CONTRACTOR's DAILY REPORT

Contractor: Contract Title: Date


Design and Build the Temporary Structures and Landscaping works
WATER IN MOTION LLC for opening of Marinas in Deira Island
13-Oct-2022

Contract No.: Report No. Area


WME20221022 WME20221022-WIM-CDR00036
Issued by: WATER IN MOTION LLC Date Issued: 13-Oct-22 Time: 11:00 AM
Received by: NAKHEEL Date Received: 13-Oct-22 Time: 11:00 AM
Shift: Day & Night Hours Worked: 10 hours Weather: Sunny
Day Work: 10 hours
Night Work:
Manpower NO. Total Major Equipment NO. Total
Hours Hours
Project Manager 1 10 Shovel 1 10
Engineer 3 30 JCB 1 10
Foreman 2 20 Bobcat 2 20
Time Keeper 1 10
Chargehand 2 20
Carpenter 8 80
Mason 5 50
Steel Fixer 8 80
Helper 12 120
Pipefitter 3 30
Electrician 4 40
Chainman 0 0
Operator 4 40
Store assistant 1 10
Sub contractor 0 0
Total 53 540 40
DESCRIPTION OF WORK PERFORMED UPTO TODAY
1. Excavation & disposal of debris works at Zone 2 - 1580 M3 out of 1650 M3 (96%)

2.Compaction works for subgrade at Zone 2 - 7600 M2 out of 8044 M2 (94%)

3. Roadbase filling works at Zone 2 - 3100 M2 out of 8044 M2 (40%)

4. Roadbase compaction works at Zone 2 - 2900 M2 out of 8044 M2 (37%)


5. Excavation & disposal of debris works at Zone 1 - 5000 M3 out of 7200 M3 (70%)
6. Shuttering works for pcc for upstand & flush kerbs - 200 LM
7. Laterline pipe installation at zone 3 & 4
8.. Electrical conduiting works at Zone 3

9.. PCC works - 70 M2

REMARKS BY CONTRACTOR (Delays, Interruptions, Deviations, Extra Work Activities, Conferences, etc. Relevant to Today's Work).

CONTRACTOR'S AUTHORIZED REPRESENTATIVE (Signature) TITLE DATE


Abishek.v Site Engineer 13-Oct-22

CLIENT COMMENTS AND/OR EXCEPTIONS:

ENGINEER: DATE

(Signature)
ZONING LAYOUT

ZONE-01 ZONE-04 ZONE-03


ZONE-02