K and F CONSTRUCTION DEV'T CORP.

C145 Poblacion Centro, San Pascual, Batangas


Tel.# (043) 7063874 - (043) 7234394 - (043) 7063827
Email: ecp_kfe@yahoo.com

Date : 23-Mar-23
KFC-Q-2023-103

Project Title T303A, B & C CATWALK REHABILITATION


Company Name SAKAMOTO ORIENT CHEMICALS CORPORATION
Project Proponent / In Charge MR. JOHN MARK A. ABANTE

QUOTATION

ITEM DESCRIPTION QTY UNIT UNIT COST AMOUNT


A. T303A, B & C CATWALK REHABILITATION
Delivery Charge 1 lot ₱ 4,500.00 ₱ 4,500.00
Removal of Insulation
Angle Bar 3"x3"x5mm 10 pcs ₱ 3,400.00 ₱ 34,000.00
Flat Bar 2"x5mm 1 pcs ₱ 1,170.00 ₱ 1,170.00
G.I. Pipe 3/4" 2 pcs ₱ 1,690.00 ₱ 3,380.00
Rolling of Angle Bar 150 kg ₱ 45.00 ₱ 6,750.00
Labor Cost, Consumables and Use of Tools 1 lot ₱ 52,500.00 ₱ 52,500.00
Repainting (SOCC SUPPLY OF PAINTS)
Labor Cost, Consumables and Use of Tools 1 lot ₱ 18,000.00 ₱ 18,000.00
Scaffolding Works
Labor Cost, Consumables and Use of Tools 1 lot ₱ 6,000.00 ₱ 6,000.00
Sub-Total ₱ 126,300.00
Discount ₱ 1,000.00
Grand-Total ₱ 125,300.00
TIME PLAN: 10 WORKING DAY/S (VAT EX)
MAN POWER: 3-4 HEADS

TERMS OF PAYMENT : 30% Downpayment, 60% and 90% Progress Billing 10% Retention

Thank you for giving us the opportunity to quote on you and we are looking forward to your kind and
favorable decision on this matter.

Prepared by:

Edwin R. Pagcaliwangan
Project Manager
Tel.: 043 - 7068816
CP.: 0949 - 2003518