DPR OF DEVELOPMENT OF

BHARATPUR-DEEG-ALWAR
ROAD(SH- 14)
SUBJECT- PLANNING FORMULATION, APPRAISAL & MANAGEMENT
SUBJECT CODE- PLN 3204
COURSE- BPLAN
YEAR- III
SEMESTER- VI
SUBMITTED BY-
AISHWARYA SINHA(201109037)
ADITYA GUPTA(201109016)
KEY PLAN
&
LOCATION

Approval required are-


• Land Acquisition
• Tree Cutting Permission
• Utilities Shifting
• State Pollution Control Board
• Environmental Clearance
SALIENT FEATURES OF EXISTING ROAD

• There are around 20 villages


along the project road
CIVIL COST & FINANCIAL COST OF
PROJECT (in Crores)
2 lane + hard shoulder
• Cost is based on current basic SOR (schedules of rates), NH division
COMPONENTS
I. LOCATION & KEY PLAN
II. SURVEYS- (topographical, traffic, geotechnical, road investigatory)
III. INVESTIGATION- (road & pavement, bridges & culverts)
IV. DETAIL DESIGN
V. EIA & SIA
VI. ESTIMATION OF QUANTITIES & PROJECT COST
VII.ECONOMIC & FINANCIAL LIABILITY
LAND ACQUISITION REPORT
CONTRACT DOCUMENT
CONCLUSION
PROPOSALS

PROPOSED
BYPASSES &
CROSS-