AMFAN CLAN AGRO-INDUSTRIAL DEVELOPMENT ASSOCIATION, INC

Lugan 3, Poblacion, Tboli, South Cotabato

August 26, 2022

RUSTICO NOLI D. CRUZ


Vice-President
Development Bank of the Philippines

Dear Sir Cruz,

Greetings!

The AMFAN CLAN AGRO-INDUSTRIAL DEVELOPMENT ASSOCIATION, INC. has applied for grant under the
DBP Native Seed Tree Bank Project through Massive Production of Giant Bamboo Materials. This projects
aims to develop/establish two (2) giant bamboo nurseries with a total estimated cost of Php 2.5 Million
(or 1.250 Million pesos for each nurseries) will be developed/established at Brgy. Tudok and Barangay
Dlanag, T’boli, South Cotabato.

Likewise, Development Bank of the Philippines has approved its application for the establishment of
two (2) giant bamboo nursery projects on March 1, 2022 by the DBP Management Committee under
the DBP Native Tree Seed Bank Projects.

Moreover, we glad to inform you that the following activities are already fully implemented, to wit:
a. Lay-out, clearing and fencing;
b. Installation of power source, watering facility and irrigation;
c. Establishment of Bamboo Nursery (Working shed/storage and germination beds); and
d. Purchase of Wood lumber for the working shed/storage and germination beds
In this connection, we would like to request your good office for the release of funds amounting to ONE
MILLION FOUR HUNDRED NINETY FOUR THOUSAND SIX HUNDRED SEVENTY FIVE (Php 1,494,
675.00) pesos for the implementation of the 2 ND Part of the establishment of two nurseries at Brgy.
Tudok and Brgy Datal Dlanag, Tboli, South Cotabato.

Attached here with is the 2ND Part of Work and Financial Plan of ACAIDA, Inc.

Hoping for your favorable response.

Sincerely yours,

ARTEMIO S. AMFAN, JR.


ACAIDA Acting President

cc.: Director Rogelio V. Garcia


cc.: Gerald Bueno
Accomplished Activity
1ST Part
Project Title Establishment of two (2) Bamboo Nurseries
Project Proponent Amfan Clan Agro-Industrial Development Association Incorporated (ACAIDA
Inc.)
Project Duration 2 years (24 months)
Phases/Stages of Budget items Quantity Amount Total Remarks
Activities (Php) Amount
(Php)
1. Pre-
Implementation
:
 Site visit and
assessment
 Lay-out, 20,000.00 20,000.00 Implemented
clearing and
fencing
2. Installation of  Water pump (Daichi 1 unit 18,500.00 18,500.00
power source, Submersible Pump)
watering facility  3 cu. m plastic tank 1 unit 25,000.00 25,000.00
and irrigation elevated
 Sumo SDE 6000X Diesel 1 unit 44,300.00 44,300.00
Generator Implemented
 Gasoline 600 liters 78.00 46,800
 Crude and Fuel 500 liters 80.00 40,000
 Plastic Pipes #3/4 2 pcs 950.00 1,900.00
 Plastic pipes #1 5 pcs 1,475.00 7,375.00

 Labor Cost 4 550.00 for 28 61,600.00 Implemented


manpower days
 Delivery and Hauling of 12,000.00 12,000.00
Materials (From
General Santos City to
Tboli, South Cot.) *Site
A
Implemented
 Delivery and Hauling of 12,000.00 12,000.00
Materials (From Tboli to
Nursery 1, Brgy Tbolok,
Tboli, South Cotabto)
*Site B
Sub Total
3. Establishment  Cement 50 bags 235.00 11,750.00
of Bamboo  Hallow Blocks 1,200 pcs 12.00 14,400.00
Nursery  GI Sheets 30 pcs 372.00 11,160.00
(Working  CMNS #3,4,5 10 kgs 70.00 700.00
shed/storage  Deformed bar 10 mm 30 pcs 190.00 5,700.00 Implemented
and  Toilet Bowl 1 pc 998.00 998.00
germination
 Plywood 30 pcs 300.00 9,000.00
beds)
 Labor Cost 4 550.00 for 112 246,400.00
manpower days
4. Purchase of Wood  6x6x10 (12pcs) 360 bft 32.00 11, 520.00
lumber for the
working
shed/storage and
germination beds
 5x5x14 (8 pcs) 258 bft 32.00 8, 256.00 Implemented
 2x3x14 (20pcs) 140 bft 32.00 4, 480.00 Implemented
 2x2x10 (40pcs) 133 bft 32.00 4, 256.00 Implemented
 1x8x8 (160pcs) 853 bft 32.00 27, 296.00 Implemented
 1x8x14 (6pcs) 56 bft 32.00 1,729.00 Implemented
 2x4x8 (12pcs) 64 bft 32.00 2,048.00 Implemented
Sub Total Php 359, 693.00

Total Php 649, 168.00 Fully


implemented
Work and Financial Plan
2nd Part
Project Title Planting of Bamboo seedlings
Project Proponent Amfan Clan Agro-Industrial Development Association Incorporated (A
Project Duration 2 years (24 months)
Phases/Stages of Budget items Quantity Amount Total Responsible
Activities (Php) Amount
(Php)
1.Bagging of Bamboo 1 2 3 4 5
seedlings
 Land Preparation  Rental of 16 hrs 700.00/ hour 11, 200.00 Equipment
Equipment operator
 Purchase of Bamboo  Bamboo seedlings 100, 000 7.00 700, 000.00 ACAIDA Inc.
Mother Trees including hills
the estimated hauling
rate
 Bamboo seedlings 10 loads 10, 000/load 100, 000.00 Truckers
cost per load
 Purchase of 100, 000 1.60 160, 000.00 ACAIDA Inc.
polyethylene bag hills
 Bagging of Purchased  Labor cost 100, 000 3.75 375, 000.00 Laborers
mother trees hills
2.Bamboo Propagation  Fertilizer 100, 000 20,000.00 20,000.00 Laborers
application hills

 Transplanting & 1.Anna Fertilizer 10 Bottles 250.00 2, 500.00 ACAIDA Inc.


Fertilizer application
(2x a month)
 Bamboo Propagation 2.Urea 10 sacks 2, 380.00 23, 800.00 ACAIDA Inc.

3.Sulphate 10 sacks 1, 250.00 12, 500.00 ACAIDA Inc.

4.Round-up Fertilizer 4 gals 1, 500.00 6, 000.00 ACAIDA Inc.

5.Pesticides 2 gals 1, 600.00 3, 200.00 ACAIDA Inc.

Sub Total
3.Nursery 1. Fish net 500 mts 65.00 32, 500.00 ACIDA, Inc.
Maintenance/Watering 2. Wheel barrow 4 pcs 6, 950.00 27, 800.00
Activities
3. Shovel 6 pcs 362.00 2, 172.00
4. Rake 6 pcs 646.00 3, 888.00
5. Hole digger 6 pcs 745.00 4, 470.00
6. Watering can 6 pcs 336.00 2, 028.00
7. Trowel 20pcs 239.75 4,795.00
8. Chillington 4pcs 523.00 2,092.00
9. Piko 1pc 730.00 730.00
Sub Total
Total