Professional Documents
Culture Documents
Untitled
Untitled
The relay coordination was done after performing the load flow analysis and short circuit analysis. it is
done how relay is being coordinated in a systematic way and therefore protecting their own zone.
The relay time characteristic was plotted to see the operating time of each relay with respect to different
faults.
Time operation of each relay when 3 phase short circuit was created at busbar
Maximum three phase short circuit was created as shown in above figure. As per the fault level different
timing operation was obtained. The vertical lines show the fault current level and operating time of each
feeder. The relay with most minimum time trips first, followed by the second minimum if the first one
fails to clear the fault and the relay with highest time trips at the last. When the fault was created on
33KV bus the feeder relay does not operate and it shows good coordination.
Time operation of each relay when 3 phase short circuit was created at 1% of line length
Similarly, 3 phase short circuit was created on the length of feeder line. When it was created on 1% of
length line, the feeder relays fail to operates within its time set. i.e., the feeder relays operate in much
faster time as we can see in the above figure, the vertical line does not intersect with the curve. The
relay at transformer side operates as required. Similarly we have created the fault at different line length
as shown in figure below.
Time operation of each relay when 3 phase short circuit was created at 15% of line length
Time operation of each relay when 3 phase short circuit was created at 50% of line length
Time operation of each relay when 3 phase short circuit was created at 75% of line length
Time operation of each relay when 3 phase short circuit was created at 99% of line length
Time operation of each relay when 3 phase short circuit was created at load point
After creating a 3-phase short circuit at different line length we observed that the feeder relay does not
operates in required time for certain line length. It does not operate for less than 15% of line length.
Which effects the coordination of the system. Other than that, we can conclude that when the fault
occurs at feeder length (greater than 15%) the feeder relay trips first than the other two transformer
relays. And with the increase in the line length, the fault current decreases and operating time of relay
increase.
B. Time operation of each relay when 2 phase short circuit was created at 33KV busbar
Similarly, 2 phase short circuit fault was created to check the characteristics of each relay setting.
Time operation of each relay when 2 phase short circuit was created at 1%
Time operation of each relay when 3 phase short circuit was created at 15%
Time operation of each relay when 3 phase short circuit was created at 50%
Time operation of each relay when 3 phase short circuit was created at 75%
Time operation of each relay when 3 phase short circuit was created at 99%
Time operation of each relay when 3 phase short circuit was created at load point