Proposed Time Table For Backfilling
Proposed Time Table For Backfilling
Proposed Time Table For Backfilling
2nd. layer+0.90
50.0 cm Sand Backfill As per Spec. 2nd. Periory
50.0 cm Sand Backfill As per Spec.
1St. layer +0.40
Needed time for Each layer of the Periorty Backfilling area = 3 Day in parallel with the other remaining areas 10 000
EL
FFL
GROUND
09 000
TOP
10
EL
FFL
GROUND
240
OF RAIL
P.01 P.20
The other Remaining Backfilling Area will be finish in parallel with the periorty area .= 52,000 m2.
Activity .01 4.01 5.01 6.01 7.01 8.01 9.01 0.01 1.01 2.01 3.01 4.01 5.01 6.01 7.01 8.01 9.01 0.01 1.01 2.01 3.01 4.01 5.01 6.01 7.01 8.01 9.01 0.01 1.01 1.02 2.02 3.02 4.02 5.02 6.02 7.02 8.02 9.02 0.02 1.02 2.02 3.02 4.02 5.02 6.02
Time 03 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1
1st. layer .
2nd. layer . 3rd. layer . 4th. layer . 5th. layer .
1 st. Periorty Area
2nd. layer . 3rd. layer . 4th. layer . 5th. layer .
2nd. Periory Area
1st. layer . ( in case of increasing the daily average of suuplied backfilling by 5000 m3 and 03 ADD. loaders )
Remaining area
2nd. layer . 3rd. layer . 4th. layer . 5th. layer .
The time table consider the Daily supplied backfilling is 8,500 m3 / Day and after date of 11.01.2022 will increased to 13,500 m3 /Day
Additional 03 loader is Considerd