Professional Documents
Culture Documents
Solution:: Step: 1 of 14: Job Costing, Normal and Actual Costing. Anderson Construction Assembles Residential
Solution:: Step: 1 of 14: Job Costing, Normal and Actual Costing. Anderson Construction Assembles Residential
Direct materials and direct labor are paid for on a contract basis. The costs of each are
known when direct materials are used or when direct labor-hours are worked. The 2014
actual assembly-support costs were $7,614,000, and the actual direct labor-hours were
162,000. 1. Compute the (a) budgeted indirect-cost rate and (b) actual indirect-cost rate.
Why do they differ? 2. What are the job costs of the Laguna Model and the Mission Model
using (a) normal costing and (b) actual costing? 3. Why might Anderson Construction
prefer normal costing over actual costing?
:: Solution ::
step: 1 of 14
Predetermined Overhead rate:
The applied manufacturing overheads are calculated by multiplying the actual hours with
the manufacturing overhead rate. If actual overheads are greater than applied overheads
then the overheads are said to be under allocated. If actual overheads are lower than
applied overheads, then the overheads are said to be overallocated.
step: 3 of 14
(1)
In the given scenario, the indirect cost is assembly support cost. The budgeted indirect cost
rate is calculated by dividing the budgeted assembly support costs with the budgeted direct
labor hours as shown below:
step: 4 of 14
step: 5 of 14
(b) Computation of actual indirect cost rate:
The actual indirect cost rate is calculated by dividing the actual assembly support cost with
the actual direct labor hours as shown below:
step: 6 of 14
step: 7 of 14
Budgeted Indirect cost rate and Actual Indirect cost rate differ because budgeted indirect
cost rate is calculated by taking budgeted assembly support cost and budgeted direct
labour hours in numerator and denominator while actual indirect cost rate is calculated by
taking actual assembly support cost and actual direct labour hours in numerator and
denominator.
step: 8 of 14
(2)
(a) Computation of job costs of the L Model and M Model using Normal Costing:
L Model:
It is given that:
The indirect cost for L Model under normal costing is calculated by multiplying the
budgeted indirect cost rate with the direct labor hours as shown below:
The total job cost is the sum of direct materials, direct labor and indirect cost as shown
below:
step: 9 of 14
step: 10 of 14
Mission Model:
It is given that:
The indirect cost for M Model under normal costing is calculated by multiplying the
budgeted indirect cost rate with the direct labor hours as shown below:
The total job cost is the sum of direct materials, direct labor and indirect cost as shown
below:
step: 11 of 14
step: 12 of 14
(b) Computation of job costs of the L Model and M Model using Actual Costing:
L Model:
It is given that:
The indirect cost for L Model under normal costing is calculated by multiplying the
budgeted indirect cost rate with the direct labor hours as shown below:
The total job cost is the sum of direct materials, direct labor and indirect cost as shown
below:
step: 13 of 14
M Model:
It is given that:
Direct Material Cost = $ 1 27,970
The indirect cost for M Model under normal costing is calculated by multiplying the
budgeted indirect cost rate with the direct labor hours as shown below:
The total job cost is the sum of direct materials, direct labor and indirect cost as shown
below:
step: 14 of 14
(3)
Explanation:
- construction prefers normal costing over actual costing as in the case of actual costing, the
costs are calculated at the end of the accounting period i.e., when the job is completed.
However, managers require to calculate the cost at various intervals and not just at the end
of completion of job.
- They need to know manufacturing cost at various intervals to price the jobs, evaluate the
success and failure of jobs, to bid for the new jobs and to prepare interim financials
required for various purposes