Professional Documents
Culture Documents
BL501. Learning Pack 5 - Masonry Works
BL501. Learning Pack 5 - Masonry Works
Masonry refers to constructing buildings of bricks and blocks. The following is an example
of the calculating Unit Rate of the Blockwork.
Masonry
Example of Unit Rate analysis
Materials
Area (in elevation) of a block (400 x 200mm block) is 0.4 x 0.2 that is 0.08m2
1 1
Therefore 1m2 wall requires that is 12 blocks
0.08 2
Standard 400 x 200 x 200mm thick hollow blocks cost K188.00 per pallet of 100 blocks
Purchase price of 100 blocks ------------------------ K188.00
Delivery to site say ----------------------------------- K20.00
Offloading and stacking say ------------------------ K5.00
Price per 100 delivered and offloaded ------------ K213.00
213.00
Therefore price per block, = K2.13
100
1
For 1m2 of wall, 12 blocks @K2.13 ---------------------------------------- K24.75
2
1|Page
Waste on blocks, 7.5% ---------------------------------------------------------- K1.86
Mortar;
See Table 3 in Concrete Works handout
0.40 tonnes of cement required, therefore No. of 40kg bags = (400/40) = 10 bags
1.12m3 of concreting sand is required
Note: Based on Block & Brick Manual, 64m2 of wall will require 1m3 of mortar. Therefore
1m2 of wall will require 0.015625m3 of mortar.
Labour
Gang of 1 blocklayers: 2 labourers
That is 1 blocklayer: 2 labourer
In every hour, 1 blocklayer @ K4.50 = K4.50
2 labourer @ K3.60 = K7.20
Gang cost per hour-------------------- -K11.70
2|Page
Example 17 Masonry Works
8. Blockwork in 400 x 200 mm standard hollow concrete blocks in cement
mortar (1: 4)
8.2 Rough raking cutting to 200mm hollow----------------------------------------M
Materials
Waste of blocks due to raking cutting 1 metre, say 2 blocks @ K2.13 -- K4.26
Labour
Gang cost per hour (as before) K11.70
Output is 3m of cutting per hour
Cost of raking cutting 1m is (K11.70/3)--------------------------------------- K3.90
Net Unit Rate per M ------------------------------------------------------------ K8.16
Profit + on-cost, 10%----------------------------------------------------------- K0.82
Unit Rate per M------------------------------------------------------------------ K8.98
NOTE: From these two calculations, it can be concluded that 100m2 of block wall will
require 13m3 of concrete filling (corefilling)
Data:
Price of 40kg cement per tonne cost K300.00 (ii) Delivery to site cost K10.00 (iii) Unloading
and storing i.e. 1.5 hours labourer @ K3.61 (iv) Stockpile waste, - Cement (2.5%), Sand
(10%) (v) Sand cost K45.00 per m3 (vi) Aggregates cost K50.00 per m3 (vii) Blocklayer @
K4.50/hr and Labourer @ K3.00/hr
Materials
Price of cement per tonne of 25 bags ------------------------ K300.00
Delivery to site ------------------------------------------------- K10.00
Off loading and storing, 1.5 hrs labourer @ K3.61 -------- K5.42
Price per tonne, off loaded and stored ----------------------- K315.42
3|Page
Therefore price per bag, K315.42 / 25 = K12.62
Labour
Placing 1m3 of concrete in hollow blocks
1 Blocklayer @ K4.50/hr
1 labourer @ K3.60/hr
Total labour/hr = (4.50 + 3.60) = K8.10
Assume Output is 1.2m2 per hour
Cost of laying (K8.10/hr ÷ 1.2m2/hr) ------------------------------------------ K6.75
Filling 100m2 of block wall will require 13m3 of concrete @ K176.67--- K2296.71
4|Page
Example 19 Masonry Works
8. Blockwork in 400 x 200 mm standard hollow concrete blocks in cement
mortar (1: 4)
8.3 200mm lintel blocks including pointing to both faces................................M
Materials
Overall length of lintel block of 400mm x 200mm
Standard 400 x 200 x 200mm thick hollow lintel blocks cost K280.00 per pallet of 100 blocks
Mortar
1m2 (12.5blocks) of block wall = 0.015625m3 of mortar
1 block = (0.015625m3 / 12.5 blocks) = 0.00125m3 of mortar
Labour
Gang of 1 blocklayers: 1 labourers
That is 1 blocklayer: 1 labourer
In every hour, 1 blocklayer @ K4.50 = K4.50
1 labourer @ K3.60 = K3.60
Gang cost per hour-------------------- -K8.10
5|Page
Class Activity 1: Calculate the unit cost of the following and allow for 20% as profit
(a) Block in 200 x 200mm standard hollow concrete blocks in cement mortar (1:4) to
200mm walls including pointing to both faces.................................................................m2
Class Activity 2: Calculate the unit cost of item C but include the use of Mixer (as per
previous activity) and allow for 20% profit
Class Activity 3: From these four (4) items, create a spreadsheet approach with cost
break-up (include a column for profit as well)
6|Page