CONTRACTOR's DAILY REPORT

Contractor: Contract Title: Date

WATER IN MOTION LLC DEIRA MARINA 05-Oct-2022

Contract No.: Report No. Area


WME20221022 WME20221022-WIM-CDR00028
Issued by: WATER IN MOTION LLC Date Issued: 05-Oct-2022 Time: 11:00 AM
Received by: Date Received: Time:
Shift: Day Hours Worked: 10 hours Weather:
Day Work: 10 hours
Night Work:
Manpower NO. Total Major Equipment NO. Total
Hours Hours
Project Manager 1 10
Engineer 1 10
Foreman 2 10
Time Keeper 1 10
Chargehand 2 10
Carpenter 9 10
Mason 18 10
Steel Fixer 3 10
Helper 8 10
Chainman 0
Operator 5 10
Store assistant 1 10
Sub contractor 0 10
Total 41 10
DESCRIPTION OF WORK PERFORMED TODAY 1 Excavation, leveling & compaction works at zone 1 & 6
2. Irrigation mainline excavation works at zone 1

3. Road base laying & compaction at zone 1 drive way

REMARKS BY CONTRACTOR (Delays, Interruptions, Deviations, Extra Work Activities, Conferences, etc. Relevant to Today's Work).