Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Feature Report

Engineering Practice

Calculations in Process
Engineering
Mohammad Toghraei
Knowing how specific calculations
differ can focus your efforts
FIGURE 1. The
Single flow 2-phase 3-phase Non-
Engrowth Training most popular
flow flow Newtonian
Design types of calcula-
fluid tions are related
Liquid Gas Different Liquid/gas

T
he topic of carrying out process pairs /solid to the sizing
engineering calculations in the Line-sizing
of lines, tanks,
most effective manner can be vessels, pumps,
Tank/vessel compressors heat
considered in these four ways: exchangers and
1. The purpose of the calculation Hydraulic calc.:
PSVs. This igure
pump/comp CV
2. The content of the calculation shows these
3. The method used to carry out the HX sizing Increasing difficulty general items and
calculation their variations
PSV sizing
4. The performer of the calculation
she specifies the required setpoint • Step 1 requires identifying suit-
The purpose of the calculation of the PSV, the release rate and a able input values (assumptions)
Engineers typically carry out cal- few other items. This effort does • Step 2 involves choosing and using
culations for a variety of purposes not require the engineer to design a an appropriate methodology —
including the following: PSV by sizing the orifice diameter, one that uses the parameters es-
a) To conduct a technical or eco- spring constant and so on. tablished in Step 1 — to arrive at
nomical evaluation of a plant or It is clear that no process engineer an answer that has the required
specific unit (such as a heat and designs a centrifugal pump just by accuracy in the available time slot
material balance), to carry out calculating the impleller diameter • Step 3 involves the evaluation
evaluations in the early stages of and vane angles. Today, process en- and verification of assumptions
the project, or for use while writ- gineers can expect that the manu- and results
ing studies or technical memos facturer will provide much detailed Step 1. Identifying suitable
for stakeholders information to support the process input values (assumptions). Ju-
b) To size, rate or specify a piece of of designing and specifying process nior engineers tend to struggle with
equipment equipment. As a result, there is very this step. Too often in the university
c) To generate a specific operational little “pure designing” in today’s setting, the instructor provides the
procedure specialized market; rather, there “given values,” whereas in real-world
Sizing, rating, and specifying are is always an element of specifying situations, it is up to the engineer to
three distinctly different goals of involved when carrying out sizing determine which input values and
calculation efforts. Process sizing calculations. assumptions are relevant. This ef-
means defining all the (process) as- While specifying and sizing are fort requires three sub-steps:
pects of the equipment, so that the concepts related to equipment or 1. Find effective parameters. Engi-
manufacturer can produce it with instruments that are planned to be neers need to find the parameters
little process knowledge. Sizing ef- procured later, rating is an activity that will impact the results they are
forts typically involve calculations that involves calculations associ- seeking. For example, within a spe-
that aim to identify all the un- ated with existing equipment com- cific issue, there could be three pa-
knowns associated with one equip- ponents. During rating, the ques- rameters M, N and P. In this step,
ment component, to enable the fab- tion that the engineer is trying to these three parameters need to be
ricator to produce that component. answer is whether an existing com- evaluated in order to recognize the
By contrast, when specifying an ponent can be used in a specific new ones that are most relevant to the
equipment component or instru- application or not. Rating efforts problem at hand. At this stage, the
ment system, the engineer must de- require evaluating current equip- engineer should be able to evaluate
fine a specific amount of information ment for a specific type of service the three parameters of M, N, and
for the manufacturer, and can then and conditions. P to determine that, for example, M
expect the manufacturer to satisfy and P are the only required param-
those requirements. For example, The content of the calculation eters (or the most relevant param-
when an engineer plans to buy a Calculations involve the following eters) and these will be considered
pressure safety valve (PSV), he or three steps: further in Step 2. Or with the level
CHEMICAL ENGINEERING WWW.CHE.COM DECEMBER 2013 51
CHOOSING THE BEST MEDIA
Engineering Practice ome companies accept calculations that are done by hand, while others will utilize or even

of required accuracy, perhaps only


S require the use of specific software. With hand-done calculations (as opposed to those car-
ried out using a spreadsheet program), a clear disadvantage is that any adjustments will
require all of the subsequent steps to be re-done (That is, there is no way to link equations so
that they will be automatically updated if a given parameter is changed).
M will be considered in Step 2. By comparison, spreadsheet programs, such as Microsoft Excel or an equivalent data pro-
2. Select a numerical design value. cessor, are designed so that any changes will result in the computer adjusting all subsequent
In this step, a numerical value needs steps automatically. The disadvantage to this is that the calculation process is not always vis-
to be assigned or determined for the ible, as some formulas may be buried within a cell. To maximize the advantages and minimize
selected parameter(s) identified in the disadvantages of a spreadsheet program, the following steps should be taken:
the previous step. The magnitude
of the design or rated parameter is
that number (or range) that covers conservative approach may be too for a second run-through or recon-
all the different scenarios that could conservative in a way that makes sideration of Steps 1 and 2.
be encountered during the operation it unacceptable. In such cases, the As mentioned, the design process
of the plant, plus a reasonable mar- original — albeit more complicated might need some iteration to reach
gin. For example, Mdesign= 6 could — route must be taken. This may the most appropriate results. For
be a wise decision when parameter occur in situations in which the example, if the calculation is sizing
M can accept magnitudes of 2.0, 3.5 worst-case scenario has led to ex- or specifying, it will result in one of
and 5 during plant operation. traordinarily oversized equipment the following three conditions:
Trial-and-error efforts, which or equipment that is overly difficult 1. A case involving an extremely
typically require an educated guess or costly to construct. inexpensive or small piece of equip-
at the beginning and some adjust- Discussed below are some of the ment. In this case, the equipment
ments made along the way based popular simplifying conversions often cannot be custom-made but
on final results, are often required. that are widely used today: must be selected off-the-shelf. As a
Certain rules-of-thumb can help 1. The thermodynamic approach result, the final piece of equipment
engineers to make a better pre- versus the kinetic approach. Most may not be exactly what is required
liminary guess, and this can help often, the thermodynamic approach via the calculations, and adjust-
to decrease the calculation time. is selected due to its well-estab- ments may be required to mate the
The reason for this iterative route lished methods and its popularity in piece into the overall configuration.
is that each methodology has some terms of published works and data. For this reason, it may be efficient to
limitations, and at the end of the For example, finding the evapora- have the specifications of standard-
first run of calculations, any limi- tion rate from a surface of a liquid is ized (off-the-shelf) equipment on
tations should be checked to make challenging. It depends on different hand throughout the course of the
sure they have been met. parameters and requires the con- calculations, so that adjustments
Step 2. Choosing the right meth- sideration of various phenomena can be made as the calculations are
odology. This step is very impor- including heat transfer and mass being constructed.
tant. The selected methodology must transfer. However, by changing the 2. A case involving moderately sized
be accurate and at the same time, approach from kinetic (in which or moderately complex equipment.
the required engineering time for the evaporation rate is calculated) In this case, the equipment will typ-
that method should be justifiable. A to thermodynamic (in which only ically be custom made in the shop.
skilled process engineer should be the saturated pressure of the vapor It is important to keep in mind
able to identify calculation method- above the liquid surface is calcu- the dimension limits of the shop
ologies for each situation that meet lated), the effort will be simplified. in question. If the item is too large,
the specific accuracy and time re- 2. Assuming steady-state vs. un- it will have to be fabricated in the
quirements or constraints. steady-state conditions. Most often, field, and the price will be consider-
For example, during pipe sizing, the steady state is selected, thanks ably higher. In an illustrative case, a
an engineer should be aware of the to its well-established methods and careless designer may design a tank
standard pipe sizes that are already simplicity of its calculation using with diameter half a meter above
available on the market. Designing inexpensive software or even a the limits of the shop, and therefore
a given pipe that is sized to, for in- spreadsheet progra. For example, unnecessarily cause a price jump
stance, two decimal points, does not analyzing PSV opening phenomena because the tank suddenly changes
make sense, as the market already is not an easy task as it is inher- from a shop-fabricated item to a
provides defined pipe sizes. ently an unsteady-state operation- field-fabricated one. Shop limita-
Meanwhile, in some cases, one sce- However, during PSV sizing, we tions are imposed not just by the
nario can be “converted” to another often pick the largest flowrate that machinery-manufacturing limits
case, to enable the use of a simpler is considered a steady-state case for in the shop, but by the road restric-
version of the methodology and a mere few milliseconds during the tions or overpass weight limits that
shorten the calculation time. Such opening of the PSV. will affect the transportation of the
a “conversion” effort is only accept- Step 3. Verifying assumptions equipment to its final destination.
able if this new scenario is the more and results. This is not merely the 3. A case involving a large piece of
conservative approach. However, in end of the task, but is a very crucial equipment. In this case, the equip-
some cases, the more simplistic and step, the results of which may call ment will typically be custom
52 CHEMICAL ENGINEERING WWW.CHE.COM DECEMBER 2013
1. Ensure that all of the calculations are interconnected in such a way that altering the inputs will
alter the results accordingly. Take care in this effort, as any disconnections may be disastrous,
because adjustments to the input will not result in appropriate alteration to the output.
2. Ensure that all manual input is visible and clearly marked to give the designer the flex-
ibility to alter it. Any hidden manual input may not be recognized by a new designer as a
potentially adjustable value. for water treatment); PSV sizing
3. Ensure that new users do not disable any pre-existing macros in the program.
(performing the first steps of PSV
4. Ensure that iteration calculations are enabled where required.
5. Ensure that the calculations are legible both on the computer and in print.
sizing including defining pressur-
6. Ensure that when the flexibility of adding a new row or column is provided in a template, izing scenarios, finding the credible
all of the information is transferable. Such flexibility exists in some modular pump-sizing and governing scenario(s) and re-
spreadsheets. ❑ lease rate calculation)
Senior design process engineers: Re-
actors, especially complicated ones,
made in the field at a higher cost. cess engineers: Sizing of tanks and and industry-specific equipment. n
This high cost is due to the fact vessels; hydraulic calculations for Edited by Suzanne Shelley
that skilled workers and various pumps, compressors and control
required utilities will need to be valves; sizing of heat exchangers;and
shipped and present at the field in PSV sizing after receiving release Author
Mohammad Toghraei,
order to construct the larger compo- rates from an intermediate or se- P.Eng., is currently a con-
nents. As a result, this case is often nior engineer sultant and instructor with
Engrowth Training (www.
used as a last resort. Intermediate/senior design pro- engedu.ca; Phone: 403-808-
cess engineers: All of the above 8264; Email: moe.toghrae@
engedu.ca). Toghraei has over
The performer of the items, in multi-phase cases (that 20 years experience in the field
of industrial water treatment.
calculation is, two-phase flow for pipe sizing); His main expertise is in the
Generally speaking, each group of separators (two- and three-phase treatment of wastewater from
oil and petrochemical com-
process engineers is expected to be separators, gas-knockout drums, plexes. For the past seven years he has taken on
able to carry out specific types of sedimentation vessels, clarifiers); different technical and leadership roles in water
treatment areas of SAGD projects. Toghraei has
calculations, based on this rough other industry-specific items (such received a B.Sc. in chemical engineering from Is-
classification: as distillation towers for petroleum fahan University of Technology and an M.Sc. in
environmental engineering from the University
Junior/intermediate design pro- refining, and ion-exchange systems of Tehran, and is a member of APEGA.

PLASTIC CONTROL VALVES FOR


ALL YOUR CORROSIVE APPLICATIONS
Collins plastic control valves are
highly responsive control valves
designed for use with corrosive
media and/or corrosive atmos-
pheres.
Collins valves feature all-plastic
construction with bodies in PVDF,
PP, PVC and Halar in various body
styles from 1/2" - 2" with Globe,
Angle or Corner configurations and
many trim sizes and materials.
Valves may be furnished without
positioner for ON-OFF applications.
Call for more information on our
plastic control valves.

P.O. Box 938 • Angleton, TX 77516


Tel. (979) 849-8266 • www.collinsinst.com

Circle 14 on p. 68 or go to adlinks.che.com/45779-14
CHEMICAL ENGINEERING WWW.CHE.COM DECEMBER 2013 53

You might also like