Professional Documents
Culture Documents
Chapter 12 Solutions
Chapter 12 Solutions
CHAPTER 12:
MRP AND ERP
344
Operations Management, 11/e
8. Successful MRP requires accurate inputs (master schedules, bills of materials, and
inventory records). It also requires a computer to process information and generate material
requirements plans.
11. MRP II is a second-generation approach to planning that incorporates MRP. It has a
broader scope to manufacturing resource planning in that it links business planning, production
planning, and the master schedule. [See Figure 15–16.]
12. The term lot sizing refers to selecting a lot size to order. In the case of uniform demand,
an EOQ approach will yield an appropriate lot size. Under lumpy demand, it usually makes sense
to time orders so that they arrive as needed. The EOQ amount, though, may not equal the quantity
needed at a particular point in time. Lot-for-lot ordering is often used instead. However, some
other lot size may yield lower total costs. Because of the variations in timing and quantity
generally inherent in lumpy demand cases, there may not be a single approach which will
consistently yield a reasonably good answer.
13. Planned order receipts refers to a plan for future ordering; scheduled receipts indicates an
actual order has been made and when it is expected to arrive.
14. In the 1970s, manufacturers began to recognize the importance of the difference between
independent demand which is relatively stable and dependent demand which is rather “lumpy” by
nature. Earlier EOQ models which worked well for independent demand items did not work very
well for the more “lumpy” dependent demand items. Hence, MRP was developed to handle the
more “lumpy” dependent demand items. Adjustments still have to be made under MRP, but it was
developed to handle seasonal variations better than the older EOQ models.
15. MRP II (Manufacturing Resource Planning) involves an effort to expand the scope of
production resource planning to include other functional areas of the firm in the planning process
such as marketing, finance, and purchasing. The integration of these areas in the formulation of
the resource plan allows the company to develop a plan that works and is acceptable to different
areas of the company. On the other hand, ERP is an expanded effort to integrate standardized
record keeping that will permit information sharing among different departments in order to make
better decisions more rapidly and to manage the system more effectively. While MRP II builds
links between the overall business plan, aggregate plan and the master production schedule, ERP
attempts to link and synchronize various independent databases within the firm and integrate
them into one system.
16. The unforeseen costs of MRP include the following:
a. Training: The workers have to be trained to learn and become proficient with a new system
and its processes.
b. Integration and testing: Integrating the computer systems associated with different areas of
the firm and testing the links between various corporate areas and systems.
c. Data conversion and data analysis
d. Consultant fees
e. Solving implementation problems on an ongoing basis
f. Dealing with disappointing short-term results
g. Competition for high quality workers especially in the IT field.
Taking Stock
1. The cost of implementation: This includes the actual cost of the software, training and
implementation costs, cost of getting every department to cooperate, cost of integration and
testing, cost of data conversion, cost of data analysis, and cost of employee salaries.
The potential benefits of implementing ERP:
a. faster access to data
b. ability to collect and analyze data
c. ability to respond to customer’s questions and needs in a faster, timely fashion
d. integration of company’s databases
e. integration of financial data
f. standardization of manufacturing processes
g. standardization of human resources information
h. automation of the tasks involved in performing various business processes (taking an order
from a customer)
i. Everyone in the company has access to the same database, thus are able to see the same
computer screen providing wealth of real-time information.
2. The executives of the organization with input from different functional departments (marketing,
operations, finance) must be involved in designing and implementing an ERP system. The
representatives of the functional departments (usually fairly high level) with the supervision and
consultation of top management should be involved in the design, development and
implementation of the MRP II plan.
A truly integrative ERP will involve the entire organization, therefore everyone in the
organization will need to be trained. However, the level and the intensity of training will depend
on the job.
3. The technology of ERP software allowed many companies to integrate their databases, which in turn
allowed easier tracking of orders, faster response to customers’ inquiries, integration of financial
data and standardization of the manufacturing processes.
The easier to use the system, the less the training costs, the fewer mistakes, the faster response to
customers’ needs. The complete integration of the system will enable the company to access different
databases simultaneously, resulting in the utilization of more complete set of information to make
decisions.
The ERP system may be unreliable in a couple of different ways. First, if the computer system keeps on
crashing or going down, it becomes difficult to complete certain tasks in an efficient manner. The second
type of unreliability deals with the actual data and information stored in the system not being accurate or
reliable. The lack of reliability of the second type will not only lead to many customer service problems,
but will also result in employees using the system losing faith. These employees will utilize other sources
of information to make decisions because the formal ERP system has let them down too many times.
Beg.
Master Week 1 2 3 4 5 6 7 8
Inv.
Schedule for:
Quantity
Week
Beg.
1 2 3 4 5 6 7 8
Inv.
Gross requirements
Scheduled receipts
On hand
Net requirements
Planned order receipts
Planned order releases
Week
Beg.
1 2 3 4 5 6 7 8
Inv.
Gross requirements
Scheduled receipts
On hand
Net requirements
Planned order receipts
Planned order releases
Week
Beg.
1 2 3 4 5 6 7 8
Inv.
Gross requirements
Scheduled receipts
On hand
Net requirements
Planned order receipts
Planned order releases
Week
Beg.
1 2 3 4 5 6 7 8
Inv.
Gross requirements
Scheduled receipts
On hand
Net requirements
Planned order receipts
Planned order releases
Solutions
1. a. F: 2 G: 1 H: 1
J: 2 x 2 = 4 L: 1 x 2 = 2 A: 1 x 4 = 4
D: 2 x 4 = 8 J: 1 x 2 = 2 D: 1 x 2 = 2
Totals: F = 2; G = 1; H = 1; J = 6; D = 10; L = 2; A = 4
1. b.
Stapler
Slide Spring
2. a. B: 20 x 2 = 40 – 10 = 30 C: 20 x 1 = 20 – 10 = 10 D: 20 x 3 = 60 – 25 = 35
E: 30 x 2 = 60 – 12 = 48 E: 10 x 2 = 20 E: 35 x 2 = 70
Total: 48 + 20 + 70 = 138
b. End Item
B(2) C D(3)
Total LT 4 5 5 5 6 5
The longest sequence is 6 weeks. Week 11 – 6 weeks = Week 5.
3. End Item
L(2) C K(3)
b.
Total LT: 5 6 7 6 6 6
Solutions (continued)
The longest lead time is 7 weeks. Thus, 8 – 7 = 1, the beginning of week 1.
a. L: 2 x 40 = 80 C: 1 x 40 = 40 K: 3 x 40 = 120
–10 –15 –20
70 25 100
B: 2 x 70 = 140 B: 2 x 25 = 50 B: 2 x 100 = 200
–30
110 Total: 110 + 50 + 200 = 360
9. Saw
A(2) B C(3)
D
A
E
F
B
Saw
D
D
C
E
1 2 3 4 5 6 7 8
week
Solutions (continued)
9. (continued)
Master Beg.
Week 1 2 3 4 5 6 7 8
Schedule for Inv.
Saws Quantity 50
Week
Beg.
Item: Saw LT = 2 wks. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 50
Scheduled receipts
Projected on hand 15
Net requirements 35
Planned order receipt 35
Planned order release 35
Week
Beg.
Item: A(2) LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 70
Scheduled receipts
Projected on hand 10
Net requirements 60
Planned order receipt 60
Planned order release 60
Beg.
Item: C(3) LT = 2 wks. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 105
Scheduled receipts
Projected on hand 30
Net requirements 75
Planned order receipt 75
Planned order release 75
Beg.
Item: E(3) & E(2) LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 150 180
Scheduled receipts
Projected on hand 10
Net requirements 140 180
Planned order receipt 140 180
Planned order release 140 180
Solutions (continued)
9. c.
Beg.
E LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 150 180
Scheduled receipts
Projected on hand 10 10 30 130 80
Net requirements 140 180
Planned order receipt 20 100 100 100
Planned order release 20 100 100 100
10. Robot
B C(3)
E F G G(2) H
Master Beg.
Week 1 2 3 4 5 6 7 8
Schedule for Inv.
Robot Quantity 40
Beg.
Item: Robot LT = 2 wks. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 40
Scheduled Receipts
Projected on hand 10 10 10 10 10 10 10
Net Requirements 30
Planned order receipts 30
Planned order releases 30
Solutions (continued)
10. (continued)
Beg.
Item: C(3) LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 90
Scheduled receipts
Projected on hand 20 20 20 20 20
Net Requirements 70
Planned order receipts 70
Planned order releases 70
Beg.
Item: G(2C + 1 Robot) LT = 2 wks. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 140 30
Scheduled receipts
Projected on hand 15 15 15 15 35 5 5 5 5
Net requirements 125
Planned order receipts 160
Planned order releases 160
12. a.
Golf
Cart
Top Base
Supports
Top
b.
Cover
Cart
Motor
Frame
Controls Body Base
Wheels
Seats
2 3 4 5 6 7
week
Solutions (continued)
12. c.
Master Beg.
Week 1 2 3 4 5 6 7 8
Schedule for Inv.
golf carts Quantity 200
Beg.
Item: Gold Cart LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 200
Scheduled receipts
Projected on hand
Net requirements 200
Planned order receipts 200
Planned order releases 200
Beg.
Item: Top LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 200
Scheduled receipts
Projected on hand 40 40 40 40 40 40 40
Net requirements 160
Planned order receipts 160
Planned order releases 160
Solutions (continued)
12. c. (continued)
Beg.
Item: Cover LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 160
Scheduled receipts
Projected on hand
Net requirements 160
Planned order receipts 160
Planned order releases 160
Beg.
Item: Base LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 200
Scheduled receipts
Projected on hand 20 20 20 20 20 20
Net requirements 180
Planned order receipts 180
Planned order releases 180
Beg.
Item: Motor LT = 2 wks. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 180
Scheduled receipts
Projected on hand 300 300 300 300 300 120 120 120
Net requirements (120)
Planned order receipts
Planned order releases
Solutions (continued)
12. c. (Continued)
Beg.
Item: Body LT = 3 wks. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 180
Scheduled receipts
Projected on hand 50 50 50 50 50 50
Net requirements 130
Planned order receipts 130
Planned order releases 130
Beg.
Item: Seats LT = 2 wks. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 360
Scheduled receipts
Projected on hand 120 120 120 120 120 120
Net requirements 240
Planned order receipts 240
Planned order releases 240
Beg.
Item: Frame LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 130
Scheduled receipts
Projected on hand 35 35 35
Net requirements 95
Planned order receipts 95
Planned order releases 95
Solutions (continued)
12. c. (Continued)
Beg.
Item: Controls LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 130
Scheduled receipts
Projected on hand
Net requirements 130
Planned order receipts 130
Planned order releases 130
Beg.
Item: Wheel Assemblies LT = 1 wk. 1 2 3 4 5 6 7 8
Inv.
Gross requirements 520
Scheduled receipts
Projected on hand 240 240 240
Net requirements 280
Planned order receipts 280
Planned order releases 280
13. a.
Master Beg.
Week 1 2 3 4 5 6 7 8 9
Schedule for Inv.
golf carts Quantity 100 100 100
b.
Beg.
Item: Golf cart LT = 1 wk. 1 2 3 4 5 6 7 8 9
Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand
Net requirements 100 100 100
Planned order receipts 100 100 100
Planned order releases 100 100 100
Solutions (continued)
13. b. (continued)
Beg.
Week 1 2 3 4 5 6 7 8 9
Inv.
Quantity 100 100 100
Beg.
Item: Tops LT = 1 wk. 1 2 3 4 5 6 7 8 9
Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand 40 40 40 40 40
Net requirements 60 100 100
Planned order receipts 60 100 100
Planned order releases 60 100 100
Beg.
Item: Base LT = 1 wk. Inv. 1 2 3 4 5 6 7 8 9
Beg.
Item: Golf Cart LT = 1 wk. 1 2 3 4 5 6 7 8 9
Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand
Net requirements 100 100 100
Planned order receipts 100 100 100
Planned order releases 100 100
Solutions (continued)
13. c. (continued)
Beg.
Week 1 2 3 4 5 6 7 8 9
Inv.
Quantity 100 100 100
Beg.
Item: Bases LT = 1 wk. 1 2 3 4 5 6 7 8 9
Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand 20 20 20 50 100 50 100 50
Net requirements 0 100 50
Planned order receipts 30 50 50 50 50 50
Planned order releases 30 50 50 50 50 50