Professional Documents
Culture Documents
IV. Loading Process 1 Check The Jumper Code: U V U V U V
IV. Loading Process 1 Check The Jumper Code: U V U V U V
IV. Loading Process 1 Check The Jumper Code: U V U V U V
secondary side.
Make sure checked:
Purpose: the excitation generator machine units are based on the in-phase voltage
transformer parameter set and its corresponding input, so in commissioning operators
should double check the secondary side voltage matching with the primary side
voltage.
Record data according to the following table:
Ex-factory power I
Ex-factory power II
The diling switch keys 3 and 4 on the intelligent board should be diled according to
the address (power controller 1# is 00, 2# is 01, 3# is 10, 4# is 11).
The CAN BUS terminal electric resistor at both ends on (generally short circuit the
I/O board and the LK1 on the de-excitater intelligent board, but please check if the
terminal resistor is on at the regulator controller terminal. With the resistors at both
ends on, the resistor of CANBUS is 60Ω when there’s no power. )
Make sure the above operation finished:
V. Calibration testing
7-10
Users’ guide____Testing regulation
7-11
Users’ guide____Testing regulation
PT=100.00%, Φ=90°
CT current Set A active Set A reactive Set B active Set B reactve
(A) power (%) power (%) power (%) power (%)
PT=100.00%, Φ=-90°
7-12
Users’ guide____Testing regulation
value=0.816*Iln/1.1
7-13
Users’ guide____Testing regulation
7-15
Users’ guide____Testing regulation
If the residual voltage initiation is on, the results: 10 seconds after initiation witout
successfully establishing the voltage, the auxiliary power supply would be
automatically put into use. 5 seconds later, the initiation stops automatically and sends
out signals “ initiation failure”.
Results:
Flashing polarity Results :
2. Fan operation
Manually switch on and off the fans. Normal operation:
Attention: intelligent power controller system operats the fan switch on the display
screen, while the conventional power controller system has a manual switch inside it.
Automatically switch on and off the fans. Normal operation:
Attention: if the startup command R651 is effective, the fans would be turned
automatically.
Automatic switch of fan Normal operation:
In the AC current line 1, fan’s direction check Results:
In the AC current line 1, fan’s direction check Results:
Power plant switch Results:
Fan operational status signal indicator Normal display:
Attention: when the power conroller applies the A /B two fans, the direction and
status indicator of both fans should be checked.
3. De-excitater operation
Handy manual switch on and off the brake Normal operation:
Remote operational switch on and off the brake Normal operation:
Accident and invertion failure brake Normal operation:
Line I breke circuit Normal operation:
Line II brake circuit Normal operation:
Attention: both of the circuits in the ABB de-excitater switch should be checked.
De-excitator switch status signal indicator Normal display:
7-17
Users’ guide____Testing regulation
7-18
Users’ guide____Testing regulation
controller
23 Error or exit of 1# power
controller
24 Error or exit of 2# power
controller
25 Set A power fault
26 Set B power fault
27 24V power fault
28 Communication fault
29 Initiation failure
30 Over-excitation protection
31 Over-excitation exit
Attention: according to the semand of users, the signals at contact point without
power may not be totally identiacal to the above signals. The acutual value should be
checked according to the special diagram.
1. Preset value
Channel A preset Channel Bpreset Channel C preset
Attention: when the “0 voltage initiation “ is operable, the preset value of Channel A
and B IS 10%, while it is not operable, the preset value is 97%. When the preset is at
normal state in channel C, the preset value is the low limit of its current regulation.
7-20
Users’ guide____Testing regulation
Short connected the JP1 on analogue quantity board by jumper code, switch to
channel C, and observe the waveforms from the rectifier. The operation of exctation
increase or decrease should be able to symmetrize the waves and should be
continually adjustable.
Results:
After the test, get the PJ1 out. Make sure this done:
normal state.
7-22
Users’ guide____Testing regulation
diode rectifier voltage or QF01, operators can judge the correctness of this circuit wire.
The in-phase voltage transformer 3-phase voltage is basically the same. The input DC
voltage for the QF01 operational switch should be 1.4 fold larger than the in-phase
change secondary volt 220v voltage. (If there are 2 steps changing at the same time,
fill in the following table.)
Sandard value Actual value
In-phase changing primary volt
In-phase changing secondary volt
Rectifer volt
7-23
Users’ guide____Testing regulation
7-24
Users’ guide____Testing regulation
Channel B PT voltage:
Channel C PT voltage:
Attention: the preset value of channel C is the loe limit of the excitation current in
channel C, generally speaking, after voltage increase, the terminal voltage is
10%~20% of the rated value.
3. Regulating ranges
Channel Regulating range Standard value Results
A Terminal voltage high limit: High limit: 110% rated voltage
Low limit: Low limit: 70% rated value
B Terminal voltage high limit: High limit: 110% rated voltage
Low limit: Low limit: 70% rated value
C Excitation voltage or current High limit: 110% rated excitaion
High limit: voltage
Low limit: Low limit: 10%~20% 0-loaded
excitation voltage
After channel C tracks channel B, channel A is at work, after the channel C tracking
is finished (LDD, LID flashes alternately), modify parameter ID [6](ie.
Kc=Kc*UKA/UKC), so as to prevent interruption in the generator termianl when
channel C is switched to Channel A. otherwise remodify the ID [6] in channel A
Set A Kc:
8. Frequency test
Frequency
PT voltage
7-27
Users’ guide____Testing regulation
The regulator works at channel A , similate the following faults respectively, the
regulator should be able to switch to the standby channels without vibration on the
generator voltage.
A: 1PT phase loss results:
Meathod: cut any of the 1PT 3-phase input voltage
B: Power error: microcomputer channel 5v power results:
Meathod: turn off the power switch QF03 of regulator in channel A.
C: regulator error results:
Method: restore the CPU of regulator in channel A.
When the regulator is working at B channel, similate the above error, the regulator
should be able to switch to channel C, without vibration in the generator voltage.
Results:
7-28
Users’ guide____Testing regulation
Order Phase Termina Step up Vibration Regulator Step down Vibratio Regulat
No. step l voltage regulati times for y time for regulation n times ory time
quantit before on step up step up quantity for step for step
y step quantity down down
Attention: this test is done through the commissioning software. If the results
are not satisfactory, operators can modify the TA3,TA4 parameter of the AVR.
Because of the great rotor time constant difference between the testing machine units
and the actual machine units, this test is just for reference, which means that the actual
phase step test should be done on site.
7-29
Users’ guide____Testing regulation
7-30
Users’ guide____Testing regulation
as positive, the increase of grade results in the decrease of reactive power of the
machine unit.
7-31
Users’ guide____Testing regulation
Channel A results:
Channel B results:
(communication control)
5 Constant PF regulation
(communication control)
7-33
Users’ guide____Testing regulation
7-34
Users’ guide____Testing regulation
Attention: for the convetional system there’s no need to calibrate the power
controller and the de-excitater parameter except the output value of exciation current
transducer.
7-35
Users’ guide____Testing regulation
7-36
Users’ guide____Testing regulation
temperature (℃)
3#components
temperature (℃)
5#components
temperature (℃)
4#components
temperature (℃)
6#components
temperature (℃)
2#components
temperature (℃)
7-37
Users’ guide____Testing regulation
At the same period, a single silicon component would not exceed 5℃, or there amy be
something wrong with the silicon component or the units. In this circunstance,
operators should lay emphasis on this test and prolong the testing time.
1. Insulation test
Main excitation circuit to the ground MΩ
Results:
DC operation circuit to the groud MΩ
Results:
AC power circuit to the groud MΩ
Results:
7-38
Users’ guide____Testing regulation
7-39
Users’ guide____Testing regulation
z Make sure that all the cubicles are properly installed according to the diagram
“the arrangement diagram of excitation cubicles” in the excitation system. Pay
attention to the correctness of the arranging direction and order of the cubicles.
z Check the laid cables and wires according to the diagram, including checking the
voltage mutual-inducer, current mutual-inducer and protection circuit and prevent
no short circuit in voltage mutual-inducer and no open circuit in current
mutual-inducer.
z Double check the parent wires cross the cubicles, cables and BUS in the
excitation system to make sure its correctness.
z Especially check the wiring of de-excitater switch and the over-excitation
protection circuit
z Double check correctness of voltage and polarity input into the AC/DC power
from outside.
z Check the correctness of in-phase voltage transfomer and its primary grade
circuit. Then switch on the switch, making the power supply available. Check if the
following power is at normal state at the power output terminal.
Items DC 24v DC power Regulator power supply
power DC electricity Channel A Channel B
operation supply
2. Flashing
Handy manual results:
Automatic initiation results:
Attention: to prevent electricity moving to the rotor circuit, the swich of excitation
should be turned off. Operators can check the normality of the initiation circuit
through the action of excitation contactor. Keep the initiation once it is on, unless the
initiation time is up or the operator manually stops the initiation.
If the residual voltage initiation is not on, the results: 10 seconds after initiation
witout successfully establishing the voltage, the initiation would automatically stop
and sends out signals “initiation failure”.
If the residual voltage initiation is on, the results: 10 seconds after initiation witout
successfully establishing the voltage, the auxiliary power supply would be
automatically put into use. 5 seconds later, the initiation stops automatically and sends
out signals “ initiation failure”.
Results:
Flashing polarity Results:
Attention: in checking theinitiation polarity, there should be an excitation power
supply, which should be switched on. To prevent electricity moving to the rotor circuit,
the swich of excitation should be turned off. Then switch on the main contactor of
Q61 to measure the voltage between the positive and negative wire on the
dde-excitater switch and its polarity.
3. Fan operation
7-41
Users’ guide____Testing regulation
7-42
Users’ guide____Testing regulation
7-43
Users’ guide____Testing regulation
11 DC power section II
off
12 AC power off
13 De-excitater switch
on
14 De-exctater switch
off
15 De-excitater switch
off mistakenly
16 1#power contrller
error or exit
17 2#power contrller
error or exit
18 Set A power error
19 Set B power error
20 24v power error
21 Communication error
22 Initiation failure
23 Over-excitaton --- ---
protection exit
Attention: (1) according to the semand of users, the signals at contact point without
power may not be totally identiacal to the above signals. The acutual value should be
checked according to the special diagram. (2) Other signals, such as “PT “ error, the
“regulator error” can be tested in the open loop testing.
7-44
Users’ guide____Testing regulation
7-45
Users’ guide____Testing regulation
take place of the rotors. Connect them to the output side of the rectifier as the
commissioning load. The capacity should be about 30Ω, with a capacity of more
than 1KW.
(4 )The point of the ondoscope should be connected to the rectifier bridge for the sake
of observing the output excitation voltage waveforms.
Attention: when the “0 voltage initiation “ is operable, the preset value of Channel
A and B IS 10%, while it is not operable, the preset value is 97%. When the preset is
at normal state in channel C, the preset value is the low limit of its current regulation.
7-46
Users’ guide____Testing regulation
7-47
Users’ guide____Testing regulation
7-48
Users’ guide____Testing regulation
7-49
Users’ guide____Testing regulation
changeable rectifier power can no longer meet the requirement of the test, which
means that the excitaion system is needed for the short circuit test. Since the
generator terminal has already been short circuit, the excitation power needs other
source of power supply. There are 2 modes:
(1) After the electricity is reversed, the excitation voltage transformer supplies
the power
(2) Connect the power through the electricity from the factories: get electricity
from 6kV or 10Kv wire to the excitation voltage transformer, or use the
factory testing voltage tranformer in place of the excitation voltage
transformer.
exctation”, “system voltage tracking “ and “channel tracking”, and switch off the
excitation switch. At the same time, the operation of initiation botton and
switchingchannel is forbidden, which is to prevent abnormality.
Before the test, operators should first of all, check the correctness of the order
phase of the power. Make sure it is of positive phase.
Generall speaking, in the above 2 modes, to carry out the short circuit test, there are
the following wiring ways:
7-50
Users’ guide____Testing regulation
2) De-excitator braker devided, operators should remove the “devide pulse cut” signal
in the regulator
3) Connect an electric furnace or a resistoric load at the input terminal of the
excitation switch. Connect the touching point of the ondoscope. operators get ready to
observe the voltage waveforms from the rectifier.
Attention: first connect the resistor for test, which is to test if the control of
regulator and rectifier is at normal state.
4) The machine units are in the state of shutdown, the regulator powered off, switch
on the interconnection switch at the side of generator outlet, which would provide
electricity for the excitation voltage transformer and PT, check the phase order of the
rectifier bridge input power to ensure the positive phase.
5) Switch off the interconnection switch, resend electricity to the regulator, and set the
regulators in A/B channel into the mode of “constant excitation regulation”. Short
connect the JP1 of the regulator in channel C on the analogue quantity board, set the C
channel in the mode of “constant control angle regulation”
6) Regulators switched to channel C
Attention: this is the first time the excitaton system is tested with the generator unit,
so it is impossible to judge if the current feedback is normal. Channel C doesn’t need
the current feedback signals in the “constant angle control regulation” mode, which
is safer and more reliable. .
7) Switch on the interconnection switch at the exit of the generator, providing
electricity for the excotation voltage transformer and PT. Regulator set C will begin to
work normally, and send out pulse signals.At this moment, the set signal of channel C
is at its loe limit, the output of excitation voltage is 0.
8) Operate the excitaion increase botton on the regulator to add the set value of
channel C, the control signals in channel C would s decrease accordingly, while the
output voltage of the rectifier would increase. At this moment observe the voltage
waveform to see if it is steady and if there’s mutation.
9) Operate the excitaion decrease botton on the regulator to reduce the set value of
7-51
Users’ guide____Testing regulation
channel C, the control signals in channel C would increase accordingly, while the
output voltage of the rectifier would decrease. At this moment observe the voltage
waveform to see if it is teady and if there’s mutation.
10) When the output voltage reaches it maximum value, wind the botton
“rectifier/reversion” to the position of “reversion”. The output voltage should drop to
0, and make sure if it is normal.
11) After the above tests, operators can judge the performace of the regulator and
rectifier. Switch off the interconnection switch, and turn on the de-excitater, so that
the “devided braker pulse cut” returns to normal state.
7-52
Users’ guide____Testing regulation
4) After the test, set channel A/B in the “automatic mode” once again. Detah the JP1
in channel C, and get ready to carry out the other-excitation idle-loaded pressure
build-up test.
Attention: don’t switch the channels in this test, when adopting the “constant
control angle mode”, operaters had better to set all the 3 channels into this mode.
7-53
Users’ guide____Testing regulation
De-excitator braker devided, operators should remove the “devide pulse cut” signal in
the regulator
2) Connect an electric furnace or a resistoric load at the input terminal of the
excitation switch. Connect the touching point of the ondoscope.
3) Operators get ready to observe the voltage waveforms from the rectifier.
Attention: first connect the resistor for test, which is to test if the control of
regulator and rectifier is at normal state.
4) The machine units are in the state of shutdown, the regulator powered off, switch
on the interconnection switch at the side of generator outlet, which would provide
electricity for the excitation voltage transformer and PT, check the phase order of the
rectifier bridge input power to ensure the positive phase.
5) Switch off the interconnection switch, resend electricity to the regulator, and set the
regulators in A/B channel into the mode of “constant excitation regulation”. Short
connect the JP1 of the regulator in channel C on the analogue quantity board, set the C
channel in the mode of “constant control angle regulation”
6) Regulators switched to channel C
7) Switch on the interconnection switch at the exit of the generator, providing
electricity for the excotation voltage transformer
8) With the R631 signal, regulator set C will begin to work normally, and send out
pulse signals. At this moment, the set signal of channel C is at its loe limit, the output
of excitation voltage is 0.
9) Operate the excitaion increase botton on the regulator to add the set value of
channel C, the control signals in channel C would decrease accordingly, while the
output voltage of the rectifier would increase. At this moment observe the voltage
waveform to see if it is steady and if there’s mutation.
10) Operate the excitaion decrease botton on the regulator to reduce the set value of
channel C, the control signals in channel C would increase accordingly, while the
output voltage of the rectifier would decrease. At this moment observe the voltage
waveform to see if it is steady and if there’s mutation.
11) When the output voltage reaches it maximum value, wind the botton
7-54
Users’ guide____Testing regulation
control angle mode”, operaters had better to set all the 3 channels into this mode.
7-56
Users’ guide____Testing regulation
4) Switch off the interconnection switch, resend electricity to the regulator, and set the
regulators in A/B channel into the mode of “constant excitation regulation”. Short
connect the JP1 of the regulator in channel C on the analogue quantity board, set the C
channel in the mode of “constant control angle regulation”
5) Regulators switched to channel C
6) Switch on the excitation power
7) With the R631 signal, regulator set C will begin to work normally, and send out
pulse signals. At this moment, the set signal of channel C is at its low limit, the output
of excitation voltage is 0.
8) Operate the excitaion increase botton on the regulator to add the set value of
channel C, the control signals in channel C would decrease accordingly, while the
output voltage of the rectifier would increase. At this moment observe the voltage
waveform to see if it is steady and if there’s mutation.
9) Operate the excitaion decrease botton on the regulator to reduce the set value of
channel C, the control signals in channel C would increase accordingly, while the
output voltage of the rectifier would decrease. At this moment observe the voltage
waveform to see if it is steady and if there’s mutation.
10) When the output voltage reaches it maximum value, wind the botton
“rectifier/reversion” to the position of “reversion”. The output voltage should drop to
0, and make sure if it is normal.
11) After the above tests, operators can judge the performace of the regulator and
rectifier. Switch off the interconnection switch, and turn on the de-excitater, so that
the “devided braker pulse cut” returns to normal state.
The steps for short circuit test:
1) Set the machine unit at a certain spinning speed, make sure that the command of
interconnection signal is removed, and the functions of “residual initiation”,
“ssystematic voltage tracking” and “channel tracking” are off, switch off the initiation
power switch, and make sure that the JP1 jumper in the regulator of analogue quantity
BUS channel C.
2) Power the regulator and swith it to channel C.
7-57
Users’ guide____Testing regulation
Attention: operators can also adopt the “constant control angle” mode in channel
A/B, but this should be set through the commissioning software. After that, the
indicator lights for this mode would be on. Input the maximum signal through the
commissioning software.
Attention: restart the regulator in channel A/B, thus exiting the “constant control
angle” mode. In the process of the test remember to make sure the regulator in
channel A/B is in the “constant control angle” mode.
3) Turn on the interconnection switch to supply electricity reversally
4) With the R631 signal, the regulator begins to work properly, and sends out pulse
signal. Operate the excitation increase botton, the voltage in the rectifier will inrease
accordingly, the rotor current would increase, as well as the stator short circuit in the
generator current. Observe the normality of rotor current in the regulator, and then
cooperate with the testing department of the generators to finish the short circuit dry
test or the short circuit characteristic test.
5) After the test, set channel A/B in the “automatic mode” once again. Detah the JP1
in channel C, and get ready to carry out the other-excitation idle-loaded pressure
build-up test.
Attention: don’t switch the channels in this test, when adopting the “constant
control angle mode”, operaters had better to set all the 3 channels into this mode.
Stop serious alarm:operators should close the functions of “residual voltage
exctation” , “system voltage tracking “ and “channel tracking”, and switch off the
excitation switch. At the same time, the operation of initiation botton and
switchingchannel is forbidden, which is to prevent abnormality.
Attention: restart the regulator in channel A/B, thus exiting the “constant control
angle” mode. In the process of the test remember to make sure the regulator in
channel A/B is in the “constant control angle” mode.
generator
In the above mode of short circuit test, it is only necessary to remove the
7-58