PROFILE CORE SKILLS & COMPETENCIES


I am a Washington Accorded cost
and commercial professional with  Preparation of Tender documents & Cost Plans
over 07 years of experience  Pre-qualification Assessment & Tender Evaluation
(Including Gulf experience) gained  Measuring Works & Preparation of BOQ (POMI, CESMM)
in pre and post contract stages with  Subcontractor Management
Local, International contractors  Change Management (New Rate Building and Price Variations)
and consultants. Held commercial  Evaluation of Payment application (Interim & Final Accounts)
positions responsible for  Preparation of Monthly progress report
overseeing and managing the  Preparation of Action plan for the Project
commercial aspects of different
types of construction projects in
UAE and Srilanka. ACADEMIC CREDENTIALS
 Bachelor of Technology in Civil Engineer at Open
University of Srilanka (Reading)
PERSONAL INFO  Bachelor of Science at Eastern University Srilanka.
 National Diploma in Quantity Surveying Technology at
 Date of Birth: 1991.11.16 Hardy College of Technology, Srilanka.
 Gender: Male  Diploma in MS-Office at British Informatics of Computer
 Civil Status: Married Technology.
 Nationality: Srilankan  Intensive Course on Project Management Primavera P6 at
 Passport No: N7377218 Centre for Housing Planning & Building (CHPB).
 Training Course on Computer Aided Draughting
(AutoCAD) 2D & 3D at Centre for Housing Planning &
Building (CHPB).
 Diploma in Computer Hardware Engineering at British
Informatics of Computer Technology.
 Certificates course in Disaster Management at Eastern
University, Srilanka.
 Certificates course in Psychology and Personality
Development at Eastern University, Srilanka
 Achieved Basic & Intermediate Levels on University
Students’ Competency Test of Information Technology- by
Ministry of Higher Education, Srilanka.

Page No 01
COMPUTER LITERACY PROFESSIONAL EXPERIENCE
 Auto CAD Estimator Nov 2022 – Up to Date
 ArcMap
On Roading Contracting L.L.C.
 Primavera 6.0
 MS Project
v
Clients: Emaar, Dubai Holdings, IMDAAD, IDAMA, Nakheel,
 ArcGIS Al – Futtaim Group, EMRILL
 MS Office
 Work with Construction Manager to Managing the Tender
MEMBERSHIPS department including all the coordination and preparation of all
the Bid Documents.
 RICS – APC Candidate  Check and review of Contract Agreements.
 Quantity Take-off & Preparation of specifications.
 Respond to tender queries by sending addendums to tenderers.
 Preparation of Tender Analysis of Bids and Tender Evaluation
Report.
 Preparation of Project progress report.

Quantity Surveyor Sep 2019 – Sep 2022


Coast Conservation and Coastal Resource Management Department
Contractors: Boskalis International BV, Netherlands and CHECH CHINA Harbour

SN Completed Project (Selected) Cost


(Mn.LKR)
01 Building for Fisheries Department – G+14+R 1800
02 Office Building – G+5+R 1050
03 Information Centre 1225
04 Apartments – G+8+R 1660
05 Beach Road – 5 km 345
06 Breakwater + Groynes + Revetments 1725
07 Beach Parks 900
08 Beach Nourishment 1900

 Work with Senior QS to Managing the Tender department including all the coordination and preparation of all the Bid Documents
 Check and review of Contract Agreements
 Quantity Take-off & Preparation of specifications.
 Respond to tender queries by sending addendums to tenderers.
 Preparation of Tender Analysis of Bids and Tender Evaluation Report.
 Undertaking Feasibility Studies Performing Risk, Value Management and Cost Control.
 Check and Recommending the final bills and did the levelling work to check the quantity
 Reviews the various activities of construction projects about variations and submission for approvals.
 Designing of Building, Beach parks & Coastal Structures, carry out the procurement work, estimation and construction.
 Check, review and recommend on new rates

Quantity Surveyor Sep 2018 – Sep 2019


Nawaloka Construction Company (Pvt) Limited, Srilanka
v
Project: Rehabilitation and improvement of 64km of Rural roads in Kegalle – KE03 ( iroad Project)
150 million USD

Page No 02
 Maintain Logs of Insurances, Notifications, Valuation, & Claims
 Assist and check with AQS to maintain logs of Recommended Request for Inspection (RFI) form, Daily progress report of the
sites, Site machineries, concrete records and Record of material at site & Material request.
 Work with consultant farm to take the Joint measurement & approvals.
 Prepare variation proposal, calling RFQs & prepare price analysis.
 Preparation of variation & Pricing variation claims.
 Review and advice on Extension of Time (EOT).
 Process Sub Contractors payment bills and Interim payment application.
 Prepare cost impact assessment.
 Scheduling and execution of subcontract agreements.
 Monitoring and controlling the progress as per work programme.
 Prepare the Daily, weekly and monthly progressive reports and assist the Engineers about the ground situation.
 Preparing Measurement sheet, Summary bill sheet and Breakup of the Payment.
 Certificate Variation orders and adjustments for change in the cost & Project progress Monitoring.
 Coordinate with Draftsman to Preparation of work resource allocation and designing of Roadway using with Computer Aid
Design (Auto CAD)
 Measurement and Quality checking of Asphalt Concrete.
 Preparation of work schedule and implementation of strategies.
 Involved in Quality Assurance and Quality Control (QA & QC) work relevant entire concrete and testing work.
 Preparing measurement sheet & bar schedule for Drainage, culverts and bridges.
 Other documentation work in Office

Assistant Quantity Surveyor cum Draftsman Assistant Sep 2016 – Sep 2018

Irrigation Department of Srilanka

Project: Kalugaloya Reservoir Project at Ampara


300 million USD

 Work as a Site Investigation Assistant to design the Distribution Canal and Field canal.
 Plot the Longitudinal section (LS) & Cross Section (CS) of Distribution canal & Field canal by using Auto CAD.
 Supervised construction of structures.
 Prepare weekly, Monthly progress report & material card.
 Prepared cutting filling sheet (Earth working sheet) of canal earth work.
 Prepared Quantity sheet (TDS Sheet), Bars schedule, Bill of Quantity (BOQ) & Estimates of Canal Structures for Tender
submission.
 Work as a Technical Evaluations Committee (TEC) Assistant and Prepared the TEC report.
 Prepared Progress Report of the project
 Work as an Assistant for prepared the Action Plan for the Project.
 Check the contactor Interim Payment and recommend to Engineer.
 Analyze and evaluate the cost impact of different design options and construction methodology.
 Monitoring and controlling the progress as per work programme.
 Prepare the Daily, weekly and monthly progressive reports and assist the Engineers about the ground situation at Progress meeting.