PROJEK MASS RAPID TRANSIT LALUAN 2: SUNGAI BULOH - SERDANG – PUTRAJAYA (SSP)
METHOD STATEMENT
Syed Mohd
Dzulhazmi Bin Norhisham Bin Abd Shukor Bin
Name Dzulkafli
Name Syed Mohamed
Name Ismail
Zain
Jr. Project Construction
Position Engineer
Position Manager
Position Project Manager
REVISION HISTORY
TABLE OF CONTENTS
1 INTRODUCTION ............................................................................................................................. 4
1.1 PURPOSE ................................................................................................................................... 4
1.2 SCOPE ....................................................................................................................................... 4
2 ABBREVIATIONS & DEFINITIONS ................................................................................................ 4
3 REFERENCES ................................................................................................................................ 4
4 SCOPE OF WORK .......................................................................................................................... 5
4.1 GENERAL DESCRIPTION ............................................................................................................... 5
4.2 MATERIAL ................................................................................................................................... 5
4.3 MACHINE, PLANT AND EQUIPMENT ................................................................................................ 5
4.4 MANPOWER................................................................................................................................. 6
4.5 CONSTRUCTION PROCEDURES / METHODOLOGY ........................................................................... 7
8 APPENDICES ................................................................................................................................ 15
APPENDIX A: ALUMINIUM COMPOSITE PANEL WORKS FLOW CHART ..................................... 16
APPENDIX B: JOB SAFETY & HEALTH ANALYSIS ......................................................................... 18
APPENDIX C: ENVIRONMENTAL ASPECT IMPACT ........................................................................ 19
APPENDIX D: INSPECTION & TEST PLAN ....................................................................................... 20
List of Tables
Table 1: Table of Abbreviations & Definitions ......................................................................................... 4
Table 2: List of Project Documents & Standards .................................................................................... 4
Table 3: List of Materials ......................................................................................................................... 5
Table 4: List of Machine, Plant & Equipment .......................................................................................... 5
Table 5: List of Manpower ....................................................................................................................... 6
1 INTRODUCTION
1.1 Purpose
This method statements are prepared for all works involved in Aluminium Composite Panel
Works for Project Mass Rapid Transit Laluan 2: Sg. Buloh – Serdang – Putrajaya (SSP),
Package BDT 202: Proposed Construction and Completion of SSP Line Feeder Bus Depot and
Associated Works at Serdang, Selangor Darul Ehsan in accordance with the specifications and
construction drawings.
1.2 Scope
This document is applicable to Package BDT202: Proposed Construction and Completion of SSP
Line Feeder Bus Depot and Associated Works at Serdang, Selangor Darul Ehsan.
4 SCOPE OF WORK
This Method Statement describes the construction procedures for Aluminium Composite Panel
Works. To ensure the works is comply with specification and standard practice. The scope of
works comprises of surface preparation, mixing epoxy resin, floor coating and other ancillary
works required as per the contract specification, BQ and Construction Drawing.
4.2 Materials
The materials required for the works includes, but are not limited to the items listed within the
following:
4.4 Manpower
Coordinate deliveries to comply with constructions schedule and arrange for off the
ground and under cover storage locations. Do not load any building area beyond safe
design load limits.
Protect the structure and work of the other trades during delivery, storage handling
and execution of the installation work.
Provide safe and adequate equipment to execute the work, hoisting, plant, and other
equipment required for the proper completion of work.
Aluminium composite panels will be packed into bundles to avoid slipping that may
cause dents and scratches. Wooden pallets will be used for the ease of handling.
Aluminium composite panels and all its accessories will be transported to site and
unloaded with appropriated lifting and hoisting equipment, and stacked/ stored
properly at proper area.
The material to be stored in a dry location that will prevent damage from weather,
accidental damage, theft and moisture.
Handle materials to prevent warping, twisting, sliding over rough surfaces and
damage in any kind. Exercise care in moving and opening cartons to prevent damage
to the panel surface.
4.5.2 Requirement
Work come before the aluminium composite panels shall all be completed before the
installation of panels such as roof structure, covering work, gutter work and other
trade.
Inspect site and verify that there are no conditions that will adversely affect the
installation work of the aluminium composite panels.
Installers shall verify the existence and appropriation of steel or concrete structures
where the sub-frames of aluminium composite panels are to be fixed onto.
Installers shall also verify works before the aluminium composite panels are
completed, and will have no further disturbance to the installation works of panels.
To coordinate with all the interfacing elements and ensure that all interfacing details
are approved prior to commencement of works.
Setting out and plumbing the x and y axis shall be done according to the gridline
marks and reduced level datum marked.
It is only practical and advisable that the setting out of the façade shall be done in full
height or one plane. Handover must be the full height of the facade but can be limited
to certain length of the facade.
Site inspection on the the setting out shall be conducted where applicable.
Site measurements shall be taken and recorded in the shop drawings for verification.
Before start work, conduct PTT with working parties and road closure conduct by
TMO.
Skylift will use as a platform for setting out work and installation works.
Aluminium brackets, angle brace and other accessories that consist part of the
bullnose or cladding system, shall be fixed with self-drilling screws only by electrical
drill.
Installation work should be carried out in accordance with the approved shop
drawings.
First, brackets should be fixed to the steel or concrete structures which are expected
to carry the entire weight of the bullnose or cladding system.
For the meeting of dissimilar materials for example aluminium and steel, insulation
element for example Chromate Coating / Paint needs to be in place. If place not
observed or not properly painted on either face of dissimilar materials, to apply
chromate coating at site prior to installation.
L angles will then be fixed to the brackets align with marking and alignment which
have been made earlier.
Lastly, the aluminium composite panels should be held to a right position with sliding
stopper to prevent slipping, and then fix the panels onto the aluminium sub-frames
with clamps.
The 25mm gaps between panels shall be covered up with the extruded aluminium
sections, and sealed with approved silicone sealant.
Clearing operation should be carried out in stages from the top and working
downwards.
The aluminium composite panels can be easily cleared with water and a sponge or
with a soft bristled brush and a mild detergent solution.
Avoid strong alkaline or acid products and abrasive solutions. The clearing should be
followed with a thorough rinsing with clean water to ensure the removal of all
remnants of the cleaning agent used earlier.
It is recommended that cleaning be done once or twice a year. However, the cleaning
frequency will depend on the location and environmental conditions.
An initial step of forceful water rinse from the top down is recommended prior to any
cleaner application. Low water volume with moderate pressure is much better than
considerable volume with little pressure.
Cleaner with corrosive material is prohibited for the cleaning of the panel surface.
Avoid aggressive acid, alkali or ethyl alcohol which can cause damage to the panel
surface.
When mild solution of detergent is used removing soil, it should be used with soft
sponge or soft rag. The washing should be done with uniform pressure. Normally the
operation is done with a horizontal motion first, followed by a vertical motion.
After washing, the surface should be thoroughly rinsed with clean water. The rinsed
surface is air-dried or wiped with lint free cloth.
4.5.7 Protection
The protection film should be remained during the construction process in order to
protect the coated surface from stains caused by sealant and machine oils. If
adhered, these stains should be removed as soon as possible before hardening with
suitable detergent.
Do not use abrasive or rough cleaning material as it can damage the surface.
Strong organic solvent such as MEK (Methyl Ethyl Ketone), MIBK (Methyl Iso-Butyl
Ketone), Triclene (Tri-chloroethylene) and paint thinner is strictly prohibited.
Avoid extreme temperature to clean the coated surface. Heat may accelerate
chemical reactions and may evaporate the water from solution.
Extremely low temperature may give the poor cleaning effects. On the contrary,
cleaning under higher temperature may result in streaking.
To prevent the surface from scratch, do not over clean the panel surface. Excessive
rubbing and sharp cleaning tools can harm the panel surface.
a) Safety induction to be conducted to all new workers that involved to this activity.
b) HIRARC briefing to be conducted by safety and health officer to all personnel who are
involved with this works activity.
c) Pre-task talk tool box meeting shall be conducted by site supervisor every day and /or
before commencement of any works related to this work activity to remind all workers
about the safety control measure.
d) All workers shall be provided with Personal Protective Equipment (PPE) and shall be worn
at all time on site.
e) All workers shall be provided with additional personnel protective equipment’s determined
and stated in Hazard Identification, Risk Assessment and Risk Control (HIRARC).
f) A permit to work system shall be established for excavation work.
g) Before allowing to works all the machine and equipment shall undergo pre-entry
inspection, approved by SC and be certified as fit for use.
h) All machine and equipment shall be inspected daily by a designated person before the
start of work and every defect shall be immediately corrected before commences.
i) All scaffold structure shall be of tubular or modular type and comply with national or
acceptable international standards. All scaffold to be erected under the supervision of
competent scaffold supervisor. A-frame type scaffold shall be restricted to be used at
project site.
j) Every scaffold and every part thereof shall comply with the Malaysian Standard or any
other relevant international standard. No scaffold shall be erected or be substantially
altered or be dismantled including scaffolds use as false work for supporting formwork
except under the direct supervision of a designated person.
k) Scaffold erector should always adopt a safe system of work during the erection, altering
and dismantling of scaffolds. This shall include the use of fall arrest equipment
l) Every metal tube scaffold exceeding 40 meters in height and every other scaffold
exceeding 15 meters in height shall be constructed in accordance with the design and
drawings of a Professional Engineer.
m) WPC shall implement a Scaffold Tagging System (Green Tag and Red Tag) for every
scaffold structure. The tags shall be display at appropriate location for information and
inspection.
n) The WPC shall envelop all scaffolds with screen nets to prevent debris from falling outside
the scaffold.
o) All users of scaffolding are provided with basic training in working at height.
p) All working places situated at a height in excess of 2.0 m, which is not protected by full
edge protection, is considered to be “working at height”. Work at height shall only be
permitted with the use of properly established fall prevention systems or work positioning
devices including full body harnesses with shock absorbing lanyards attached to anchor
points or tensioned safety lines and or retractable life lines.
q) All workers required to follow all the temporary signage’s displayed on site and barricades
at diversions and temporary haul road as necessary (if applicable).
r) All vehicles used at site must be roadworthy and registered with the appropriate authority
in accordance with the Road Traffic Ordinance 1958. (Ord 48 of 1958).
s) No person shall be driving a vehicle of any class or description on site unless he is the
holder of a driving license authorizing him to drive a vehicle of that class or descriptions.
t) All workers shall be advised to report any accident or injury to Site Supervisor.
6 ENVIRONMENTAL ISSUES
All workers shall educate on good environmental management practices and well-disciplined
Lorries carrying raw material, excess earth and debris should be covered with tarpaulin or
other similar material to prevent spillage.
All construction machinery should be in good working condition to reduce emission of
shoot, smoke and dust.
Wheel washing facility or wash through will be constructed at the exit point of the project
site. It should be fully utilized and regularly maintained. Access route within the project site
should be sufficiently compacted to minimize dust dispersion especially during dry whether
condition.
7.1 Requirements
The general requirements for Floor Screeding/Rendering Works shall be in accordance with
details and specification as per contract.
Implementation and compliance of work with Inspection and Test Plan (ITP).
Confirmation and approval inspection via RFI for both work inspection and testing activities.
All Inspection and testing shall be in accordance to the approved Inspection and Test Plant
(ITP), Refer to Appendix B
RFI
Test report and related work record will be submitted to SC for review prior start
commencement of subsequence construction activities.
To monitor using Quality Control Checklist
8 APPENDICES
APPENDIX A
Start
Passed Rectification
Yes No
Start installation
Yes No
Final Inspection
No
End
APPENDIX B
Risk Rating
Likelihood
Current Counter Additional Current Person In
Severity
Item Activity Hazard Risk
Measure(s) Counter Measure(s) Charge
1 Materials delivery Physical Major bodily Admin ctrl 2 2 4 - Traffic management plan Construction
Injury - Site safety induction (TMP) Manager
Transportation of materials Hit by the - Pre-task talk - Communication with
by lorry moving public Property - Weekly toolbox talk purchasing dept. supplier Site supervisor
vehicles and / damages - Supervised by site and project team (PIC)
or motorcycles. supervisor confirmation on the details Site safety
- Experienced driver with of deliveries. supervisor
valid driving license - Time arrangement/ avoid
- Site access points from delivery process during
public roads attended by peaks hours
trained security guards and
trained flagman
(equipped with whistle &
others necessaries traffic
control tools).
- Banksman – if required
- Dedicated & protected
traffic and pedestrian
route
- Clear & visible speed limits
sign
- Adequate, proper, clear
and visible signage, road
iINFRA SDN BHD Doc No: HSE-P03-F01
HAZARD IDENTIFICATION, RISK ASSESSMENT AND RISK CONTROL (HIRARC) REGISTER Rev No: 1
operator
Fall from forklift - Flashing light, reverse Plant &
alarm & horn Machinery
- Separated pedestrian Inspector
route (PMI)
- Forklift class suit with the
work arrangements/ to be
done
PPE
- Safety helmet, Hi-Vi vest,
safety shoe
Physical Minor bodily Admin ctrl 2 2 4 - Communication with Construction
injury - Site safety induction purchasing dept. supplier manager
Improper - Pre-task talk and project team (PIC)
storage/ Property - Weekly toolbox talk confirmation on the details Site supervisor
/unorganized damage - Supervised by site of deliveries.
of materials supervisor Operator
- Store material at
designated location.
- Daily housekeeping
3 Materials storage Physical Major Admin ctrl 2 2 4 - Materials received in a Construction
bodily injury - Site safety induction good packaging manager
Improper - Weekly toolbox talk - Communication with
arrangement Property - Pre-task talk purchasing dept. supplier Site supervisor
/stacking of damages - Supervised by site and project team (PIC)
materials supervisor confirmation on the details Operator
Obstruction - Maintain good of deliveries.
housekeeping
Physical Minor bodily Admin ctrl 2 2 4 - Maintain good Construction
injury - Site safety induction housekeeping/immediate manager
Slip, trip & fall - Pre-task talk swept any debris and/or
- Weekly toolbox talk rubbish Site supervisor
- Supervised by site
supervisor
- Keep storage area neat
and orderly, remove
used/unwanted materials
iINFRA SDN BHD Doc No: HSE-P03-F01
HAZARD IDENTIFICATION, RISK ASSESSMENT AND RISK CONTROL (HIRARC) REGISTER Rev No: 1
absorber
Physical Major Admin ctrl 2 3 6 - Lifting plan (if required) Project
Bodily injury - Site safety Induction - Operated on even Engineer
Boom lift/sky lit - Weekly toolbox talk ground and on a stable
topple Property - Pre-task talk base Site Supervisor
damages - Permit to work - Steel plate for outrigger (if
Hit by others - Supervised by site required) Lifting
machineries supervisor - Avoid using boom lifts in Supervisor
- Lifting supervisor extremely windy conditions
- Experienced - Do not operate on Crane
driver/operator surfaces that exceed the operator
- Trained worker manufacturer’s maximum
- Safe Working Load (SWL) rated slope.
displayed - Properly reviewing the
- Levelling device manufacturer’s manual will
Isolation help an operator
- Temporary barricades understand how to
- Safety/warning sign effectively maneuver the
PPE boom lift and when it is and
Safety helmet, high visibility isn’t safe to move the lift
vest & safety shoe while it is extended.
Ergonomic Minor bodily Admin ctrl 2 2 4 Architect
injury - Site safety induction Coordinator
Awkward - Weekly toolbox talk
position and/or - Pre-task talk Site Supervisor
repeated - Supervised by the site
movement supervisor
- Workers are given and
use the right power tool for
the job
- Experienced workers
- Warning/ safety signage
PPE
- Safety Helmet, Hi-Vi vest
& safety shoe
Additional PPE
- Glove
iINFRA SDN BHD Doc No: HSE-P03-F01
HAZARD IDENTIFICATION, RISK ASSESSMENT AND RISK CONTROL (HIRARC) REGISTER Rev No: 1
features
- Guards of power tools is in
place during use
- Portable power tool
register
- Inspected by their user at
the start of every shift
- Thoroughly examined at
least once every three
months
PPE
- Safety Helmet, Hi-Vi vest
& safety shoe
Additional PPE
- Proper glove
Physical Minor injury Admin ctrl 2 2 4 - All portable power tools
- Site safety induction used is maintained, stored
Concrete dust Irritate eyes, - Weekly toolbox talk and inspected in
& flying nose, throat - Pre-task talk accordance with the
particle and the - The operators of these manufacturers’
upper tools are suitably trained. recommendations
Skin contact respiratory - Supervise by site - Site manufactured tools
system. supervisor and equipment is strictly
Expose to high - Workers are given and prohibited
level noise Moderate use the right power tool for - Power tools shall not be
irritation the job modified in any manner
severe skin - Guards for these power that disables any safety
damage tools is in place during use features
from - Portable power tool
chemical register
burns - Inspected by their user at
the start of every shift.
Hearing loss. - Thoroughly examined at
least once every three
months
- Safety glasses, face mask,
glove & ear plug
iINFRA SDN BHD Doc No: HSE-P03-F01
HAZARD IDENTIFICATION, RISK ASSESSMENT AND RISK CONTROL (HIRARC) REGISTER Rev No: 1
safety shoe
Additional PPE
- Suitable glove
Physical Fatality Admin ctrl 2 3 6 - Lifting plan (if required) Project
- Site safety Induction - Operated on even Engineer
Fall from Major bodily - Weekly toolbox talk ground and on a stable
height/ bucket injury - Pre-task talk base Driver/
- Permit to work - Avoid using boom lifts in Operator
- Valid PMA extremely windy conditions
- SWL displayed - Do not operate on Site Supervisor
- Supervised by site surfaces that exceed the
supervisor manufacturer’s maximum Lifting
- Trained driver/operator rated slope. Supervisor
- Trained workers - Properly reviewing the
- Bucket with anchor point manufacturer’s manual will
for full body harness help an operator
- Enter and exit the understand how to
platform only when it is fully effectively maneuver the
lowered/ ground level. boom lift and when it is and
PPE isn’t safe to move the lift
Safety helmet, high visibility while it is extended.
vest & safety shoe
Additional PPE
- Double lanyard full body
harness with shock
absorber
Physical Fatality Admin ctrl 2 3 6 - Lifting plan (if required) Project
- Site safety Induction - Operated on even Engineer
Falling objects Major bodily - Weekly toolbox talk ground and on a stable
injury - Pre-task talk base Driver/
- Permit to work - Avoid using boom lifts in Operator
- Supervised by site extremely windy conditions
supervisor - Do not operate on Site Supervisor
- Experienced surfaces that exceed the
driver/operator manufacturer’s maximum Lifting
- Trained worker rated slope. Supervisor
- Wide platform - Properly reviewing the
iINFRA SDN BHD Doc No: HSE-P03-F01
HAZARD IDENTIFICATION, RISK ASSESSMENT AND RISK CONTROL (HIRARC) REGISTER Rev No: 1
6 Housekeeping Physical Minor bodily Admin ctrl 2 2 4 - Designated area for Construction
injury - Site safety induction storage of materials Manager
Slip, trip & fall - Pre-task talk
- Weekly toolbox talk Site Supervisor
- Supervised by site
supervisor
- Daily housekeeping
- Maintain good
housekeeping
PPE
- Safety helmet, Hi-Vi vest &
safety shoe
APPENDIX C
Project : PROJEK MASS RAPID TRANSIT LALUAN 2: SUNGAI BULOH – SERDANG – PUTRAJAYA (SSP) PROPOSED CONSTRUCTION AND
COMPLETION OF SSP LINE FEEDER BUS DEPOT AND ASSOCIATED WORKS AT JINJANG, KUALA LUMPUR FOR MASS RAPID TRANSIT
CORPORATION SDN BHD (MRT CORP)
Activity: INSTALLATION OF RC HOOD
Rating
Condition (N/AB/E)
Revision
Risk Rating
Applicable Legal/Other
Probability
Item
Severity
Activity Environmental Aspect Environmental Impact Control Measure(s)
Requirement
Water consumption for Consumption of Resources Natural Resources N 3 3 9 • Reduce usage of water • Project
pantry Depletion consumption. Environmental
• All pipe leakage need to rectify Management Plan
immediately. (EMP)
Management Plan
(EMP)
• DEIA Approval
Condition No (36)
• Solid Waste and
Public Cleansing
Management Act,
2007
2 Toilet Facilities
Portable Toilet and Sewage may produce bad Water pollution and N 2 3 6 • To always maintain and • Project
Permanent Toilet smell or leak into Land contamination arrange for desludging the Environmental
waterways septic tank. Management Plan
(EMP)
• DEIA Approval
Condition No (33)
• Solid Waste and
Public Cleansing
Management Act,
2007
3 Wash Through Facilities Sediment laden runoff from Water pollution N 4 2 8 • Construction of erosion and • Project
disturbed areas sedimentation control (ESC) Environmental
measures. Eg, Temporary Management Plan
earth drain, silt traps, check (EMP)
dams and silt fence. • DEIA Approval
Condition No (5) (6)
(7) (8) (9) (10) (11)
(12) (14) (17) (18)
(31)(32) (34) (45) (47)
• Project Specific
Erosion and
Sediment Control
Plan (ESCP).
• National Water
Quality Standards
(NWQS).
iINFRA SDN BHD Doc No: HSE-P03-F02
ENVIRONMENTAL ASPECT IMPACT REGISTER Rev No: 0
Generation of dust from Air Pollution N 4 2 8 • The speed limit and traffic • Project
machineries movement volume restriction within the Environmental
site area shall be implemented Management Plan
to reduce dust dispersion. (EMP)
• Water browser need to standby • DEIA Approval
for watering on the access Condition No (14)(15)
road (26) (27) (29) (30)
• (47)
• Environmental
Quality (Clean Air)
Regulations 2014.
• Environmental
Quality (Control of
Emission from Diesel
Engines) Regulations
1996.
• Environmental
Quality (Control of
Emission from Petrol
Engines) 1996.
• Recommended
Malaysian Air Quality
Guidelines (RMAQG)
Dirtying of public road Public nuisance / Public N 2 3 6 • Water browser need to • Project
complain / Air pollution standby for watering all the Environmental
time. Management Plan
• Earth drain shall be (EMP)
constructed to channel surface • DEIA Approval
runoff to silt trap. Condition No (14)(15)
(26) (27) (29) (30)
(47)
• Environmental
Quality (Clean Air)
Regulations 2014.
• Environmental Quality
(Control of Emission
from Diesel Engines)
Regulations 1996.
iINFRA SDN BHD Doc No: HSE-P03-F02
ENVIRONMENTAL ASPECT IMPACT REGISTER Rev No: 0
• Environmental
Quality (Control of
Emission from Petrol
Engines) 1996.
• Recommended
Malaysian Air Quality
Guidelines (RMAQG)
4 Schedule Waste Storage Generation of schedule Land contamination N 3 3 9 • Provision of scheduled waste • Project
• Schedule Waste waste inventory. Environmental
been stored • Labelling for type of schedule Management Plan
wastes. (EMP)
• Provision for waste card base • DEIA Approval
on waste type Condition No (37) (38)
• All schedule waste must be • Environmental
notified in the E-SWIS within 30 Quality (Scheduled
days after generate. Waste) Regulations,
2005
Schedule Waste Storage Schedule waste spillage or Land contamination E 4 2 8 • Immediate clear any spillage • Project
• Handling of leakage on the ground using spill kit. Environmental
schedule waste • Provision to provide and use of Management Plan
spill kit. (EMP)
• Provision to provide oil sump • DEIA Approval
for collection of any spillage. Condition No (37) (38)
• Environmental
Quality (Scheduled
Waste) Regulations,
2005
Schedule Waste Storage Incompatible schedule Fire/Explosion AB 2 3 6 • Provision of scheduled waste • Project
• Compatibility of waste stored in same store inventory. Environmental
schedule waste • Labelling for type of schedule Management Plan
type being stored wastes. (EMP)
• Provision for waste card base • DEIA Approval
on waste type. Condition No (37) (38)
• Schedule waste shall be stored • Environmental
in appropriate container. Quality (Scheduled
• Incompatible schedule wastes Waste) Regulations,
stored in separated container. 2005
iINFRA SDN BHD Doc No: HSE-P03-F02
ENVIRONMENTAL ASPECT IMPACT REGISTER Rev No: 0
6 Installation work
Setting out & Preparation Generation of dust Air Pollution N 2 1 2 • The speed limit and traffic • Project
work (lorry in & out) volume restriction within the Environmental
site area shall be implemented Management Plan
to reduce dust dispersion. (EMP)
• Water bowser need to standby • DEIA Approval
for watering on the access Condition No (14)(15)
road (26) (27) (29) (30)
(47)
• Environmental
Quality (Clean Air)
Regulations 2014.
• Environmental
Quality (Control of
Emission from Diesel
Engines) Regulations
1996.
• Environmental
Quality (Control of
Emission from Petrol
Engines) 1996.
• Recommended
Malaysian Air Quality
Guidelines (RMAQG)
Generation of noise Noise pollution N 2 1 2 • To install hoarding. • Project
• Working within approval Environmental
working hours. Management Plan
• Maintenance of machinery (EMP)
to be conducted regularly. • DEIA Approval
• All noise generating Condition No (36)
equipment and machinery • Solid Waste and
shall be shut down when Public Cleansing
not in used. Management Act,
2007
iINFRA SDN BHD Doc No: HSE-P03-F02
ENVIRONMENTAL ASPECT IMPACT REGISTER Rev No: 0
7
Cleaning & Housekeeping Generation of non- Land contamination N 4 2 8 • All type of waste must be • Project
scheduled waste. segregated, stored and Environmental
disposed of in accordance with Management Plan
the package EMP. (EMP)
• Open burning is strictly • DEIA Approval
prohibited. Condition No (36)
• Waste shall dispose of at the • Solid Waste and
approved disposal site. Public Cleansing
Management Act,
2007
iINFRA SDN BHD Doc No: HSE-P03-F02
ENVIRONMENTAL ASPECT IMPACT REGISTER Rev No: 0
Reviewed By SYED MOHD NORHISHAM MOHAMAD ZAIN CONSTRUCTION MANAGER 29 July 2020
APPENDIX D
Inspection Point
No. Activity Description Reference Document Acceptance Criteria Frequency Records/Checklist
WPC SC MRTC
1.0 Approvals
Compliance to:
Before
Approved Construction Drawing Approved Material
1.1 Submission Material General Specification/BQ commencement the H H R
BQ Submission
work
M&W Spec
Compliance to:
Before
Submission Method Specification
1.2 General Specification/ BQ commencement the Approved MST H H R
Statement Construction Drawing
work
M&W Spec
2.0 Aluminium Composite Panel Process
Compliance to:
Method Statement for Prior RFI/ Inspection
Specification
2.1 Material Delivery Aluminium Composite Panel commencement the Checklist – Aluminium H S W
Construction Drawing
Installation Works work Composite Panel
M&W Spec
Method Statement for Compliance to: During RFI/ Inspection
2.2 Survey and Setting Out Aluminium Composite Panel Specification commencement the Checklist – Aluminium H W W
Installation Works M&W Spec. work Composite Panel
Note 1: Acronym to be used on “Inspection Point” columns by the relevant Inspection Authority (Note 2)
H - Hold Point Points where no further works shall proceed without the written approval of the Client/SC.
Note 2: Inspection Authority acronyms
- Points where Client/SC can opt to observe / or visually examine or participate in the quality control operation of the
W - Witness Point WPC Works Package Contractor
WPC.
Point where the Client/SC representative monitor the WPC activities to the degree necessary for confidences that the Client Mass Rapid Transit Corporation
S - Surveillance
work process/ method is complying with the established criteria.
SC Supervision Consultant
R - Review Review of the WPC 's ITP records for correctness and completeness
Inspection Point
No. Activity Description Reference Document Acceptance Criteria Frequency Records/Checklist
WPC SC MRTC
Compliance to:
Aluminium Composite Method Statement for During RFI/ Inspection
Specification
2.3 Panel Installation Aluminium Composite Panels Commencement the Checklist – Aluminium H W W
Construction Drawing
Works Installation Works work Composite Panel
M&W Spec.
Note 1: Acronym to be used on “Inspection Point” columns by the relevant Inspection Authority (Note 2)
H - Hold Point Points where no further works shall proceed without the written approval of the Client/SC.
Note 2: Inspection Authority acronyms
- Points where Client/SC can opt to observe / or visually examine or participate in the quality control operation of the
W - Witness Point WPC Works Package Contractor
WPC.
Point where the Client/SC representative monitor the WPC activities to the degree necessary for confidences that the Client Mass Rapid Transit Corporation
S - Surveillance
work process/ method is complying with the established criteria.
SC Supervision Consultant
R - Review Review of the WPC 's ITP records for correctness and completeness