NO AREA DESCRIPTION (WORKFRONT) TOTAL Unit INSTALLED

QTY

1 WTP
Power & Control Cable

Pulling Cable 393 Line 374

Termination

786 Line 411

Cable Tray

Ladder Tray 272 m 272

Perforated Tray 283 m 283

Panel and Junction Box 37 Unit 22

Instrument Installation 292 Ea 143

Conduit 3185 m 3000

Valve 65 0

Earthing 2275 m 2000

Lightning Protection 11 set 9

Fire Alarm 53 set 15

Communication 13 set 0

Lighting 102 Ea 49
EXPECTED MATERIAL ISNTALLATION
REMAINING STATUS MATERIAL PROGRESS
ONSITE START

19 95% on progress

375 52% on progress

0 100%

0 100%

59% on progress

149 49% on progress

185 remaining material still waiting for 94% 4/7/2023 4/8/2023


delivery

on progress

275 88% on progress

0 82% on progress

38 28% on progress

13 0% on progress

53 48% 4/11/2023
ISNTALLATION
REMARK
FINISH

4/13/2023

5/15/2023

Done

6/7/2023

5/15/2023 Field Instrument not needed for calibration

4/17/2023 Additional material shall be onsite on 7 April 2023

Most of the material already installed, but not yet termination


5/5/2023
and on process installation of the tubing

4/17/2023

4/12/2023

4/15/2023

5/15/2023 on progress

Remaining for indoor electrical room and control room,


4/17/2023 waiting for ceiling works finished
Ceiling should be finished on 10 April 23
NO AREA DESCRIPTION (WORKFRONT) TOTAL Unit INSTALLED
QTY
2 WWTP

INSTRUMENT LIST 44 Ea 0

PANEL & JUNCTION BOX 51 Ea 9

CABLE TRAY 266 m 200

Cable Tray support

CONDUIT 788 m 152

VALVE 2 Set

Lightning Protection 8 Set

Power & Control Cable 142 Line

Pulling Cable 142 Line 41

Fire Alarm 20 set 20

Communication 11 set 0

Lighting 35 Ea 24
EXPECTED MATERIAL ISNTALLATION
REMAINING STATUS MATERIAL PROGRESS
ONSITE START

44 Material not yet supplied by vendor 0% 4/11/2023 4/13/2023


WWTP

42 18% 4/11/2023 4/13/2023

66 Material already onsite 75% on progress

Support not completed yet, additional 4/7/2023 5/9/2023


material expected onsite 7 April 2023

636 Material already onsite 19% Material already onsite on progress

Material not yet supplied by vendor


WWTP

Material already onsite Material already onsite 5/7/2023

on progress

101 29%

0 100%

11 0% on progress

11 69% on progress
ISNTALLATION
REMARK
FINISH

5/15/2023

5/12/2023

5/14/2023

5/14/2023 Cable Tray installation waiting for additional support and


pedestals

5/25/2023

5/15/2023

5/12/2023

5/25/2023

Done

4/17/2023 on progress

4/17/2023