Activity Codes Khazran

351492
7th, Nov 2022

Activity ID Activity Name location Priority Project ResponsibilityOriginal Duration Start Finish
Stage

Khazran 149 05-Jan-23 01-Aug-23

A1510 Expenses 0 05-Jan-23 05-Jan-23


Initiation 0

Planning 135 05-Jan-23 06-Jul-23

Architechtural Drawing Prep 31 05-Jan-23 15-Feb-23


A1000 Site Plane Archetect Studio Highly Important 2 Ayesha 10 05-Jan-23 17-Jan-23

A1010 Working Plan Archetect Studio Highly Important 2 Ayesha 4 19-Jan-23* 24-Jan-23
A1020 Floor Plan Archetect Studio Important 2 Ayesha 7 25-Jan-23* 02-Feb-23

A1030 Elevation Archetect Studio Important 2 Ayesha 8 25-Jan-23* 06-Feb-23


A1040 Facad Archetect Studio Highly Important 2 Ayesha 5 25-Jan-23* 31-Jan-23
A1050 Sectional Drawings Archetect Studio Highly Important 2 Ayesha 5 25-Jan-23* 31-Jan-23
A1060 Idefining physical interphases Archetect Studio Highly Important 2 Ayesha 15 25-Jan-23* 15-Feb-23
A1070 Defining system elements Archetect Studio Highly Important 2 Ayesha 9 25-Jan-23* 07-Feb-23
A1080 documentation of drawimgs Archetect Studio Highly Important 2 Ayesha 6 25-Jan-23* 01-Feb-23
A1480 Design of Railings Archetect Studio Important 2 Ayesha 5 25-Jan-23* 31-Jan-23
Structural Drawing Prep 47 01-Feb-23 06-Apr-23
A1090 Excavation Plan Design Office Highly Important 2 Yaseen 8 01-Feb-23* 13-Feb-23
A1100 Foundaton Plan Design Office Highly Important 2 Yaseen 6 13-Feb-23* 20-Feb-23
A1110 Column Layou Plan Design Office Important 2 Yaseen 8 21-Feb-23* 04-Mar-23
A1120 Beam Detailing Design Office Important 2 Yaseen 5 27-Feb-23* 05-Mar-23
A1130 Slab Detailing Design Office Highly Important 2 Yaseen 10 06-Mar-23* 19-Mar-23
A1140 Staircase Detailing Design Office Medium 2 Yaseen 9 20-Mar-23* 02-Apr-23

Page 1 of 3 Submitted to :Sir Mansoor


NBC
Activity Codes Khazran
351492
7th, Nov 2022

Activity ID Activity Name location Priority Project ResponsibilityOriginal Duration Start Finish
Stage

A1150 Shear Wall / Lift wall detailing Design Office Medium 2 Yaseen 6 30-Mar-23* 06-Apr-23
Plumbing/HVAC Drawing Prep 65 10-Apr-23 06-Jul-23
A1160 SLD Diagram Design Office Medium 2 Ayesha 3 10-Apr-23* 13-Apr-23
A1170 Control Diagram Design Office Medium 2 Ayesha 4 12-Apr-23* 17-Apr-23
A1180 Power Diagram Design Office Medium 2 Ayesha 12 18-Apr-23* 04-May-23
A1190 Schematic Diagam Design Office Medium 2 Ayesha 13 18-Apr-23* 06-May-23
A1200 Installation Detail Design Office Medium 2 Ayesha 5 08-May-23* 14-May-23
A1210 HVAC Layout Diadram Design Office Medium 2 Ayesha 10 15-May-23* 28-May-23
A1220 Impedane Diagram Design Office Medium 2 Ayesha 9 29-May-23* 10-Jun-23
A1230 Water Supply/ System Drainage
Design Office Highly Important 2 Ayesha 7 08-Jun-23* 17-Jun-23
A1240 Drainage System Drawing Design Office Highly Important 2 Ayesha 5 19-Jun-23* 25-Jun-23
A1250 Bathroom Closets Design Office Medium 2 Ayesha 8 26-Jun-23* 06-Jul-23

Produrement Phase 9 06-Jul-23 18-Jul-23


A1260 Hiring of Technical Team America Important 3 Khazran 8 06-Jul-23* 17-Jul-23
A1270 Hiring of Contracctor Karachi Important 3 Khazran 9 06-Jul-23* 18-Jul-23
A1280 Hiring of Sub-Contractor Karachi Medium 3 Khazran 7 06-Jul-23* 15-Jul-23
A1290 Purchase of Materials Cement mills Important 3 Zubaida 5 06-Jul-23* 12-Jul-23
A1300 Macchinery Hiring Karachi Important 3 Zubaida 6 06-Jul-23* 13-Jul-23
A1460 Hiring of Consultants Karachi Medium 3 Khazran 6 06-Jul-23* 13-Jul-23
A1470 Bringing Labour Quetta Medium 3 Zubaida 4 06-Jul-23* 11-Jul-23
Execution Phase 155 05-Jan-23 01-Aug-23
A1310 Excavation Construction Site Medium 4 Muzaffar 8 12-Jul-23* 23-Jul-23
A1320 Lean Concrete Construction Site Important 4 Muzaffar 7 24-Jul-23* 01-Aug-23
A1330 Foundation Reinforcement Placement
Construction Site Medium 4 Muzaffar 10 05-Jan-23 17-Jan-23

Page 2 of 3 Submitted to :Sir Mansoor


NBC
Activity Codes Khazran
351492
7th, Nov 2022

Activity ID Activity Name location Priority Project ResponsibilityOriginal Duration Start Finish
Stage

A1340 Concrete Pouring Construction Site Medium 4 Muzaffar 11 05-Jan-23 18-Jan-23


A1350 Column Dowels Construction Site Important 4 Muzaffar 12 05-Jan-23 19-Jan-23
A1360 Laying of Beam and Slab Reinforcement
Construction Site Medium 4 Muzaffar 13 05-Jan-23 21-Jan-23
A1370 Final Concrete Pouring Construction Site Important 4 Muzaffar 5 05-Jan-23 11-Jan-23
A1490 Masonary Work Construction Site Medium 4 Muzaffar 11 05-Jan-23 18-Jan-23
A1500 Placement of Doors and Windows
Construction Site Important 4 Muzaffar 5 05-Jan-23 11-Jan-23
Finishing Phase 8 05-Jan-23 14-Jan-23
A1380 Paint Construction Site Low 5 Kashif 5 05-Jan-23 11-Jan-23
A1390 Marble Finishing Construction Site Low 5 Salman 3 05-Jan-23 09-Jan-23
A1400 Ceiling Construction Site Medium 5 Ali 5 05-Jan-23 11-Jan-23
A1410 Electrical Work Construction Site Low 5 Waseem 4 05-Jan-23 10-Jan-23
A1420 Mechanical Work Construction Site Low 5 Saba 4 05-Jan-23 10-Jan-23
A1430 Fixtures Fitting Construction Site Low 5 Saba 8 05-Jan-23 14-Jan-23
Maintenance 15 05-Jan-23 23-Jan-23
A1440 Annual Maintainance Construction Site Medium 6 Khazran 10 05-Jan-23 17-Jan-23
A1450 3-year Maintenance Construction Site Medium 6 Khazran 15 05-Jan-23 23-Jan-23