Lab 5 Khazran

351492

Assigning Relations 7th, Nov 2022

Activity ID Activity Name Planned Duration Start Finish Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023
Jan Feb Mar Apr May Jun Jul Aug Sep
Khazran 149 05-Jan-23 01-Aug-23 01-Aug-23, Khazran

A1510 Expenses 0 05-Jan-23 05-Jan-23 Expenses


Initiation 0

Planning 135 05-Jan-23 06-Jul-23 06-Jul-23, Planning

Architechtural Drawing Prep 31 05-Jan-23 15-Feb-23 15-Feb-23, Architechtural Drawing Prep


A1000 Site Plane 10 05-Jan-23 17-Jan-23 Site Plane
A1010 Working Plan 4 19-Jan-23* 24-Jan-23 Working Plan
A1020 Floor Plan 7 25-Jan-23* 02-Feb-23 Floor Plan
A1030 Elevation 8 25-Jan-23* 06-Feb-23 Elevation
A1040 Facad 5 25-Jan-23* 31-Jan-23 Facad
A1050 Sectional Drawings 5 25-Jan-23* 31-Jan-23 Sectional Drawings
A1060 Idefining physical interphases 15 25-Jan-23* 15-Feb-23 Idefining physical interphases
A1070 Defining system elements 9 25-Jan-23* 07-Feb-23 Defining system elements
A1080 documentation of drawimgs 6 25-Jan-23* 01-Feb-23 documentation of drawimgs
A1480 Design of Railings 5 25-Jan-23* 31-Jan-23 Design of Railings
Structural Drawing Prep 47 01-Feb-23 06-Apr-23 06-Apr-23, Structural Drawing Prep
A1090 Excavation Plan 8 01-Feb-23* 13-Feb-23 Excavation Plan
A1100 Foundaton Plan 6 13-Feb-23* 20-Feb-23 Foundaton Plan
A1110 Column Layou Plan 8 21-Feb-23* 04-Mar-23 Column Layou Plan
A1120 Beam Detailing 5 27-Feb-23* 05-Mar-23 Beam Detailing
A1130 Slab Detailing 10 06-Mar-23* 19-Mar-23 Slab Detailing
A1140 Staircase Detailing 9 20-Mar-23* 02-Apr-23 Staircase Detailing
A1150 Shear Wall / Lift wall detailing 6 30-Mar-23* 06-Apr-23 Shear Wall / Lift wall detaili ng

Actual Level of Effort Remaining Work Page 1 of 3 Submitted to :Sir Mansoor


Actual Work Critical Remai... NBC
Lab 5 Khazran
351492

Assigning Relations 7th, Nov 2022

Activity ID Activity Name Planned Duration Start Finish Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023
Jan Feb Mar Apr May Jun Jul Aug Sep
Plumbing/HVAC Drawing Prep 65 10-Apr-23 06-Jul-23 06-Jul-23, Plumbing/HVAC Drawing Prep
A1160 SLD Diagram 3 10-Apr-23* 13-Apr-23 SLD Diagram
A1170 Control Diagram 4 12-Apr-23* 17-Apr-23 Control Diagram
A1180 Power Diagram 12 18-Apr-23* 04-May-23 Power Diagram
A1190 Schematic Diagam 13 18-Apr-23* 06-May-23 Schematic Diagam
A1200 Installation Detail 5 08-May-23* 14-May-23 Installation Detail
A1210 HVAC Layout Diadram 10 15-May-23* 28-May-23 HVAC Layout Diadram
A1220 Impedane Diagram 9 29-May-23* 10-Jun-23 Impedane Diagram
A1230 Water Supply/ System Drainage 7 08-Jun-23* 17-Jun-23 Water Supply / System Drainage
A1240 Drainage System Drawing 5 19-Jun-23* 25-Jun-23 Drainage System Drawing
A1250 Bathroom Closets 8 26-Jun-23* 06-Jul-23 Bathroom Closets
Produrement Phase 9 06-Jul-23 18-Jul-23 18-Jul-23, Produrement Phase

A1260 Hiring of Technical Team 8 06-Jul-23* 17-Jul-23 Hiring of Technical Team


A1270 Hiring of Contracctor 9 06-Jul-23* 18-Jul-23 Hiring of Contracctor
A1280 Hiring of Sub-Contractor 7 06-Jul-23* 15-Jul-23 Hiring of Sub-Contractor
A1290 Purchase of Materials 5 06-Jul-23* 12-Jul-23 Purchase of Materials
A1300 Macchinery Hiring 6 06-Jul-23* 13-Jul-23 Macchinery Hiring
A1460 Hiring of Consultants 6 06-Jul-23* 13-Jul-23 Hiring of Consultants
A1470 Bringing Labour 4 06-Jul-23* 11-Jul-23 Bringing Labour

Execution Phase 155 05-Jan-23 01-Aug-23 01-Aug-23, Execution Phase


A1310 Excavation 8 12-Jul-23* 23-Jul-23 Excavation
A1320 Lean Concrete 7 24-Jul-23* 01-Aug-23 Lean Concrete
A1330 Foundation Reinforcement Placement 10 05-Jan-23 17-Jan-23 Foundation Reinforcement Placement
A1340 Concrete Pouring 11 05-Jan-23 18-Jan-23 Concrete Pouring

Actual Level of Effort Remaining Work Page 2 of 3 Submitted to :Sir Mansoor


Actual Work Critical Remai... NBC
Lab 5 Khazran
351492

Assigning Relations 7th, Nov 2022

Activity ID Activity Name Planned Duration Start Finish Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023
Jan Feb Mar Apr May Jun Jul Aug Sep
A1350 Column Dowels 12 05-Jan-23 19-Jan-23 Column Dowels
A1360 Laying of Beam and Slab Reinforcement 13 05-Jan-23 21-Jan-23 Laying of Beam and Slab Reinforcement
A1370 Final Concrete Pouring 5 05-Jan-23 11-Jan-23 Final Concrete Pouring
A1490 Masonary Work 11 05-Jan-23 18-Jan-23 Masonary Work
A1500 Placement of Doors and Windows 5 05-Jan-23 11-Jan-23 Placement of Doors and Windows

Finishing Phase 8 05-Jan-23 14-Jan-23 14-Jan-23, Finishing Phase


A1380 Paint 5 05-Jan-23 11-Jan-23 Paint
A1390 Marble Finishing 3 05-Jan-23 09-Jan-23 Marble Finishing
A1400 Ceiling 5 05-Jan-23 11-Jan-23 Ceiling
A1410 Electrical Work 4 05-Jan-23 10-Jan-23 Electrical Work
A1420 Mechanical Work 4 05-Jan-23 10-Jan-23 Mechanical Work
A1430 Fixtures Fitting 8 05-Jan-23 14-Jan-23 Fixtures Fitting

Maintenance 15 05-Jan-23 23-Jan-23 23-Jan-23, Maintenance


A1440 Annual Maintainance 10 05-Jan-23 17-Jan-23 Annual Maintainance
A1450 3-year Maintenance 15 05-Jan-23 23-Jan-23 3-year Maintenance

Actual Level of Effort Remaining Work Page 3 of 3 Submitted to :Sir Mansoor


Actual Work Critical Remai... NBC