You are introduced to the topic of Piping and Process Instrumentation drawing. You will make then
use of the drawing techniques developed during the module.
Learning outcomes
After completion of this unit, you will be able to:
• Describe the different types of pipes and their uses.
• Define methods of pipe connections and their applications.
• Identify the different types of pipe fittings and valves.
• Draw/Interpret dimensioned single-line drawings with fittings and valves.
• Interpret isometric plans.
• Calculate linear dimensions and straight length of pipe in angular runs.
Recommended reading
• Students can read up on more detail for enrichment in the following resources (Access
Engineering Unisa online library): Piping Handbook, sections below describe the necessary
chapters to be read.
Practice questions
• Work through the given diagrams and examples. The lecturer will issue questions for you to
practise during the module. Refer to Study Unit 15 for additional practise questions.
Introduction
Plant process and thermo-fluid engineering systems are described using a variety of standardised
layout plans (e.g. Process Flow Diagram (PFD), System Flow Diagram (SFD), Process and
Instrumentation Diagram (PID or P&ID), Single or Double Pipe Layout Diagrams, equipment layout or
plot plans). The minimum information for these diagrams can vary across industries, companies and
geographical location, however, their fundamental objectives and intended communication remain
unchanged.
A pipe is a tube made of metal, plastic, concrete or fibreglass. Pipes are used to convey liquids,
gases, slurries or fine particles. A piping system is generally considered to include interconnection of
pipes, pipefittings, flanges and process equipment such as heat exchangers, vessels, pumps,
compressors, fans/blowers, valves etc, and so on. Piping is used in a wide range of applications, and
some are listed here:
• Plumbing
• Civil piping
• Process/industrial piping
• Transportation piping
A PFD from a commercial steam turbine vendor such as Turbomeca France may have some variation
in symbol representation of a turbine-condenser or flanged pipefitting compared to another firm
such as General Electric Steam Power Global.
The development of such diagrams is similar to the design process, continuously revised, improved
and creation of various revisions. Version control and document management are necessary
requirements. These diagrams are required at each of three levels in the project evolution cycle
briefly described below. These three stages are globally recognised in Project Management Best
Practice programs and cover industrial or commercial small to mega-build projects (Excluding the
Shut-down/Turn-around Projects):
Stage 1: Project inception, assignment of responsibilities, preliminary design, cost estimate, permits
and licenses, project scheduling, stakeholder engagement,
financial/insurance/underwriting/contract agreements, feasibility and desktop studies, identification
of required code and standards.
Stage 2: Detailed design, procurement, project costing, continued stakeholder engagement, detailed
multi-disciplinary system/component simulation, manufacturing drawings, prototyping, and
laboratory testing.
Stage 3: Project execution, project and site management, site delivery and construction,
construction management, plant start-up, commercial operation of systems, and hand-over to the
client, including maintenance/reliability/spares documentation and project close-out/project
debrief, snag list, and as-built documentation.
Consider each parameter and try to establish why they are important. Do some background reading
on the basic physics associated with each listed parameter.
Types of Piping and Selection Considerations
Students can read up on more detail for enrichment in the following resources (Access
Engineering Unisa online library): Piping Handbook, Section A3 Piping material. A brief description
is given below.
Typical pipe materials are (investigate some of the potential use cases for each material type):
• Cast iron
• Steel
• Copper/Copper Alloy
• Plastic
• Concrete
Main consideration for pipe selection includes temperature, pressure and corrosion. Other factors
include safety, cost, compliance with project specifications and codes/standards.
Temperature
The temperature factor is determined by the type of fluid in the pipe, or the quantity of external
heat exposed to or applied upon a pipe.
Example, suppose a copper pipeline is installed with its outer surfaces in the sun of average
temperature 30 ⁰C at five hours average daily sunshine during the summer months. This copper pipe
is now subjected to a steady thermal energy source causing the material temperature of the pipe to
increase. Adequate thermal expansion consideration must be taken into account at pipe fittings and
supports. Thermal stress must also be factored into the design.
Another example is the transport of cryogenic or high temperature fluids, in these scenarios the
effect of fluid temperature on the pipe material must be assessed and will include aspects such as
thermal expansion and thermal stress. Piping flexibility is then a requirement in the design of a
piping layout.
Pressure
The pressure factor is a process or system state variable and depends on the design of the piping
system. The pipe internal pressure will largely determine the wall thickness of the pipe. Mass flow
rates will largely determine the pipe inner diameter (volumetric flow rates are suitable for
incompressible flow and non-2-phase flow). Note both factors are coupled in the selection of pipe
diameter and wall thickness, that is, you need to consider both pressure and relevant flow rate in
the analysis.
Fail or abnormal operation considers scenarios such as sudden valve shut during normal operation. A
sudden pressure rise will occur within the pipe and this maximum must be accounted for in the
design of the piping system. Therefore maximum pressure may occur during abnormal operation. A
pipe blockage can create an obstruction and cause pressure rise and/or flow-rate reduction of fluid
transport within a pipe.
Safety
The design of the piping system must be safe during failed scenarios as best as possible and clearly
safe during normal operation. It is not possible to design for every abnormal scenario. Various fail-
over systems must be introduced (e.g. vents, emergency shut-off valves, secondary or multiple
alternate routing, and limit switches, warning alarms, process control sensing elements, and so on).
A HAZAD/OP analysis or similar will identify risks and establish the required fail-safe systems
necessary depending on the nature of the fluid, piping system and proximity or impact on civilian
environments. Example, a nuclear piping system will feature a far greater number of fail-safe
systems than a low-pressure domestic water reticulation system.
Corrosion
Transport of fluid within a pipe may contain trace, dissolved or contaminated elements such as
mineral salts, chemical deposits, solid particles, and so on. Mineral deposits could be naturally
occurring whereas chemical deposits can arise from chemical-dosing operations in a plant. Solid
particles such as flue gas can be entrapped in air pipelines or if scrubbers have inadequate measures
to eliminate flue gas particles. State changes (such as boiling) can cause mineral or solid deposits to
build up within the pipe, fluid motion creates relative movement between the solid particles and
pipe inner surface to cause wear.
Depending on the chemical potential between the fluid and pipe material, chemical reactions can
occur that will cause the pipe material to corrode. Galvanic corrosion can occur on both inner and
outer surfaces depending on conditions to support this effect.
Pipe Connection
Students can read up on more detail for enrichment in the following resources (Access
Engineering Unisa online library): Piping Handbook, Section A2 Piping Components: A2.6, A2.7,
and A2.8. A brief description is given below.
There are various pipe connection methods that may be used to join two pipes. The selection of a
suitable connection will depend on the following considerations among others:
• Weld
• Screwed
• Flanged
• Soldered
• Bell (Hub) and Spigot
• Mechanical joint
• Solvent
• Flaring
Fittings
Students can read up on more detail for enrichment in the following resources (Access
Engineering Unisa online library): Piping Handbook, Section A2 Piping Components: A2.1 until
A2.6. A brief description is given below.
Pipe fittings allow a pipe to change direction or size, or to allow branching or connections. These are
necessary when a pipe has to navigate corners, obstacles or change in elevation. Changes in pipe size
are often associated with a supply change in volumetric flow rate or mass flow rate (compressible
flows). Branching and connections often occur in network piping and may be integrated with pipe
size changes and changes in direction.
The three main types of fittings are screwed, welded and flanged. Some typical pipe fittings are
listed below.
• Welded
• Screwed
• Union
• Coupling and half-coupling
• Street elbow
• Bushing
• Plug
• Flanges
Valves
Students can read up on more detail for enrichment in the following resources (Access
Engineering Unisa online library): Piping Handbook, Section A10.1 Selection and Application of
Valves: A10.1, 10.2, 10.7 and 10.8. A brief description is given below.
Valve components help to control and regulate flow within a pipe or pipe network through several
functions: regulate flow rate, maintain a set pressure, and prevent backflow or pressure build-up.
Valves are required to control open/close flows in a network. These functions are often
accomplished through a specific valve type.
Selected equipment symbols are described here and used in this course (Madsen). These symbols
are used on process/piping and instrumentation diagrams and are contained in the Appendix. You
should be familiar with these symbols as your progress through your study years. However, for this
course we will consider a subset of these symbols for the purpose of an introduction to piping
drawing.
Additional equipment symbols from the Appendix may be added by discretion of the lecturer, keep
aware on course communication for this aspect.
Symbol Description
Pump
Heat exchanger
Concentric expander
Concentric reducer
Closed tank
Open tank
Fan
Pipe Drawings
The preparation of a pipe drawing involves inputs from a variety of sources and some of these are
listed below. We will consider only two types in the module: basic process or system flow diagram
and a basic process and instrumentation diagram.
A process flow diagram (PFD) or system flow diagram (SFD) is an input to the development of a
piping drawing which shows the pipe specification including fittings and valves. You will be required
to interpret a basic process or system flow diagram and thereafter construct or interpret a pipe
drawing.
Some basic examples are given below. Critique these and other such drawings to develop an
engineering response and judgment towards interconnected components. You are only required to
identify components and understand the basic process flow.
Note: no valves, flanges, fittings are shown on these PFDs. When drawing the piping diagram, we
then show the valves, flanges and fittings (we need to consult various other documents as stated
in the previous section to obtain the required information, however, this is not required for this
course).
Pump with inlet and outlet
One pump, showing inlet and outlet, and flow Two pumps, showing inlet and outlet, with a 3-
direction. P-804 is just a name given to the way valve coupling or Tee-section. P-801/2 is
pump. just a name given to the pump.
Boiler
Boiler showing Boiler Feed Water (BFW) in and High Pressure (HP) steam on the exit. Hot air
enters at the top (note the arrow direction for line 7) and the cooler air then exits at the bottom.
R-801 is just a name given to the boiler used in the PFD.
Air Preheater
This item heats incoming air for the boiler. Air flows from the left towards the right (note
horizontal arrow direction). Steam flows through the zig-zag symbol, where we note this symbol is
a heat exchanger (see symbol diagram above). H-801 is just a name given to the air preheater as
used in the PFD.
Single-line piping
This single-line drawing is a piping drawing that shows the size and location of pipes, fittings and
valves. The drawing is produced to scale and is readily developed to illustrate layout and fabrication
of a piping system.
The single-line piping drawing is a piping layout and is an orthographic drawing developed from a
varied set of documents. These usually include P&ID, site survey data, equipment location plan,
electrical layout, service facilities (water reticulation, sewage, firefighting, drainage, etc.) plan and
other such documents. The important aspect is to identify all the existing and planned
plant/process/equipment/building components before developing the piping layout. Guidelines by
relevant Codes, Standards and Government Regulations applicable to spacing and position
requirements among others are important. There may be several iterations of a single-line piping
drawing.
In this course you will be required to develop a single-line pipe drawing given a basic P&ID diagram
or a basic component layout/description which can be illustrated with a system flow diagram.
In this course you can provide piping specification by stating the following information:
• Pipe diameter
• Pipe length
• Pipe flow arrows
• Elevation location of all pipe direction changes in section views
• Pipe contents and identification number (if given)
• Size and type of valves and fittings (if given)
• Equipment name and numbers (if given)
½” – 4’ - W – SS-100
Where:
Therefore as a suggestion, use the following format for pipe-specification for this course, and
depending on the information given: Pipe diameter – Pipe length – Pipe contents – Pipe material –
System identification number. A simplified version showing only pipe dimensions is:
½” – 4’
Pipe fittings and valves are generally considered as illustrations unique to a pipe drawing as
compared to a PFD or PID. On the pipe drawing (example for a single line), all pipe fittings, valves
including welds will be distinguished from each other thereby showing such detail on a pipe drawing.
We will consider selected aspects for this course, and these are described in the figure(s) below
based largely on the Butt weld (see the following website for socket, threaded and additional items
for enrichment: http://www.wermac.org/documents/symbols_iso.html). We will use these symbols
when developing or interpreting the pipe drawing.
Additional pipe fittings and valve symbols from the Appendix may be added by discretion of the
lecturer, keep aware on course communication for this aspect.
Pipe connections1 Common valves1
1 http://www.wermac.org/documents/symbols_iso.html
Piping elevations and sections
Pipe elevations or sections are used to define vertical pipe location relative to a common datum;
usually taken as Bottom of Pipe (BOP), other reference points are Top of Concrete (TOC) or Top of
Steel (TOS). The elevations are defined with respect to pipe centres and the symbol is ℄ (in MS word
this is “2104 Alt+x”).
℄ EL. 6m
4”4m
4”1m
TO TANK EL. 5m ∴This height is 1m (=6m-5m)
4” F2
Foundation elevation
Pipe Diameter in is 1m from 0m datum.
“ and length in m.
℄ Elevation defined
on the left, and
2” F1 measured from FDN.
EL. 0m datum
℄ EL. 1.2m
BO TANK. EL. 1m
2”-4m
FDN. EL. 0m
2” V1 2” V2
5 Elbow 90⁰ 1
6 2” pipe 4m
7 4” pipe 5m
Abbreviation meanings:
2”- 1m
pipe-outlet segment:
2”- 4m
2”F2
1/2”F1 2”- 1m
2”- 5m
Pump
1/2”- 3m
2” V2
2” V2
1/2” V1
4 2” Tee Elbow 1
5 2” Elbow 90⁰ 1
6 1/2” pipe 3m
• Identify the symbols, fittings, and valves as indicated by the green dot.
• Re-draw a given single line diagram.
• Add pipe specification (as per suggested template).
• Add centre line dimensions.
Pipe Isometrics
You will recall an Isometric drawing is a three-dimensional representation of an object. The pipe
isometric allows elevation and transverse direction changes to be readily communicated using a
single drawing. The single line pipe drawing can only represent a projection of the isometric onto a
view i.e., Front, Top, and Side view. The single line pipe drawing is an orthographic representation of
the pipe isometric. The pipe isometric may represent fittings, valves, dimensions, additional notes
and instrumentation.
Two examples are shown below. Try to reproduce Figure 1 and Figure 2, show the pipe as a single
line isometric, you can include only the symbolic representation of the pipe fittings and valves
discussed previously. Choose your own suitable dimensions and scale.
Angular pipe runs are calculated using the Pythagoras theorem or suitable trigonometric
relationships. Such situations arise when the designer needs to use a pipe bend other than 90°, e.g.,
a 45°, or 60° pipe bend.
Figure 3 shows an example for angular pipe run, can you demonstrate the angular pipe length is
46.7”? The vertical distance is given be difference of the centre-line elevations, you are also given
the angle of the pipe bends, 45°.
Common Symbols
Pipe Connection/Fittings/Valves
Question 9.1
You have an incomplete diagram of a single-line pipe drawing with additional information
given below:
• A pump draws water through a 1/2” pipe from an in-line reservoir. The inlet pipe is
made of stainless steel and has a total length of 20 m.
• The pump discharges the water through a 2”stainless steel outlet pipe with a total
length of 10 m.
• A tee section tap-off is located on the same elevation as the outlet pipe. This length is 5
m and is a stainless steel 2” pipe.
• Vertical difference between pipe inlet and outlet is negligible.
Using sensible choices for component dimensions, component spacing, and line thickness,
you are required to complete the given drawing using your drawing instruments or CAD:
2”F2
1/2”F1
Pump
2” V2
2” V2
1/2” V1
You have an incomplete diagram of a single-line pipe drawing with additional information
given below:
A pump draws water through a 2” pipe from a reservoir located 3 m below the tank
foundation. The inlet pipe is made of stainless steel and has a total length of 10 m.
• The pump discharges the water into a tank through a ½”stainless steel pipe with a total
length of 10 m. This pipe terminates 1 m above Top of Tank (TO Tank).
• Vertical difference between pipe inlet and outlet is negligible.
Using sensible choices for component dimensions, component spacing, and line thickness,
you are required to complete the given drawing using your drawing instruments or CAD:
TO TANK. EL. 5m
BO TANK. EL. 0m
Pump
You are given three Orthographic Views of a pipe isometric. Redraw these three views using the
dimensions given and make use of line projections to understand changes in elevation and
transverse directions. Then use the dimensions given to produce an isometric view. The completed