accesses, refuse collection accesses, street lighting, traffic management
and fire hydrant positions. The Contractor is responsible for obtaining
the approvals for these other works.
25. 16.4 Station Site Perimeter Security Proper Station Entrance
Protection & Pedestrian access
The boundary of the station operating area is typically at the street level with barrier separation has been
where access is provided, and is determined by the separation of the provided?
station operating area from any adjacent structures. This shall be defined
as the Station Perimeter. Security provisions for the Station Perimeter
shall be as follows:
(b) Pedestrian access – All pedestrian access either from the street or
other exterior areas/sections of the station complex shall be designed as
to permit barrier separation from the station operating area in the
event of an emergency.
(b) Provide in the direct area of passenger travel with the following:
• Door Frame Metal detectors; and
• Luggage scanning machine (i.e. x-ray scanner on conveyor)
(c) Entrance to paid area is to be configured so as to permit the operation
of this security point without impact on the movement of passengers at
the other entrance gates.
27. 16.6 Awareness and Training Proper awareness and training
programs are implemented?
Public and station staff awareness of the security provisions and
requirements of the station’s operation is essential in maintaining a viable
security program in large and dynamic public facilities like a station.
During commissioning and initial operations the Contractor shall provide:
32. 1(3) The Contractor shall engage the Lead Detailed Designer who shall Has the Contractor submitted
undertake and prepare the design of the Permanent Works and 03 (three) names of reputed
Temporary Works. The Lead Detailed Designer may be separate for firms who have suitable
structural, MEP works, Green Building etc, however a single designer experience of designing
shall work in one area. The Contractor shall submit 03 (three) names of projects of similar
reputed firms who have suitable experience of designing projects of scale/complexity for
similar scale/complexity for appointment as Lead Detailed Designer and appointment as Lead Detailed
the Authority shall choose one name from these for appointment as Lead Designer and the Authority has
Detailed Designer. Provided that, the Authority may not appoint any of the chosen one name from these
firms as Lead Detailed Designer if they don’t have the requisite for appointment as Lead
experience and the Contractor shall suggest 03 (three) fresh names in Detailed Designer?
such a case.
33. 1(5) The Contractor shall appoint a suitably qualified person(s) to act as Has the Contractor appointed
the Lead Design Checker for structural and/or MEP works. Provided an IIT as structural Lead Design
further that structural Lead Design Checker for all works (buildings, Checker?
retaining walls, subways, over bridges etc) which have the potential to
affect the existing/future tracks shall only be an Indian Institute of
Technology (IIT). The Lead Design Checker shall not produce any of the
design or temporary works designs nor work directly for or report to the
Contractor’s Project Manager.
34. 1(6) The Contractor shall ensure that at the end of each month, the Is the Lead Design Checker
Lead Design Checker shall issue a written report to the Contractor’s issuing the monthly report to
Site office, with a copy to the Engineer, covering the status of all designs Contractor and Engineer?
checked during the preceding month. The format of the Design Checker’s
monthly reports shall be one to which the Engineer raises a Notice.
35. 1(7) The Lead Design Checker shall undertake design checks on the Two original copies of a Design
Contractor’s designs. All design documents, drawings, plans, calculations Certificate as set out in
and reports produced by the Contractor and Designer shall be checked Attachment – 2, signed by all
by the Design Checker, accompanied by two original copies of a parties are submitted?
Design Certificate as set out in Attachment – 2, signed by all parties
when the design is submitted to the Engineer.
36. 1(10) The Contractor shall submit his Design Quality Assurance Plan Has the Contractor submitted
as required in Appendix 4 of Schedule DA, Authority’s Requirement for Design Quality Assurance Plan
the design required by the Agreement. as required in Appendix 4 of
Schedule DA?
38. 1(2) The Project Manager and his site team shall have experience and Has the Contractor submitted
qualifications appropriate to the type and magnitude of the Works. Full full details of the qualifications
details shall be submitted of the qualifications and experience of all and experience of all proposed
proposed staff to the Engineer for his Notice, which shall be as a staff to the Engineer as per
minimum those given in Clause 16 of Schedule DA, Authority’s Clause 16 of Schedule DA?
Requirement, part 1- General.
39. 2. Checking of the Contractor's Temporary Works Design Has the Contractor submitted
Design Certificate for
The Contractor shall, prior to commencing the construction of the Temporary Works Design?
Temporary Works, submit a certificate to the Engineer, based on the
‘Design Certificate' signed by the Lead Designer and the Lead Design
Checker, certifying that the Temporary Works have been properly and
safely designed and checked, and that the Contractor has checked the
effect of the Temporary Works on the Permanent Works and has found
this to be satisfactory.
40. 2.1(2) Rock crushing plant shall not be provided on the site. Has the Contractor provided
Rock crushing plant at site?
41. 2.1(4) Entry to and exit from the site shall be controlled by 24 hour Is the Entry to and exit from the
security and shall be only available at the locations for which the site controlled by 24 hour
Engineer has given a Notice. Notice will only be given after the Contractor security?
has provided evidence that he has obtained the necessary approvals
from the relevant authorities.
42. 2.3 Survey of the site Has the Contractor carried out
the survey of the site?
A survey shall be carried out of the site to establish its precise
boundaries and the existing ground levels within it. This survey shall
include a photographic survey through still/video photography at
ground level as well aerial using drones sufficient to provide a full record
of the state of the site and adjacent areas/buildings before commencing
the Works, with particular attention paid to those areas where
reinstatement will be carried out later on. The survey shall be carried out
before the site clearance and in any case prior to the commencement of
work in any Works Area. The survey shall be carried out by the
Contractor and will require a Notice from the Engineer.
44. 2.4(2) No work shall commence in any Works Area until the Engineer has Has the Engineer issued Notice
issued a Notice signifying that he is satisfied that the barricades installed signifying that he is satisfied
by the Contractor are sufficient to prevent, within reason, unauthorised that the barricades installed by
entry. Project signboards shall be erected not more than four (4) the Contractor are sufficient?
weeks, or such other period as the Engineer has given his Notice, after
the date for commencement of the Works. Is the Project signboards
erected within four (4) weeks as
per types, sizes and locations
agreed with the Engineer?
45. 2.6 Casting Yard Has the Contractor requested
for land for CY?
(1) The Authority may provide an area of land suitable for use as a
casting yard/works area near to the site upon request by the If area for CY is provided then
Contractor. annual rent is being recovered?
(2) Should Contractor elect to use this site then the Contractor will have
to remit an annual rent equivalent to an amount of 1% of the
“Guidance Value” of the property for the period of occupancy of the
area of land. The Contractor shall be responsible for clearing the site
of all debris, vegetation and buildings, providing access into the site
and providing any utilities or services which may be required for the
Contractor’ operations. In case the land cannot be handed over to the
Contractor, the Contractor has to make his own arrangements for a
casting yard/works area(s) and other facilities without any liability to
the Authority.
46. 2.6(4) A Mechanical Type Washing Plant shall be installed by the Is the Mechanical Type
Contractor for the use of all vehicles leaving the casting yard area to Washing Plant installed by the
avoid any contamination or spillage on the connecting roads. Contractor?
47. 2.7(5) The Contractor is responsible for obtaining the requisite Whether proper permission is
approvals from the concerned local authorities for his Lorries’ obtained by Contractor for
movement plan and their operation. Lorries’ movement plan?
48. 3. Survey
Detailed survey carried out by
(2) The Contractor shall carry out detailed survey to check the levels. Contractor?
In case of any differences from the Authority’s drawings or data, the
Contractor shall bring these to the Notice of the Engineer immediately
and submit his proposals for correction.---- all such
differences/discrepancies/conflicts in survey data of the Authority and
shall not entitle the Contractor for any claims or extension of
Agreement schedules and all the necessary works in this regard shall
be done by the Contractor without any cost or time implications to the
Authority. Survey reference points are
(4) The setting up of the accurate Contractor survey reference points maintained by the Contractor?
and maintaining them shall be the responsibility of the Contractor.
The Contractor shall check the survey reference points every three Survey reference points being
months to ensure that these survey points continue to remain checked every three months?
consistent with the bench marks.
49. 4. Occupational Health Safety and Environmental Requirements OHS&E manual submitted by
Contractor before start of work
The Contractor shall comply with the conditions and requirements and approved by Engineer?
stipulated in the Occupational Health, Safety & Environment (OHS&E)
manual to be prepared by the Contractor and got approved from OHS&E manual being complied
Authority before start of work. by Contractor?
(4)The Contractor shall be responsible for the security of the Site at all I card issued to all
times during the term of this Agreement. The Contractor shall control workers/staff?
all entry and exit to and from the Site for his personnel, personnel from
the Authority, Engineer, Sub-Contractors and suppliers, by pedestrians Visitor Pass are issued to
and for all vehicles. All of the Contractor’s personnel shall be required others?
to carry an identity/security card or pass which provides a positive
photo identification and they shall be required to show the pass when
entering or leaving the Site. This shall apply to all personnel on the Site
including, but not limited to, the Contractor’s staff, Sub-Contractor staff,
Suppliers, Consultants, etc. and the staff of the Authority and Engineer.
Provision shall be made for issue of visitors’ passes for other
personnel authorized to enter the Site as visitors. Visitors on Site shall
be escorted by appropriate Site based personnel at all times.
54. 7.1.4 Removal of Graves and Other Obstructions Procedure for removal of graves
and other obstructions
If any graves and other obstructions are required to be removed in followed?
order to execute the Works and such removal has not already been
arranged for, the Contractor shall draw the Engineer's attention to them in
good time to allow all necessary arrangements and authorizations for
such removal, and the Contractor shall not remove them without first
obtaining approval from the appropriate authorities and then obtaining a
Notice from the Engineer.
55. 9. Pre-Construction Surveys of Adjacent Buildings and Structures
Separate pre-construction
The Contractor shall submit details of the measures he intends to survey report prepared for each
take to protect those buildings or structures, as identified in the building/structure in required
reports compiled under Clause 4.3 of Schedule DA, Authority’s format ?
Requirement, part 3-Design, as potentially susceptible to damage during
the construction of the Works, to the Engineer for a Notice for the Two coloured copies of all of
proposed measures. The Authority will make available to the Contractor, the pre-construction survey
for information only, the Building Condition Survey information available reports provided?
with him. The Contractor shall supplement this information, by way of
carrying out his own Building condition Survey, to the extent
necessary to ensure compliance with the Authority’s Requirements,
Specifications and Conditions as set out in the Agreement.
The Contractor shall determine the potential influence zones for his
Works as per the stipulations contained in Outline Design specifications
and prior to commencing any work within the zone of influence of the
buildings and structures (EBS),
Prior to commencing any work within the 50 m zone of influence of the
buildings and structures, the Contractor shall complete a pre-
construction survey to identify and record any existing defects in
the building structure and fabric. A separate pre-construction survey
report shall be prepared for each building/structure, in a format given a
Notice by the Engineer. The report shall include sufficient key plans,
sketches and photographs to enable easy location of existing defects and
comparison with possible future ones. Two coloured copies of all of the
pre-construction survey reports shall be provided to the Engineer.
58. 10.6 Approval for Temporary Traffic Arrangements and Control All arrangements for Temporary
Traffic Arrangements and
The Contractor shall make all arrangements with and obtain the Control made and necessary
necessary approval from the transport authorities and the local approval from the transport
Traffic Police for temporary traffic arrangements and control on public authorities and the local Traffic
roads. Police obtained?
59. 10.8 Particulars of Temporary Traffic Arrangements and Control Proposed temporary traffic
arrangements and control on
The following particulars of the proposed temporary traffic public roads submitted to the
arrangements and control on public roads shall be submitted to the Engineer?
Engineer for his Notice of No Objection, at least 28 days before the traffic
arrangements and control are implemented: Engineer has issued NONO?
(1) details of traffic diversions and pedestrian routes;
(2) details of lighting, signage, guarding and traffic control arrangements
and equipment;
(3) any conditions or restrictions imposed by Traffic Police or any other
relevant authorities, including copies of applications, correspondence
and approval.
(4) Where concrete barriers are used to separate flows of traffic, the
barriers shall be in a continuous unbroken line. No gaps shall be left
between any sections of the barrier.
(5) Site perimeter fencing and barriers along the roadway, shall have
flashing amber lights positioned on the top of them every 50 metres
apart and at every abrupt change in location.
60. 11.1 Reinstatement of Public Roads and Footpaths Design for the reinstatement of
Public Roads and Footpaths
The Contractor shall submit his design for the reinstatement to the submitted and approved?
relevant authorities and obtain their prior approval to carrying out the
Work.
64. 12.4 Latrines and Wash places Latrines and wash places
provided and being maintained?
The Contractor shall provide latrines and wash places for the use of
its personnel and all persons who will be on the Site. The size and
disposition of latrines and wash places shall accord with the numbers and
dispositions of persons entitled to be on the Site, which may necessitate
their location on structures and, where necessary there shall be separate
facilities for males and females. The capacities and layout shall be
subject to a Notice from the Engineer. The Contractor shall arrange
regular disposal of effluent and sludge in a manner that shall be in
accordance with local laws/ regulations.
(1) drawings showing the layout within earmarked area for the
Contractor's offices, project signboards, principal access and other
major facilities required early in the Agreement, together with all
service utilities;
(2) drawings showing the details to be included on the project
signboards and diversion boards.
Drawings showing location of stores, storage areas, concrete batching
plants and other major facilities and their access roads/paths shall be
submitted to the Engineer for his Notice as early as possible but in any
case, not less than twenty-eight (28) days prior to when such facilities are
intended to be constructed on the Site.
(a) they are accredited for the relevant work to a standard acceptable to
the Engineer; and
(b) Particulars of the proposed laboratory are submitted to the Engineer
for a Notice.
(2) Unless agreed otherwise by the Engineer in-situ tests shall be done All equipments are maintained
in the presence of the Engineer. and calibrated?
(3) Equipment, apparatus and materials for in-situ tests and laboratory
compliance tests to be carried out by the Contractor shall be
provided by the Contractor. The equipment and apparatus shall
be maintained by the Contractor and shall be calibrated before
the testing starts and at regular intervals as permitted by the
Engineer. The equipment, apparatus and materials for in-the situ
tests shall be removed by the Contractor as soon as practicable
after the testing is complete.
72. 18. Disposal Excavated Material including Waste Contractor has submitted land
plan for fill or dumping sites as
(1) For fill or dumping sites, the Contractor shall prepare a land plan with per requirements?
details of surface drainage requirements, spreading and compaction of
the fill during dumping acceptable to the Engineer. The Contractor NONO for dumping sites issued
shall also provide security for such sites. The dumping sites to be used by Engineer?
by the Contractor shall be identified and provided by the Contractor
and with the approval of the relevant authorities and having obtained a
Notice from the Engineer.
73. 19. Restoration of Areas Disturbed by Construction All areas reinstated as per the
requirements?
(1) Unless otherwise directed by the Engineer, any areas disturbed by the
construction activity, either inside or outside the Project Right of Way Contractor has carried out
or Site Areas, shall be reinstated as follows: design and construction of
(2) All areas affected by the construction work shall be reinstated to their landscaping for all works areas
original condition, or better, with new materials, including but not and submitted his proposals to
necessarily limited to, sidewalks, parking lots, access roads, adjacent the relevant authorities?
roads and landscaping. Grass cover shall be provided for any bare
earth surface areas, along with proper provisions for surface drainage. Approval of landscaping?
Appendix 8 Utilities
The organization of the Contractor’s Project Plan shall comply with Contractor’s organization
ISO 10005 (2005): Quality Management-Guidelines for Quality comply with ISO 10005
Assurance Plan. (2005)?
All on-Site and off-Site testing sampling in India is to be carried out Tests conducted in NABL
by laboratories accredited by NABL (National Accreditation accredited labs?
Board of Testing and Calibration Laboratories) or internationally
accredited laboratory to ISO 17025: 2005.
A fully equipped concrete laboratory shall be installed at Site Site lab established?
along with laboratory technicians and support staff. Testing Technicians and support staff
machines shall be periodically calibrated in accordance with NABL available?
requirements. Details included in clause 14.1. Calibration of machines done
regularly?
Within thirty (30) days of the Commencement Date, Contractor Quality Plan, Design Quality
shall submit to the Engineer for his review, comment and Notice Plan and Delivery Schedule
of No Objection the following, as appropriate: and Manufacturing Quality
(a) Quality Plan; Plan and Delivery Schedule
(b) Design Quality Plan and Delivery Schedule; and submitted within 30 days?
(c) Manufacturing Quality Plan and Delivery Schedule. NONO for above documents
available?
The Contractor shall promptly supply the Engineer with six (6)
controlled copies of his Quality Plans, Inspection and Test six controlled copies of his
Plan(s), related procedures / instructions / forms upon such Quality Plans, Inspection and
documents being reviewed and approved by the Engineer. The Test Plan(s), related procedures
Contractor shall maintain such controlled documentation throughout submitted?
Controlled copies available?
the duration of the Agreement.
The Quality Plan shall define the Contractor's management The Quality Plan as per the
structure for the execution of the Works and for the control of the requirements submitted?
quality of the Works and shall, without limitation, define:
The Design Checker shall issue a certificate that design can Certificate submitted by Design
meet Contractor’s all obligations under the Agreement to the Checker?
Engineer in the format to be got approved by the Engineer.
The Design Quality Plan(s) shall define the Contractor's policy for Design Quality Plan(s)
the design of the Permanent Works or Plant and/or Temporary submitted as per
Works and shall, without limitation, define: requirements?
(a) The organization of the Contractor's design staff;
(b) The specific allocations of responsibility and authority given to
identified design staff with particular reference to the review
and verification of design drawings and calculations by the
Contractor;
(c) The specific methods of design to identify any relevant Method
Statements and develop those Method Statements to a degree
of detail sufficient to permit the Engineer to understand;
(d) The procedures to be applied to manage and control the quality
of the design work, with particular reference to the following:
(i) The design and performance requirements which shall be
defined in terms of basic data and design assumptions made;
relevant codes, standards and regulatory requirements; safety,
security and environmental requirements; and commissioning
requirements;
(ii) The design methods. Software applications to be used in the
design, both proprietary and public domain, shall be identified
and any requirements for physical and mathematical model
testing and validation; It is desirable that any design done on
proprietary software of the Designer be independently verified
using another software.
(iii) The preparation, checking, issue, distribution, indexing and
filing reports, calculations, drawings and specifications along
with the means of their revisions;
(iv) The formal design review, authorisation and approval of design
documentation;
(v) The design verification and validation;
(vi) The design checks by the Design Checker; and
(vii) List of examples of the forms and formats to be used to record
the activities under the Design Quality Plan shall be attached at
the end of each section or a reference included to existing
standard procedures.
(e) For the following, the Engineers review and Notice of No
Objection is required before proceeding with the next stage of
the works or design;
(i) The design of temporary traffic arrangements shall be reviewed
and approved by the Engineer before submitting the same to the
relevant authorities;
(ii) The design of excavation and lateral support systems for
underground excavations shall be reviewed by the Engineer
before the excavation commences;
(iii) The design of formwork and false work for cast in-situ and
precast concrete works shall be reviewed and approved by the
Engineer before the erection of the same commences;
(iv) The implementation of temporary traffic arrangements shall be
reviewed and approved by the Engineer before the associated
works proceed.
The Contractor shall ensure that audits of all the activities in each
quality plan are carried out to ensure the continuing suitability and
effectiveness of the Quality Management System. Reports of each
such audit shall be submitted promptly to the Engineer for his
information.
(a) The Contractor shall conduct Management Reviews of its Any revision to Quality Plan?
quality system, at least annually. As work progresses, the
Contractor shall update the Quality Plan to reflect current
conditions. The need for revisions to the Quality Plan may be
identified by the Contractor and/or the Engineer. The Contractor
shall submit any revisions or updates to the Quality Plan to the
Engineer for his Notice of No Objection within thirty (30) days of
the identification of the need for a revision.
(b) In addition, the Contractor shall submit its Quality Plan for
review by the Engineer annually even if no revisions have
occurred during the preceding twelve (12) months. The
Contractor shall submit a certified copy of the updated Quality
Plan with revisions highlighted.
Contractor shall prepare Method Statements for each area All MS as per requirements
and/or type of activity conducted, and submits them to the submitted?
Engineer for his review, comment and Notice of No Objection prior
to commencing construction on any Temporary or Permanent
Works. Method Statements shall be prepared for all Temporary and
Permanent Works and shall be specific to the work being
constructed and to the location of work.
The Contractor, and through him, his consultants, sub-contractor ITP as per requirements
and suppliers engaged in supplying, manufacturing, construction, submitted?
installation, commissioning and testing or any other service
connected with the Works, shall maintain Inspection and Test
Plans (ITP) appropriate for the services they provide that are
accepted by the Engineer. These accepted ITP’s will stipulate the
necessary level and frequency of tests and inspections for each
aspect of the Works, and also stipulate, without limitation:
Quality Control Engineers shall have a minimum of ten (10) Qualified materials technicians
to conduct the sampling and
years construction / installation experience with at least five
testing of materials, goods and
(5) years’ experience in the inspection, sampling and testing of supplies appointed?
works of the type being constructed. If required on the request of
Engineer additional inspectors shall be appointed, at no additional
cost.
The actual size of the Site staff shall reflect the complexity, needs,
shifts and composition of Quality Control activities consistent with
work in progress. The staffing levels shall be consistent with the
Contractor’s Quality Plan and the Project Baseline Programme, the
relative locations of work in progress and the nature of the work.
The Quality Plan shall identify administrative/clerical support for the
maintenance and management of records/documents pertinent to
Quality Control activities.
xiii. 13. MONTHLY PROGRESS REPORT
The Contractor shall continuously monitor the performance of his MPR as per requirements being
Quality Management System, which shall be included in each submitted?
Monthly Progress Report (MPR).
13.1 Quality Certifications
(a) The Quality Plan and all of the measures and procedures
provided therein are functioning properly and are being fully
complied with, except as specifically noted in the certification.
(b) All work, including that of the Designer, and all other designers,
sub- Contractor at all tiers, suppliers and fabricators, has been
checked and/or inspected by the Contractor’s Designer and Weekly records are prepared
Design Checker, except as specifically noted in the certification, and maintained as per
conforms to the requirements of the Agreement. requirements?
13.2 Weekly
(c) The identity of the Quality Control Engineer or data recorder, the
type of test or observation employed, the results and the
acceptability of the work and action taken in connection with any
deficiencies noted;
The Contractor shall, in accordance with the quality control Quality item lists maintained as
requirements of the Specification and other documents included in per requirements?
the Agreement, prepare and maintain quality item lists which
establish the criteria for control of each major component or activity
during design, construction and/or manufacture and installation,
commissioning and servicing in accordance with the need to ensure
the desired quality requirements of the Works.
The Engineer shall be free to carry out such additional tests as may
be decided by him at his sole discretion, from time to time, in
addition to those specified in this document. The Engineer shall
also be free to appoint any third party for inspection and testing of
important items like stay cables and steel work including welding
etc., at his own cost. The Contractor shall provide the samples and
labour for collecting the samples. No extra payment shall be
payable to the Contractor for samples or for the collection of the
samples. The results of such additional tests and third party
inspection shall be binding on the Contractor.
The Engineer shall have the right at all times to inspect all
operations including the source of materials, procurement, layout
and storage of materials, all equipment including the concrete
batching and mixing equipment, and the quality control system.
Such an inspection shall be arranged and the Engineer's approval
obtained prior to starting of the particular item of work. This shall
however, not relieve the Contractor of his responsibilities.
All materials tested comply with
All materials which do not conform to the Specifications shall specifications?
be rejected and shall be removed from the Site immediately. The
Engineer shall have the power to cause the Contractor to purchase The testing machines
and use materials from any particular source, as may, in the recalibrated periodically?
Engineer's opinion, be necessary for the proper execution of
Works.
All the materials to be used in the work and tested in the laboratory
shall comply with the Engineer or such recognized specifications as
acceptable to Engineer.
Frequency of Testing
Unsuitable Materials
If the Contractor has used or proposes to use or repair any item of NCRs status?
the Works which does not conform to the requirements of the
Agreement, he shall immediately submit for review by the Engineer
a proposal for rectification, and supply full particulars of the
nonconformity and, if appropriate, of the proposed means of repair.
If the Engineer issues nonconformity reports, either product based
as a Non- Conformance Report (NCR) or procedural through
quality audit as a Corrective Action Request (CAR) or similar
documents to notify the Contractor of any item of the Works which
does not conform to the requirements of the Agreement, the
Contractor shall promptly investigate the matter and submit for
review within fourteen (14) days of notification by the Engineer of
the remedial measures to be taken and stating the reasons for the
measures and the corrective and preventive action.
The Contractor shall notify the Engineer of the places of Source of supply of all goods
manufacture and/or the source of supply of all goods and and materials intimated
materials to be incorporated into the Works and shall give timely to Engineer?
reasonable notice (which shall not in any event be less than fifty-six
(56) days) to the Engineer before the start of any manufacturing
and/or the supply of goods and materials.
In relation to all Quality Control points and Quality ‘Hold Points’ Notice for all Quality Control
involving inspection and/or witness testing by the Engineer, the points and Quality ‘Hold Points’
Contractor shall give the Engineer notice of when the relevant given?
work will be inspected and/or tested. The period of notice shall
be as follows; unless otherwise agreed by the Engineer:
(a) In the case of on-Site work, such notice shall be given not less
than forty-eight (48) hours of normal working time before the
work is to be inspected and/or tested;
(b) In the case of work carried out off the Site, such notice shall be
given not less than fourteen (14) days before the work is to be
inspected and/or tested; and
(c) In the case of work carried out offshore outside of India, such
notice shall be given not less than twenty-eight (28) days before
the work is to be inspected and/or tested.
In relation to all Quality Control Points involving inspection and/or Details of Tests not witnessed
testing by the Contractor, the Engineer may elect to witness such by Engineer?
inspections and/or tests but, on expiration of the period of notice
pursuant to clause 17, the Contractor may proceed with the
inspections and/or tests notwithstanding the absence of the
Engineer or of any response to the said notice. Witness by the
Engineer shall not discharge the Contractor of the responsibility to
provide acceptable product, nor shall it preclude subsequent
rejection by the Engineer.
The Contractor shall obtain certificates for each batch of Certificates for each batch of
manufactured goods and documentary evidence that goods, manufactured goods
supplies and materials and Contractor’s Equipment conform to the provided?
Agreement requirements for incorporation in the Works. Each
certificate and/or proofing document shall include all reports of
inspections and/or tests carried out at the place of manufacture.
The Contractor shall make available at the Site no less than twenty-
four (24) hours prior to installation or use of such goods, supplies or
materials and Contractor’s Equipment all certificates and/or
proofing document(s).
The Contractor shall compile reports of each inspection and/or Compiled reports of each
test. Such reports shall show the results of all the inspections inspection and/or test and
and/or tests carried out and shall certify that the work has been compliance with the
inspected and/or tested in accordance with the requirements of the requirements of the Agreement
provided?
Agreement and that the work complies with the requirements of the
Agreement. Any analysis of the results required to confirm that the
work complies with the requirements of the Agreement shall be
compiled in accordance with clause 21 and reported to the
Engineer in accordance with clause 22.1.
xxi. 21. TIME LIMIT FOR FILING OF REPORTS FOR INSPECTIONS Signed copies of reports kept in
AND/OR TESTS office timely?
The Contractor shall ensure that a signed copy of report of each in-
situ and each off- site inspection / test is filed in his Records
Office within 3 (three) working days and within seven (7)
working days of the date of completion of the test process
respectively.
The Contractor shall provide and maintain at all stages of the QC Registers maintained as per
work a quality control register or registers to identify the requirements?
status of inspections, sampling and testing of the work and all
certificates. Each register shall:
(c) Show the results of each report of inspection and/or test and
any required analysis of these results and compare these
results against the acceptance criteria, including:
(i) Standard deviation and coefficient of variation for each grade
of concrete;
(ii) Summary of trial mix for each grade of concrete;
(iii) Summary of sample type and quantity that has been sent for
third party testing;
(iv) Summary of third party testing reports;
(v) Summary of calibration, status of monitoring and measurement
equipment, batching plant/s; and
(vi) Summary of in-process testing for routine dynamic pile load
test, static pile load test, lateral load test (if required) and pile
integrity test etc. that have been conducted that month.
All samples for testing shall be fully prepared for transportation and
testing by the Contractor and shall be delivered by the Contractor to
the place of testing.
(b) The material has been handled or stored in such a manner that
it is no longer represented by the previously tested samples.
xxvi. 26. TIMING FOR INSPECTION BY THE ENGINEER Tests carried out during day
and in the presence of Engineer
The Contractor shall allow the Engineer a reasonable time to carry after proper notice?
out any inspection and/or witness testing and to assess the result of
any inspection and/or test before proceeding with the Works.
xxvii. 27. FAILURE OF CONTRACTOR TO INSPECT THE WORKS Any work rejected/uncovered
due to non-testing?
The Engineer may reject the work in question, or require it to be
uncovered, in the event of any failure by the Contractor to inspect
and/or test at a Quality ‘Hold Point’ by Contractor’s Quality
Department.
xxviii. 28. FAILURE OF THE CONTRACTOR TO TEST THE WORKS Third Party Inspection required?
If the Contractor fails to test, either type test or routine test or qualification
test, for each batch of goods or elements of the Works, then the Engineer
shall arrange for third party inspection. The Engineer shall recover two
times the actual cost associated with testing, including the services of any
specialised personnel or independent assessors, and will deduct such
cost from the Contracor.