Subject: Request for Quotation for Supply, Installation and Commissioning of a Deep Tube-well & pump motor set

with all
materials. (MS & SS) 80 M3/Hr.

Technical specification for Installation and Commissioning of a Deep Tube-well.

Sl.No Description of work. Quantity Unit Unit Price. Total Amount.


Preparation, packing and transportation of one complete Tube-
Well equipment including all accessories to the work site and
making all preliminary arrangement required for sinking the
1 Tube-Well and re-transportation after completion pf the work 1 L.S
with all accessories complete as per standard practice and
direction of the competent authority.

Main bore whole 28'' / 22”/18 '' boring by Rotary Rig/


water jet with reverse circulating Method. -

From 000 ft. to 100 rft 100 ft


2 From 101 ft. to 200 rft 100 ft
From 201 ft. to 400 rft 200 ft
From 401 ft. to 500 rft 100 ft
From 501 ft. to 600 rft 100 ft
Supply of fitting & fixing of 6 ” dia 10’ long 4.60 - 5.2 mm
3 MS/PVC sand trap at the bottom of bail plug as per standard 10 ft
practice and direction of the competent authority.

Supply of best quality 6 ” dia Brand New Stainless steel/PVC


4 strainer continuous slot. 100 ft

5 Supply of dia MS blind 4.60 - 5.2 mm mm thickness 190 ft


pipe with socket completed as per standard practice.

Supply of best quality 14” dia 6 mm thickness ERW MS


6 housing pipe as per standard practice, Origin – KORIA 240 ft
/China

Supply of MS/PVC reducing socket between 14 ” dia housing


8 pipe and 6 ” dia blind pipe. 3 Ft

Supply of centralizer made out of 0.5” MS rod dropping round


9 the strainer to be placed at every 20’ interval. 10 No

Complete installation of tube well fixture (housing pipe,


strainer, sand trap, Connected of MS rod, reducing socket,
10 powering of pea- gravel’s) etc. as per design. 543 ft

Surrounding the annular space between the tube well and bore
11 hole supplying of graded pea- gravel’s and coarse 500 Cft
sand complete as per standard practice.
Developing/Charging the tube well by pumping method or
12 Compressor charging specified. 1 L.S

Total Amount In Taka