Barangay: VILLAR
Municipality: BOTOLAN
Province: ZAMBALES
CONSTRUCTION OF ADDITIONAL HAND PUMP DEEP WELLS AND IMPROVEMENT OF EXISTING WATER SUPPLY SYSTEM FOR BARANGAY VILLAR
Sub-Project Title:
IP COMMUNITY
Category: COVID-19 RELATED EMERGENCY NEEDS
Physical Target: 4 HAND PUMP DEEP WELL & 1 WATER TANK
Total Sub-Project Cost: 999,050.66
Mode of Implementation: BY COMMUNITY FORCED ACCOUNT
SUB-PROJECT DESCRIPTION: Sub-Project Duration: 8 calendar days
1. Construction of Hand Pump Deep Well Water Supply System in GIDA Equipment Needed: Drilling Rig
2. Improvement of Existing Water Supply System
Technical Personnel: MTF/ME & TF
Item
Scope of Work ( Direct Cost ) % Wt. Quantity Unit Unit Price Amount
no.
1 CONSTRUCTION OF HAND PUMP DEEP WELL 83.23% 4.00 units 184,735.00 738,940.00
2 REHABILITATION OF EXISTING WATER SYSTEM 16.77% 1.00 lot 148,849.50 148,849.50
Total 100.00% 887,789.50
Total Sources of Fund
Other
Breakdown of Estimated Project Cost Construction KALAHI Community BLGU MLGU
Sources
Cost CIDSS Grant In-Kind Cash In-Kind Cash In kind Cash
A. DIRECT COST
1 Material Cost: 242,389.50 242,389.50
2 Equipment/Tools Rental 608,000.00 468,000.00 140,000.00
3 Labor Cost: 37,400.00 37,400.00
Sub-Total ( A ) 887,789.50 747,789.50 0.00 0.00 0.00 0.00 0.00 140,000.00 0.00
B. INDIRECT COST
1 Overhead Expenses 62,713.00 31,402.87 31,310.13
2 Contingencies 20,048.16 20,048.16
3 Other Necessary Indirect Cost
a) Bond Premium 7,500.00 7,500.00
b) Steel Filing Cabinet 16,000.00 16,000.00
c) Project Signage (Tarpauline) 5,000.00 5,000.00
Sub-Total ( B ) 111,261.16 51,451.03 0.00 0.00 0.00 59,810.13 0.00 0.00 0.00
TOTAL (A+B) 999,050.66 799,240.53 0.00 0.00 0.00 59,810.13 0.00 140,000.00 0.00
TOTAL PROJECT COST 999,050.66 799,240.53 0.00 0.00 0.00 59,810.13 0.00 140,000.00 0.00
PERCENTAGE 100% 80.00% 0.00% 0.00% 0.00% 5.99% 0.00% 14.01% 0%
Prepared by : Approved by :
Noted by:
Note: Costing to be used on the MIBF will be the Total Estimated Cost
REPUBLIC OF THE PHILIPPINES
Brgy CANANTONG
Municipality of LAUR
Province of NUEVA ECIJA
BILL OF QUANTITIES
RATE PER
ITEM No. of
ITEM DESCRIPTION QTY UNIT DAY/UNIT TOTAL
NO. Crew/ Labor
COST
1 GRADEN PLOT PREPARATION (clearing and weeding)
Estimated Quantity: 2795.00 sq.m
Labor (Batch 1)
Quantity : 1397.50 sq.m
Capability Output : 349.38 sq.m
Manpower Required :
59 Laborer
Gang output : 349.38 sq.m/day
Total Duration : 4 day
Labor (Batch 2)
Quantity : 1397.50 sq.m
Capability Output : 349.38 sq.m
Manpower Required :
59 Laborer
Gang output : 349.38 sq.m/day
Total Duration : 4 day
247,800.00
Unit Cost = 88.66 per sq.m
2,795.00
Labor (Batch 3)
Quantity : 698.75 sq.m
Capability Output : 174.6875 sq.m
Manpower Required :
59 Laborer
Gang output : 174.6875 sq.m
Total Duration : 4 days
Labor (Batch 4)
Quantity : 698.75 sq.m
Capability Output : 174.6875 sq.m
Manpower Required :
59 Laborer
Gang output : 174.6875 sq.m
Total Duration : 4 days
Labor (Batch 5)
Quantity : 698.75 sq.m
Capability Output : 174.6875 sq.m
Manpower Required :
59 Laborer
Gang output : 174.6875 sq.m
Total Duration : 4 days
Labor (Batch 6)
Quantity : 698.75 sq.m
Capability Output : 174.6875 sq.m
Manpower Required :
59 Laborer
Gang output : 174.6875 sq.m
Total Duration : 4 days
Sub-Total 396,480.00
TOTAL COST FOR ITEM # 2 421,920.00
421,920.00
Unit Cost = 150.96 per sq.m
2,795.00
Labor (Batch 7)
Quantity : 559.00 sq.m
Capability Output : 139.75 sq.m
Manpower Required :
59 Laborer
Gang output : 139.75 sq.m
Total Duration : 4 days
Labor (Batch 8)
Quantity : 559.00 sq.m
Capability Output : 139.75 sq.m
Manpower Required :
59 Laborer
Gang output : 139.75 sq.m
Total Duration : 4 days
Labor (Batch 9)
Quantity : 559.00 sq.m
Capability Output : 139.75 sq.m
Manpower Required :
59 Laborer
Gang output : 139.75 sq.m
Total Duration : 4 days
Sub-Total 492,240.00
Equipment /Tools Rental
Grass cutter 200sqm/day 23 days 2 2,000.00 92,000.00
Pick Mattock 3cu.m/day 23 days 30 50.00 34,500.00
Wheel Barrow 40cu.m/day 23 days 3 50.00 3,450.00
Sub-Total 129,950.00
622,190.00
Unit Cost = 222.61 per sq.m
2,795.00
Sub-Total 365,400.00
365,400.00
Unit Cost = 43.71 per ln.m
8,360.00
SUMMARY
A DIRECT COST
Material Cost 25,440.00
Equipment/Tools Rental 129,950.00
Labor Cost 1,501,920.00
Sub-Total A 1,657,310.00
B INDIRECT COST
1 Overhead Expenses
A. Administrative Supervision 79,695.00
1. Time Keeper 1.00 23.00 days 420.00 9,660.00
2. Project Implementation Team 3.00 207.00 hours 52.50 32,602.50
3. Monitoring & Inspection Team 3.00 207.00 hours 52.50 32,602.50
4. BDC-TWG Chairperson 1.00 92.00 hours 52.50 4,830.00
3 Miscellaneous Expenses
a) Hand Tools
Bolo Knife 50.00 23.00 days 2.00 2,300.00
broom stick, 50.00 23.00 days 2.00 2,300.00
Shovels 50.00 23.00 days 2.00 2,300.00
Plastic Drum/Container 6.00 23.00 days 2.00 276.00
7,176.00
a) PPE's
Facemask 3,284.00 pcs 1.00 3,284.00
Rubber Gloves 100.00 pairs 55.00 5,500.00
8,784.00
4 Other Necessary Indirect Cost
a) Bond Premium 1.00 lot 11,250.00
b) Steel Filing Cabinet, 3 drawers 1.00 unit 16,000.00
c) Project Signage (Tarpauline) 1.00 lot 6,000.00
Sub-Total B 192,583.43
Prepared by : Approved by :
Noted:
Note: Costing to be used on the MIBF will be the Total Estimated Cost
Proposed Project
CASH FOR WORK PROGRAM FOR COVID-19 RESPONSE
Duration 10 Calendar Days
OFFICE SUPPLIES
Item Description Quantity Unit of Measure Unit Cost Total Cost
Bond Paper(long) 3 rms ₱ 245.00 ₱ 735.00
Calculator 1 pcs ₱ 500.00 ₱ 500.00
Check booklet 1 pcs ₱ 600.00 ₱ 600.00
Pencil 10 pcs ₱ 6.00 ₱ 60.00
Ballpen(retractable) 10 pcs ₱ 8.00 ₱ 80.00
Ballpen(my gel) 5 pcs ₱ 23.00 ₱ 115.00
Columnar Pad(16 columns) 1 pcs ₱ 67.00 ₱ 67.00
Correction Tape 5 pcs ₱ 32.00 ₱ 160.00
Sticky Note 5 pcs ₱ 25.00 ₱ 125.00
Stapler #35 1 pcs ₱ 320.00 ₱ 320.00
Staple Wire #35 2 bxs ₱ 50.00 ₱ 100.00
Fastener 2 bxs ₱ 100.00 ₱ 200.00
Masking Tape 5 pcs ₱ 25.00 ₱ 125.00
Clear Tape 5 pcs ₱ 25.00 ₱ 125.00
Puncher(big) 1 pcs ₱ 380.00 ₱ 380.00
Manila Paper 20 pc ₱ 6.00 ₱ 120.00
Paper Clip(big) 2 bxs ₱ 55.00 ₱ 110.00
Permanent Marker 15 pcs ₱ 38.00 ₱ 570.00
White Folder(long) 25 pcs ₱ 9.00 ₱ 225.00
Brown Envelop(long) 25 pcs ₱ 6.00 ₱ 150.00
Expandable Envelop(long) 12 pcs ₱ 28.00 ₱ 336.00
Record Book 1 pcs ₱ 95.00 ₱ 95.00
Plastic Envelop with handle 3 pcs ₱ 70.00 ₱ 210.00
Push Pin 1 bxs ₱ 95.00 ₱ 95.00
Rubber Band 1 bxs ₱ 100.00 ₱ 100.00
Rubber Stamp ( Paid, Inspected & Received by, Certified True Copy) 3 pcs ₱ 200.00 ₱ 600.00
Stamp Pad 1 pcs ₱ 110.00 ₱ 110.00
Stamp Pad Ink 1 pcs ₱ 100.00 ₱ 100.00
Photocopy 1 lot ₱ 600.00 ₱ 600.00
LOAD ALLOWANCE 2 MOS. ₱ 300.00 ₱ 600.00
GRAND TOTAL TOTAL ₱ 7,713.00
TRAVEL EXPENSES
Total Amount of Total Amount
Itinerary Purpose No. of Pax Two Way Fare Meals Allowance No. of Travels Responsible Person
Travel of Meal Allow.
Barangay Treasurer/BDC-
Opening of Bank Account 2 ₱ 420.00 ₱ 140.00 1 ₱ 840.00 ₱ 280.00
TWG Chairperson
Establishment &
Replenishment of Petty 1 ₱ 420.00 ₱ 140.00 3 ₱ 1,260.00 ₱ 420.00 Barangay Treasurer
Land Bank of the Philippines (Iba Branch) Cash Fund
₱ 42,060.00 ₱ 9,940.00
Barangay: VILLAR
Municipality: BOTOLAN
Province: ZAMBALES
CONSTRUCTION OF ADDITIONAL HAND PUMP DEEP WELLS AND IMPROVEMENT OF EXISTING WATER SUPPLY SYSTEM FOR
BARANGAY VILLAR IP COMMUNITY
4 HAND PUMP DEEP WELL & 1 WATER TANK
8 calendar days
WORK SCHEDULE & GANTT CHART
CONSTRUCTION OF ADDITIONAL HAND PUMP DEEP WELLS AND IMPROVEMENT OF EXISTING WATER SUPPLY
Sub-Project Title : SYSTEM FOR BARANGAY VILLAR IP COMMUNITY
Category : COVID-19 RELATED EMERGENCY NEEDS
Physical Target : 4 HAND PUMP DEEP WELL & 1 WATER TANK
Total Sub-Project Cost : PhP 999,050.66
BILL OF QUANTITIES
RATE PER
ITEM No. of
ITEM DESCRIPTION QTY UNIT DAY/UNIT TOTAL
NO. Crew/ Labor
COST
1 CONSTRUCTION OF HAND PUMP DEEP WELL 4.00 sets
Materials
Sub-Total 106,140.00
Labor
Drilling of Deep Well
Hauling of Materials
Sub-Total 24,800.00
Sub-Total 608,000.00
Sub-Total 136,249.50
Labor
Clean up of Tank
Sub-Total 12,600.00
SUMMARY
A DIRECT COST
Material Cost 242,389.50
Equipment/Tools Rental 608,000.00
Labor Cost 37,400.00
Sub-Total A 887,789.50
B INDIRECT COST
1 Overhead Expenses (7-11% of EDC)
Sub-Total B 111,261.16
Prepared by : Approved by :
Noted:
Note: Costing to be used on the MIBF will be the Total Estimated Cost