Professional Documents
Culture Documents
Plan Schedule
Plan Schedule
JANUARY (31 DAYS) FEBRUARY (29 DAYS) MARCH (31 DAYS) APRIL (30 DAYS) MAY (31 DAYS) JUNE (30 DAYS) JULY (31 DAYS) AUGUST (31 DAYS) SEPTEMBER (30 DAYS) OCTOBER (31 DAYS)
START FINISH WEEK DURATION START FINISH WEEK DURATION JAN 01-08 JAN 09-16 JAN 17-24 JAN 25-31 FEB 01-07 FEB 08-14 FEB15-21 FEB 22-29 MAR 01-08 MAR 09-16 MAR 17-24 MAR 25-31 APR 01-08 APR 09-16 APR 17-23 APR 24-30 MAY 01-08 MAY 09-16 MAY 17-24 MAY 25-31 JUN 01-08 JUN 09-16 JUN 17-23 JUN 24-30 JUL 01-08 JUL 09-16 JUL 17-24 JUL 25-31 AUG 01-08 AUG 09-16 AUG 17-24 AUG 25-31 SEP 01-08 SEP 09-16 SEP 17-23 SEP 24-30 OCT 01-08 OCT 09-16 OCT 17-24 OCT 25-31
1 GENERAL REQUIREMENTS 3,800,000.00 9.58% 17-Jan 8-Mar 1 7 1.37% 1.37% 1.37% 1.37% 1.37% 1.37% 1.37%
3 CONSTRUCTION OF FINAL CLARIFIER TANK NO. 2 5,193,687.29 13.10% 15-Feb 16-Sep 5 28 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47%
C. 'Hauling of Excavated Material and Dumping it inside LISP IV ( 1000 meters radius
from source site to dumping site & No Spreading and Compaction at Dump Site)
0.00%
F. 'Formworks 0.00%
G. 'First Stage Concrete, 21 Mpa (3,000 PSI), g 3/4 28days, Using Pump Crete (Monolitic
Pouring) 0.00%
Q. 'Paving Block Walkway (With Sand Bedding )- 3,000psi (Installation and Installation) 0.00%
4 'CONSTRUCTION OF EQUALIZATION TANK 2,015,759.38 5.08% 15-Feb 16-Sep 5 28 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18%
C. 'Hauling of Excavated Material and Dumping it inside LISP IV ( 1000 meters radius
from source site to dumping site & No Spreading and Compaction at Dump Site)
0.00%
F. 'Formworks 0.00%
G. 'First Stage Concrete, 21 Mpa (3,000 PSI), g 3/4 28days, Using Pump Crete (Monolitic
Pouring) 0.00%
Q. 'Paving Block Walkway (With Sand Bedding )- 3,000psi (Installation and Installation) 0.00%
5 'CONSTRUCTION OF SLUDGE DIGESTER 2,030,358.19 5.12% 15-Feb 16-Sep 5 28 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18%
M
D
n
o
n
o
u
d
e
e
e
e
a
g
S
S
s
r
t
t
f
f
I
l
l
i
6 CONSTRUCTION OF AERATION TANK NO. 2 3,354,610.50 8.46% 15-Feb 16-Sep 5 28 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30% 0.30%
7 'CONSTRUCTION OF SLUDGE DRYING BED 2,245,924.09 5.66% 17-Apr 24-Jul 13 13 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44%
8 All Mechanical and Piping Works 9,349,555.81 23.58% 9-Mar 24-Jul 8 18 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31%
Fabrication and Installation of Equalization transfer pump Mounting Bracket and Support 0.00%
Fabrication and Installation of Sludge transfer pump Mounting Bracket and Support 0.00%
Piping works from Blower line to Equalization Tank Air Diffusers 0.00%
Discharge Piping from Equalization Transfer Pump to Aeration Tank 1&2 0.00%
Piping Works from existing blower line to Aeration Tank no.2 0.00%
Piping works from Sludge Draw-off Pipe to Weir Box no.2 @ Air Lift sump no.2 0.00%
Discharge Piping works for Scum Pump Going to Aeration tank no.2 0.00%
Overflow Piping from Aeration Tank 2 going to Final Clarifier Tank 2 0.00%
Piping works from Weir Box no.2 Going to filtrate system. 0.00%
Piping works from existing sludge filtrate piping to sludge transfer pump @ sludge
digester 0.00%
Piping works from existing sludge filtrate piping to sludge drying bed cell #1 and cell #2 0.00%
9 Electrical Works 5,890,314.93 14.85% 1-Apr 16-Aug 11 18 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83%
10 Miscellaneous Works 5,586,804.04 14.09% 1-May 16-Oct 15 22 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64%
ACCU COST - 542,857.14 1,085,714.29 1,628,571.43 2,171,428.57 3,164,086.26 4,156,743.95 5,149,401.65 6,306,746.96 7,275,967.28 8,245,187.59 9,541,647.63 10,838,107.66 12,307,331.09 13,776,554.51 15,499,723.58 17,222,892.64 18,946,061.70 20,669,230.77 22,392,399.83 24,115,568.90 25,838,737.96 27,561,907.02 29,285,076.09 31,008,245.15 32,731,414.22 33,762,400.12 34,793,386.03 35,824,371.93 36,528,118.12 37,231,864.30 37,935,610.49 38,639,356.68 38,893,302.32 39,147,247.95 39,401,193.59 39,655,139.23
PROJECTED WEEKLY PERCENTAGE WEIGHT ( % ) PERCENT WT (%) 0.00% 0.00% 1.37% 1.37% 1.37% 1.37% 2.50% 2.50% 2.50% 2.92% 2.44% 2.44% 3.27% 3.27% 3.71% 3.71% 4.35% 4.35% 4.35% 4.35% 4.35% 4.35% 4.35% 4.35% 4.35% 4.35% 4.35% 2.60% 2.60% 2.60% 1.77% 1.77% 1.77% 1.77% 0.64% 0.64% 0.64% 0.64%
ACCUMULATED WEEKLY PERCENTAGE WEIGHT (%) ACCU % WT 0.00% 1.37% 2.74% 4.11% 5.48% 7.98% 10.48% 12.99% 15.90% 18.35% 20.79% 24.06% 27.33% 31.04% 34.74% 39.09% 43.43% 47.78% 52.12% 56.47% 60.81% 65.16% 69.50% 73.85% 78.19% 82.54% 85.14% 87.74% 90.34% 92.11% 93.89% 95.66% 97.44% 98.08% 98.72% 99.36% 100.00%
LEGENDS:
PROJECTED
ACTUAL
Workforce Qty. Total No. of Days Average Rate Per Day
Name of the Project : CONSTRUCTION OF CENTRALIZED WASTE WATER Total Project Cost : 35,375,000.26
TREATMENT PLANT 2, PHASE 1, STAGES 2 & 3 Managerial Staff 2 270
Owner of the Project : SCIENCE PARK OF THE PHILIPPINES INC. Project Direct Cost : Technical Staff 3 270
Location : LIGHT INDUSTRY & SCIENCE PARK IV Project In-Direct Cost : Skilled 17 180
Physical Target : I.00 PACKAGE Date Started (Target) : February 01, 2020 Unskilled 7 270
Planned 0.51% 0.51% 0.27% 0.20% 0.20% 0.98% UNDER ECQ PERIOD 1.07% 0.29% 0.29% 0.29% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.25% 0.25% 0.25% 0.25% 0.29% 0.29% 0.29%
1 GENERAL REQUIREMENTS ea 1 3,800,000.00 10.74%
Actual
Planned 0.15% 0.22% 0.16%
2 CIVIL/SITE DEVELOPMENT WORKS ea 1 188,125.00 0.53%
Actual
Planned 0.78% 1.96% 6.03% 8.21% 1.46% 1.43% 2.21% 3.13% 2.20% 1.13% 0.67% 1.08% 2.02% 0.43% 0.55% 0.54% 0.54% 0.54% 0.54%
3 PROCESS TANK AND MISCELLANEOUS
STRUCTURES ea 1 14,840,339.46 41.95%
Actual
SUPPLY AND INSTALLATION OF PROCESS PIPES INCLUDING Planned 0.00% 0.11% 0.24% 0.07% 0.00% 0.34% 1.61% 1.89% 1.67% 0.98% 1.14% 1.03% 0.53% 0.87%
4 SUPPORTS AND OTHER WORKS NECESSARY TO COMPLETE THE ea 1 4,656,886.70 13.16%
PROCESS PIPING WORKS Actual
PUMP AND MOTOR, FLOW METER, FLOAT Planned 0.32% 0.57% 0.06% 0.37% 0.23% 0.24% 0.24% 0.33% 1.68%
9 SWITCHES & OTHER ELECTRICAL DISTRIBUTION ea 1 3,129,399.79 8.85%
Actual
Planned
10 GROUNDING SYSTEM AND MANHOLES ea 1 1,270,802.58 3.59%
Actual
SLIPPAGE
PERIODIC
1.49% 2.92% 18.07% 9.35% 8.97% 23.53% 16.03%
% PROGRESS (Planned))
CUMMULATIVE
1.49% 4.41% 22.48% 31.83% 40.80% 64.33% 80.36%
PHYSICAL (Direct Cost)
PERIODIC
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
% PROGRESS (Actual)
CUMMULATIVE
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PERIODIC
527,222.22 1,032,505.56 6,393,526.40 3,307,572.68 3,173,063.89 8,322,944.30 5,670,978.15
% PROGRESS (Planned)
CUMMULATIVE
527,222.22 1,559,727.78 7,953,254.18 11,260,826.85 14,433,890.75 22,756,835.05 28,427,813.20
FINANCIAL (Direct Cost)
PERIODIC
- - - - - - -
% PROGRESS (Actual)
CUMMULATIVE
- - - - - - -
Prepared and Submitted by: Noted: Approved:
1 30 31
3.59%
-4.39% 0.00% 4.39%
0% 0.00% 0.00%
0% 0.00% 0.00%
- - -
- - -
Approved: