1.3 Elevation
1. Backfill (Above Sidewalk)
1
ITEMS ACTION BY REMARKS
2.0 STRUCTURAL TARGET WORKS EMV
1. Phase I – Grid Line A – E
○ Installation of : Deck floor Steel Beam(Jollibee)
○ Ground Floor Preparation(Jollibee)
○ Excavation & Installation of PVC Pipe for Storm Drain
2. Phase II – Grid Line E – I
○ Ground Floor Preparation
○ Installation of : Roofing Sheets(#2)
○ Installation of PVC Pipe for Storm Drain
& Connection for Roof Drain and Floor Drain
○ Concreting of : Slab on Fill
3. Phase III – Grid Line I – L
○ Sewage Treatment Plan (Civil Works)
○ Lifting Station (Civil Works)
○ Installation of : Concrete gutter
;Roofing(#5 & #2)
○ Installation of PVC Pipe for Storm Drain
& Connection for Roof Drain and Floor Drain
○ Facade; Plastering & Canopy
○ CHB Laying & Plastering (Parapet Wall)
4. Site Development
○ Backfilling
○ CHB Laying (Pathwalk & Parking)
2
ITEMS ACTION BY REMARKS
4.0 HEAVY EQUIPMENT
4.1 Backhoe MGC
4.2 Mobile Crane MGC
12.0 STP
12.1 Timeline – 2-3 weeks after DP
12.2 Pumps from Lifting Station to STP ;
- Tap @ Control Panel for Sequencing
3
The meeting is adjourned at ____________________
Next Meeting is to be on April 19, 2023 (10:00 am)
Host for Lunch Next Meeting: Waterproofing