Proposed Time Table For Backfilling

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

The Backfilled area = 67,562.00 m2 up to LVL. +0.40 1st layer .

Periorty Backfilling area to reach the back bulding = 14,230 m2


P.01

Required Backfilling for the Remaining Area at LVL. +0.40 = 34,152 m3


Average of Daily Supplied Backfilling = 8,500 m3/Day
The Approx. time to Finish the 1st. layer = 34,152 m3 /8,500 m3/Day = 4Day

5th layer +2.27 1 st. Periorty


50.0 cm Crushed Stone As per Spec.
4th.layer +1.77
3rd. layer+1.40 37.0 cm Sand Backfill As per Spec.

2nd. layer+0.90
50.0 cm Sand Backfill As per Spec. 2nd. Periory
50.0 cm Sand Backfill As per Spec.
1St. layer +0.40

Sand Backfill As per Spec. Remaining area


Bottom of lake

Needed time for Each layer of the Periorty Backfilling area = 3 Day in parallel with the other remaining areas 10 000
EL
FFL
GROUND

09 000
TOP
10
EL
FFL
GROUND
240
OF RAIL

P.01 P.20

The other Remaining Backfilling Area will be finish in parallel with the periorty area .= 52,000 m2.

Activity .01 4.01 5.01 6.01 7.01 8.01 9.01 0.01 1.01 2.01 3.01 4.01 5.01 6.01 7.01 8.01 9.01 0.01 1.01 2.01 3.01 4.01 5.01 6.01 7.01 8.01 9.01 0.01 1.01 1.02 2.02 3.02 4.02 5.02 6.02 7.02 8.02 9.02 0.02 1.02 2.02 3.02 4.02 5.02 6.02
Time 03 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1
1st. layer .
2nd. layer . 3rd. layer . 4th. layer . 5th. layer .
1 st. Periorty Area
2nd. layer . 3rd. layer . 4th. layer . 5th. layer .
2nd. Periory Area

1st. layer . ( in case of increasing the daily average of suuplied backfilling by 5000 m3 and 03 ADD. loaders )
Remaining area
2nd. layer . 3rd. layer . 4th. layer . 5th. layer .

The time table consider the Daily supplied backfilling is 8,500 m3 / Day and after date of 11.01.2022 will increased to 13,500 m3 /Day
Additional 03 loader is Considerd