Mass Concrete Management

for Cold Box Pilecap


Foundation
Table of Contents
01 Introduction 06 Concrete Pouring Metod

02 Equipment List 07 Site Traffic Management

03 Plan Formwork 08 Cycle Time

04 Manpower List 09 ERP Flowchart

05 Anchor Instalation 10 Dewatering Plan


01
INTRODUCTION
Introduction : Cold Box Foundation

Approximately 26.4 m
Introduction : Cold Box Foundation
Introduction : Cold Box Foundation

Section C :Concrete Height ( 1,3


m’ )
Introduction : Cold Box Foundation

Section D :Concrete Height ( 2,5


m’ )
Introduction :Cold Box Foundation
Introduction : Information
Cold Box Pilecap Foundation
Cold Box Pilecap Foundation Pouring

Concrete Area : 314,6 m2 and 258,4 m2


Concrete Height : 2,5 m’ and 1,3 m’
Concrete Volume: + 1.180 m3
Pouring Date : March 4, 2023
Pouring Start : 06.00 pm
Truck Mixer : 40 TM
Concrete Pump : 2 CP
Excavator Type Long Arm : 1 Unit
02
EQUIPMENT LIST
Equipment and Material
Equipment List :
Remarks Qty Cold Box
1. Truck Mixer Prepared 40 TM Each
2. Truck Mixer Poured 169 TM Each
3. Long Arm Excavator 1 Unit Each
4. Concrete pump 2 units Each
5. Compressor for Cleaning 1 unit Total
6. Eye wash 3 units Total
7. Vibrator 3 phase 3 unit Total
8. Vibrator Engine 1 unit Total
9. Blue Sheet 18 sheet Total
10. Washing CP / TM Area 1 area Total
11. Formwork Panel 1 set Each
12. Blue Sheet Tent 1 set Total
13. Hammer Test 1 set Total
14. Catwalk 30 set Total
15. Curing Compound 1 set Each
16. tarp 1 set Each
17. Cylinder Ring (ABIM) 30 Pcs Each
Equipment and Material
Material List :

Remarks Qty Cold Box

1. Concrete f’c 35 MPa FA (PO) 1.180 CuM Each

2. Thermocouple 3 points Total

3. Formwork 201,8 m2 Each

4. Rubber Gloves 50 pairs Each

5. Styrofoam 210 pcs Total

6. Plastic Roll 6 roll Total

7. Spray Tank for Curing Compound 1 set Total


03
Plan Formwork
Plan Formwork
Plan Formwork
Plan Formwork
Plan Formwork
04
Manpower List
Manpower List
Manpower List for Cold Box

Shift
Man Power
18.00 - 03.00 03.00 - 12.00
SM/SI B. Kurniawan Zulkarnain
SPV Sunarto Ikrom
HSE Lingken Imam
QC Prayitno Guntur
GA
Nurse
Operator
Concrete Pump 8 person + 1 ABIM spv
Abim Truck Mixer 20 Person + 6 Technician
Genset 1 person
LongArm Exca 1 person
Scaffolder Team 4 person
Electrician 4 person
Manpower 20 person
05
Anchor
Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
Anchor Instalation
06
Concrete
Pouring Method
Pouring Steps ;

- The pouring method is based on the projected

colours.

- First section Volume is 380 m3 (estimated 8

hrs, Second Section is 340 m3 (estimated 7 hrs),

Third Section is 420 m3 (estimated 8,5 hrs)

First
Section
07
Site Traffic
Management
Traffic
Management
Estimated ;

- 10 TM in Waiting in

Entrance Line

- 4 TM Waiting in

Wash Area Line

- 7 Flagman Standby
08
Cycle Time
Supply Rate, Time & Trucks Analysis
Data Proyek : Java LG Project – TSF and Civil Construction Work
Kontraktor PT. Asuka Engineering Indonesia

- Volume : ± 1.180 m3

- Mutu : Fc 35 slump 10+/-2, FA 40%


- Jml Concrete Pump (CP) : 2 (Dua) unit pompa dan 1 (satu) spare
- Estimasi kebutuhan beton per CP : 25 m3 per jam/CP
- Total kebutuhan beton per jam : 50 m3
Analisis Waktu
Plant Supply
Citraland Romokalisari Kenpark ( menit )
(menit) (menit) (Spare Plant)
- Mixing 5 5 5
- Tuang 10 10 10
- Cuci Talang 5 5 5
- Perjalanan PP 60 75 90
Total Waktu 80 95 110

10 load/jam 10 load/jam 10 load/jam


- Supply Rate 70 m3/jam 70 m3/jam 70 m3/jam
- Jml Truck Mixer 10 unit 30 unit 5 unit (Stand by)
Resume
- Rata-rata supply : ± 50 m3/jam
- Total waktu yg diperlukan : ± 22 jam
Person incharge

Personel Citraland Romo Kenpark


Project Coordinator Marco (082234698747)
Coordinator Plant/Site Aditya Rahman Edi T Yudo
( 081235784473) ( 081231274125) (081235289085)

Plant Dispatcher Amir Erwin Rudi


(085732272591) ( 08123067534 ) ( 085738755207 )

Technical Responsibility Yunus ( 085108224440)


Koordinator C Pump Haris ( 081335358668 )
Mekanik Nanto Ika
( 081232781974 ) ( 0895704367203)

Traffic/Transport
Coordinator Haris ( 08335358668 )

Safety Koordinator
Indra ( 085348993987)
09
ERP
Flowchart
ERP Flow Chart : 0 – 4 minutes
ERP Flow Chart : 1 – 4 hours
10
Dewateing
Plan
Dewatering Plan
Calculated ;

1st Pond Dimension is 3,5 x 3,5 x 1 CuM

2nd Pond Dimension is 3,5 x 3,5 x 1 CuM


3rd 2nd
3rd Pond Dimension is 3,5 x 3,5 x 1 CuM

1st Pond is a Sediment Pond


1st 2nd Pond is a Filter Pond

3rd Pond is a pH Check Pond


Dewatering Plan

Washed TM Sediment Pond Filter Pond pH Check Pond


(with Palm Fiber (pH must between 6 – 9)
Flow Flow + Charcoal) Flow
pH Apv. RELEASE OUTSIDE
SITE
pH not Apv.

12,25 m3 capacity 12,25 m3 capacity 12,25 m3 capacity

Using Chemical Sheet

Pond Volume Calculation;


1 truck mixer (TM) = 50 Liter Water for Wash
Total TM = 169 TM Poured
50 L x 169 TM = 8.450 L = 7,05 m3
Safety Factors = 1,2 x 8,46 = 8,46 m3
Capacity 12,25 m3 > 8,46 m3 (OK)
Thanks