Professional Documents
Culture Documents
Cem103 Lecture 2 Cost Estimating Components
Cem103 Lecture 2 Cost Estimating Components
Cem103 Lecture 2 Cost Estimating Components
Kinds of Estimates
Range in Accuracy
Floor Area Estimate ± 40%
Function Estimate ± 30%
Factor Estimate ± 20%
Parameter Estimate ± 15%
Contractor Detailed Estimate ± 7%
1. Floor Area Estimate – Experience showed that for similar buildings, the building cost are very
closely related to floor area. It is based on historical data.
2. Function Estimate – Measures the cost of a building relative to its use or function.
Type of Project Function Estimates
School Building Cost per student
Hospital Cost per bed
Theater Cost per seat
Parking Space Cost per parking space
3. Factor Estimate – based on historical data. However, unlike other estimating models that gather
and structure past cost data, the factor estimate develops factor for each components as a function
of a predominant cost. Example:
4. Parameter Estimates – this is an improvement over the floor area estimate because several
parameter measures are used instead of one. Lump sum cost of trades are related to component
system of construction. Examples:
a. Structural Steel Cost related to gross area covered.
b. Parking area per number of building occupants.
c. HVAC cost per CM of the building.
b. Labor
• Worker’s base wage + fringe benefit
• Productivity
c. Equipment
• Rental or depreciation
• Operator
• Fuel and maintenance
• Cost of moving equipment to and from jobsite
• Set up costs
Maximizing chances of getting contracts
VERTICAL ESTIMATES
INTRODUCTION
The program derives unit cost and generates bill of materials for the following items of work:
❖ Earthworks ❖ Masonry
❖ Concrete ❖ Painting
❖ Rebars ❖ Structural Steel
❖ Formworks
The program is flexible and adaptable to any company because of two features:
1. There are three existing databases for the cost of materials, labor and equipment. The databases
are accessed by all the estimating routines in the program and the contents of the databases may
be revised by the user anytime.
2. The factors used in preparing the routines are herewith attached for the user’s reference. For a
small additional cost, you may request that the factors be customized for your company only.
ESTIMATING FACTORS
EARTHWORKS
1. EXCAVATION
2. BACKFILLING
Foundation 1.00
Beam 1.05
Slab 1.03
Column 1.08
Shear Wall 1.05
Stair 1.05
Tie wire (kg) = kg of steel x 1.05 x 1/78
Labor = 80 MH/1000 kg of steel
CONCRETE WORKS
Structure Difficulty Factor
Foundation 1.00
Beam 1.15
Slab 1.20
Column 1.15
Shear Wall 1.15
Stair 1.25
Rebars
Spacing in meters
Vertical Horizontal LM/SM
0.60 0.60 3.6
0.80 0.80 3.2
0.80 1.00 2.8
1.00 1.00 2.4
1.00 1.20 2.3
Labor
FORMWORKS
Man-hour table per SM
Structure Assemble Erect Strip/Clean Repair
Foundation 0.53 0.32 0.32 0.21
Beam 0.86 0.43 0.43 0.43
Slab 0.64 0.32 0.32 0.32
Column 0.63 0.43 0.32 0.32
Shear Wall 0.73 0.43 0.43 0.21
Stair 1.07 0.75 0.43 0.53
If No. of Use = 1 F= 1
If No. of Use = 2 F = 1.8
If No. of Use = 3 F = 2.7
Materials
Plywood (pcs) = SM of forms x 10.76 /(F x 32)
Form 2 x 3 x 12 (pcs) = SM of forms x 0.86/F
Form 2 x 4 x 12 (pcs) = SM of forms x 1.61 / F
Nails (kg) = Plywood x 0.018 + Form 2 x 3 (0.1) + Form 2 x 4 (0.05)
Form Oil (lit) = Plywood x 0.048
STEEL WORKS
Basic Input
1. Tonnage of steel required
2. No. of paint coats required
Materials
Oxy-acetylene 2.2 sets/ton (1 set = 2 oxygen ; 1 acetylene)
Welding rod 2.5 % of steel tonnage (20 kgs/box)
Paint
Area 300 SF/ton of steel
Coverage 300 SF/gal of paint/coat
Mix 2 gal paint
1 gal thinner
Labor
Fabrication 0.55 MH
Erection 0.40
Delivery 0.10
Painting 0.05
1.10 MH/kg = 1100 MH/ton
Equipment
Fabrication 50% of Fabrication labor cost
Erection 50% of Erection labor cost
PAINTING WORKS
SAMPLE COMPUTATION
SAMPLE COMPUTATION
Order:
SAMPLE COMPUTATION
SAMPLE COMPUTATION
Order:
20 mm thick Plywood : 118 x 10.76 /( 32 x 1.8) = 23 pcs @ P 620 = P 14,398.00
2 x 3 x 12 lumber : 118 x 0.86 /1.8 = 57 pcs @ P 51 = 2,913.00
2 x 4 x 12 lumber : 118 x 1.61 /1.8 = 107 pcs @ P 68 = 7,246.00
CW Nails : (118 x 0.018) + (57 x 0.1) + (107 x 0.05) = 12 kgs @ P 25 = P 3,000.00
Form Oil : 118 x 0.048 = 2 lit @ P 5.50 =P 11.00
Total = P 24,867.00
SAMPLE COMPUTATION
SAMPLE COMPUTATION
Order:
Masonry Neutralizer : 0.1 x 425 = 42.5 liters @ P 55.00 = P 2,338.00
Permacoat Latex : 0.15 x 425 x 2 = 127.5 liters @ P 52 = 6,630.00
Patching Compound : 0.05 x 425 = 21.25 liters @ P 12 = 2,255.00
Sandpaper :
0.10.25 (425) = 42.5 SM @ P 19.80
Total
= P 1,842.00
= P 10,064.00
Material Unit Cost : 10,064.00/425 SM = P 23.68/SM
Labor Unit Cost : (0.4 + 0.2) (117 + 2 x 112)/(8 x 3) = P 8.53/SM
Total = P 32.21/SM
Total Cost : (P 32.21/SM) (425 SM) = P 13,687.10
Duration : (425 x 0.6)/ (8 x 3)] = 11 days
The program derives unit cost and generates bill of materials for the following items of work.
1. EQUIPMENT ESTIMATE
It costs money to own an equipment. One part of ownership cost includes the interest on the
money invested, taxes, insurance, registration and storage.
Although the owner pays cash for the equipment, he should charge interest on the investment,
as the money spent for the equipment could be invested into another asset that would return the
interest to the owner. Some owners charge a fixed rate of interest against the full purchase cost
of the equipment each year it is owned. This method gives an annual interest cost that is higher
than it should be. One approach is that for each year that the equipment is used, the owner should
deduct form its earnings an amount equal to the annual cost of depreciation. After the equipment
has been used for the estimated depreciation period, the owner will have recovered its original
cost.
The average annual cost of interest should be based on the average value of the equipment during
its useful life.
𝑃 (𝑁 + 1) − 𝑆(𝑁 − 1)
𝑌𝐴𝑉 =
2𝑁
b. DEPRECIATION
The loss in value of a piece of equipment over time generally caused by wear and from use,
deterioration and reduced need (obsolescence). The owner must recover this loss of value in
equipment that he owns during its useful life.
1. STRAIGHT LINE (LS) – the most widely used method in computing depreciation for
construction equipment.
(𝑃 − 𝑆 )
𝐷=
𝑁
Where N = number of years of economic life of equipment or the recovery period allowed
for income tax purposes, asset life
P = Purchase price
D = Amount of depreciation for any year
S = Estimated resale value at the end of economic life (salvage value)
OPERATING COST
Operating costs are those associated with the operation of a piece of equipment. It includes fuel and
lubrication costs, operator cost, and minor maintenance and repair costs. The other costs involved in
equipment are major maintenance, major repair, and tires. Either way, they represent a significant cost
category and should not be overlooked.
The annual cost of maintenance and repairs may be expressed as a percent of the annual cost of
depreciation, or it may be expressed independently of depreciation. In any event, it should be
sufficient to cover the costs of keeping the equipment operating.
b. Fuel Consumed
When operating under standard conditions, a gasoline engine will consume approximately 0.06
gallon per flywheel horsepower hour, while a diesel engine will consume approximately 0.04 gallon
per fwhp-hr.
Engine Factor
Example:
Operation of engine at maximum power = 5 sec out of a cycle of 20 sec, the remaining 15 sec, the
engine may operate more than ½ of its rated power. Assuming a 160 fwhp engine operates only 50
minutes per hour.
c. Lubricating Oil
The quantity of lubricating oil used by an engine will vary with the size of engine, the capacity of
the crankshaft, the conditions of the piston ringers and the number of hours between oil changes. It
is common practice to change oil every 100 to 200 hours operation. It is assumed between changes
will be 0.006 lbs.
hp 𝑥 0.006 per hp − hr 𝑐
𝑞= +
7.4 lb per gallon 𝑡
An equipment is assumed effective only 50 minutes per hour. Equipment Unit Capacity may be
expressed in:
1. Cycle time – time in minutes required to complete one cycle.
SAMPLE COMPUTATION
𝑃 (𝑁 + 1) − 𝑆(𝑁 − 1)
𝑌𝐴𝑉 =
2𝑁
0.14 (219,000)
Interest Cost = = P 12.77
2400
0.06(219,000)
Taxes, Insurance, Storage = = 5.48
2400
(450,000 – 45,000)
Depreciation = = 11.25
15(2,400)
Total = P 29.50
Maintenance & Repairs = Depreciation =P 8.44
Fuel = (108) (0.60) (0.06) (10.00) (3.785) = 147.16
108(0.60)(0.006)
Lubrication = [ + 0.04] (31.00)(3.785) = 10.86
7.4
Operator = (150 + 100)/8 = 31.25
Sub-Total = P 197.71
Grand Total = P 227.21
227.21 25
Equipment Unit Cost = ( ) = P 9.47/CM
12 50
cu.m.
2. CONCRETE DRAINAGE PIPES
Reinforced
300 mm dia x 1 m 0.19 0.024 3.60 2.4
375 mm dia x 1 m 0.22 0.027 4.05 2.7
450 mm dia x 1 m 0.26 0.032 4.80 3.2
600 mm dia x 1 m 0.34 0.042 6.30 4.2
750 mm dia x 1 m 0.42 0.053 7.95 5.3
900 mm dia x 1 m 0.52 0.064 9.60 6.4
3. EARTHWORKS
a. Excavation
b. Backfilling
c. Compaction
d. Clearance and Grubbing
4. RIPRAPPING WORKS