: QUO/JUNE/2022/098/PAKATANREKAARKITEK/R2
DATE: 28/06/2022
PROJECT: Proposed FLOWCRETE RESIN FLOORING SYSTEM for: SOYA BEAN FACTORY AT
BANDAR BARU ENSTEK
Surface preparation by using Shot blasting machine/ Heavy duty scarifier machine. All substrates must be clean
and free from dust and loose particles. All traces of contaminants such as oils, fats, greases, paint residues,
chemicals, algae and laitance should be removed by using hot torch method and shot blasting. All cracks are
subject to further movement. Should be opened out, cross cut, and filled with Flowtex PT.
(for visible area only)
Kindly refer to the below substrate requirements needed prior epoxy/polyurethane application.
i. Power floated concrete without floor hardener
ii. The compressive strength of the concrete substrate should be min 25N/mm2.
iii. The moisture content should be less than 75% in concrete with the presence of effective damp
proof membrane.
iv. The concrete floor level should not more than 5mm deviation over 3 meter straight edge (SR2)
2. PAYMENT TERM
- 40% down payment and progress payment shall be 30 days from the date of invoicing.
3. MATERIAL LEADTIME
1 to 2 weeks from the date receive of official Purchase Order.
4. PRICE VADILITY
1 month from the above date.
9. SURFACE REGULARITY
The installation of Flowcrete product will follow the profile of the underlying substrate.
Shirlie Tan
___________________ _____________________________
Shirlie Tan COMPANY'S STAMP & SIGN
Sales Manager, DATE:
Tremco CPG Malaysia Sdn Bhd
Mobile: 012 – 964 7643