Professional Documents
Culture Documents
TREMIX FLOORING (For Car Park and Drive Way) : Method Statement
TREMIX FLOORING (For Car Park and Drive Way) : Method Statement
: GPL-RCC-TREMIX Flooring-047A
STANDARD OPERATING PROCEDURE Rev No.: 00
ACTIVITY : VACCUM DEWATERING FLOORING
Date: 27-03-2020
FOR PARKING AND DRIVE WAY LOCATIONS
METHOD STATEMENT
PREPARATORY WORKS:
L:B Ratio
Location of the Maximum Length of any Bay
Bay
Any Constraints to adopting the above said, then 4m X 4m size panel can be
taken up for VDF works for alternate bays in a staggered manner.
Alternate bay/ panel can be casted immediate after VDF flooring is completed
and finished as shown in the Image below i.e after 6 hours or the Bay 1
concrete is set without footmark
Note: After the proper vaccume dewatering, the sides can be deshuttered
with extra care without breaking edges as the surface will be able to deliver
the foot mark free surface(Refer VDF detail in below)
Ensure Anti-termite treatment done for the earth surface to protect it from the
attack by sub terrane termites before VDF.
Ensure 1000 gauge LDPE sheet to be laid over compacted earth or
GSB/WMM surface prior to begin with VDF.
GODREJ PROPERTIES LIMITED SOP No.: GPL-RCC-TREMIX Flooring-047A
STANDARD OPERATING PROCEDURE Rev No.: 00
ACTIVITY : VACCUM DEWATERING FLOORING
Date: 27-03-2020
FOR PARKING AND DRIVE WAY LOCATIONS
Ensure the compacted earth surface to be tested and certified to precede the
VDF works so that the compacted surface will sustain the loads that come
over it.
Ensure GSB/WMM surface to be compacted and tested for road works if any.
And lay the LDPE sheet prior to Reinforcement work, RF work to be done as
per approved drawings or as per Site requirements with consultant advise
Ensure existing concrete surface prior to VDF, is rough with wire mesh,
cleaned and moisten to SSD condition.
If any leakage observed due to plastic shrinkage cracks should have been
treated as per GPL concrete repair SOP. (SOP No.: GPL-RCC-CONCRETEREPAIR-029)
Ensure the slope to be maintained 1:150 for areas like basement, car parking
and roadwork in the compacted earth level itself. This will ensure GSB/WMM
and concrete quantities in control.
Ensure drainage angles with weep holes and proper alignment being marked
as per drainage layout approved in GFC/shop drawing.
If the expansion joint of the building in place kindly take necessary
precautionary approval taken and action for basic expansion treatment
methodology adopted for the location.
During Concreting:
The casting of concrete flooring shall be carried in panels to avoid shrinkage
cracks and work as a control joint. The size of panel for concreting should be
followed as per details mentioned in preparatory works.
Ensure the provision of expansion joint, 25mm thick HDF board to be placed
all around the columns, in between wall and floor junction and once in every
3rd panel or each 10mm gap.
VDF to be done as per slope ratio defined in approved shop drawing or 1:150
towards drain as per layout shown in the MEP drawing and recommend to
keep minimum 50mm thickness at the lowest location for the effective VDF.
The VDF concreting works should be produced only based on approved mix
design with M20 grade.
GODREJ PROPERTIES LIMITED SOP No.: GPL-RCC-TREMIX Flooring-047A
STANDARD OPERATING PROCEDURE Rev No.: 00
ACTIVITY : VACCUM DEWATERING FLOORING
Date: 27-03-2020
FOR PARKING AND DRIVE WAY LOCATIONS
The mix design may be carried out by the contractor or the RMC vendor or a
concrete consultant and the same should be approved by the EIC.
For concrete works, concrete mix design, batching, transport, placing (Tower
crane / pump),Sampling of cubes, curing to be adhered as per concrete
SOP(GPL-RCC-CONCRETING-043)
Before placing the concrete, spread the cement slurry of consistency 2.0
kg/sqm.
Before placing the concrete, Slump of concrete to be checked. The slump of
the concrete used for Flooring being should be 100 +/- 10 mm.
Then concrete poured on the surface levelled up to the button mark level.
Button marks to be placed at each 1.2m interval and the panel size to be
supported in straight line.
Compaction:
Compaction of concrete is the process of expelling entrapped air from the
concrete.
It has been found from the experimental studies that 1% air in the concrete
approximately reduces the strength by 6%.
Voids increase permeability of concrete and in turn reduce its durability.
Fully compacted concrete will be dense, strong, durable, and impermeable.
Concrete is vibrated using Needle vibrator on both sides of the panel.
Then concrete is compacted using double beam screed vibrator.
Trowel the concrete when required for it end-use. Smooth the surface with a
steel trowel after it is partially hardened.
Hold the trowel almost flat and swing it in large overlapping arcs while
applying pressure.
VACUUM DEWATERING FLOORING FOR SITE MIX CONCRETE
Recommend NO dewatering of RMCs. RMCs have water cement ratio
already maintained to its minimum possible level by addition of admixtures.
Further dewatering decreases the water cement ratio below the required level
GODREJ PROPERTIES LIMITED SOP No.: GPL-RCC-TREMIX Flooring-047A
STANDARD OPERATING PROCEDURE Rev No.: 00
ACTIVITY : VACCUM DEWATERING FLOORING
Date: 27-03-2020
FOR PARKING AND DRIVE WAY LOCATIONS
This is the indication of concrete being properly dewatered and ready for
finishing
However, the concrete surface should not be loaded or stepped upon for 2 to
3 hrs.
During this process ensure constant pressure of suction should be
maintained during vacuum de-watering (11.6 PSI or as per approved capacity
pump)
The excess water that is being removed is the water which has been added to
concrete to increase its workability.
Then the top surface of the concrete is finished using a power trowel
immediately after de-watering.
Sprinkling of surface hardener (approved brand) of coverage 5kg/m2
(Considering medium duty) to be done at the concrete surface after finishing
of green concrete.
The power trowel is floated on the concrete surface to give it a firm and
smooth finish.
Cement or cement mortar should not be laid while power floating to achieve a
smooth finish.
The power trowel is then fitted with the blade rotor tool and floated on the
concrete to get a shiny finish.
Delay in starting this activity could lead to the extraction of the coarse
aggregates from the concrete.
Date of casting should be written in the adjacent column or on the floor to
monitor the curing.
POWER TROWEL TREMIX FLOORING WITH OUT VACCUME DEWATERING
If Vacuum dewatering is not required for the RMC supplied concrete locations
use the below method after concrete is compacted using Double beam
vibrator and uniform Trowel levelling as explained in Compaction work
The concrete is left to stiffen. When the base concrete has stiffened to the
point when foot traffic leaves an imprint of about 3-6 mm and any bleed water
should now have evaporated, but the concrete should have a wet sheen
GODREJ PROPERTIES LIMITED SOP No.: GPL-RCC-TREMIX Flooring-047A
STANDARD OPERATING PROCEDURE Rev No.: 00
ACTIVITY : VACCUM DEWATERING FLOORING
Date: 27-03-2020
FOR PARKING AND DRIVE WAY LOCATIONS
Check the level of the flooring, ensure the slope provided as per proper
direction.
Ensure there is no water stagnation on finished floor.
The finishing should be uniform and as per mock up approved.
Check the groove cuts are in straight line as per panel size approved.
Grooves are cleaned and filled to the full depth and width by bitumen 60/70 or
PU sealant
Ensure expansion joints are in straight line, cleaned well and filled with PU
sealant or bitumen 60/70.
Bitumen (60/70) and Sealant MTC to be reviewed for each batch of material.
Expansion joint board to be checked as per approved TDS using MIR.
Note: ITP to be overlooked with the listed Testing Guidelines, if ITP is missing for any
material the Test Guidelines will be adhered, If not listed as per MAS SOP No.: GPL-
PROCESS-MATERIALAPPROVAL-056 and MIR
A typical cycle:
GODREJ PROPERTIES LIMITED SOP No.: GPL-RCC-TREMIX Flooring-047A
STANDARD OPERATING PROCEDURE Rev No.: 00
ACTIVITY : VACCUM DEWATERING FLOORING
Date: 27-03-2020
FOR PARKING AND DRIVE WAY LOCATIONS
GROOVE CUTTING: