04 - Steel, Reinforcement & BRC
04 - Steel, Reinforcement & BRC
ELEMENT/TRADE/WORK CATEGORY
ITEM OUTPUT
A Material
4.48
B Plant
Included in Preliminaries
C Labour
D Overhead
5% @ RM RM 0.36
E Profit
10% @ RM RM 0.73
RM 8.39 / m2
ITEM OUTPUT
A Material
2.15
B Plant
Included in Preliminaries
C Labour
D Overhead
5% @ RM RM 0.25
E Profit
10% @ RM RM 0.50
RM 5.71 / m2
ITEM OUTPUT
A Material
1.43
B Plant
Included in Preliminaries
C Labour
D Overhead
5% @ RM RM 0.21
E Profit
10% @ RM RM 0.42
RM 4.88 / m2
ITEM OUTPUT
A Material
1.43
B Plant
Included in Preliminaries
C Labour
D Overhead
5% @ RM RM 0.21
E Profit
10% @ RM RM 0.42
RM 4.88 / m2
ITEM OUTPUT
A Material
Supply Reinforcement - All size RM 2.90 /kg
: RM2900/tonne 5.00 litre
RM 193.60
RM 38.72 /litre
*1 litre = 5 m2
RM 2.90 /kg RM 2.90 /kg
3.05 /kg
B Plant
Included in Preliminaries
C Labour
D Overhead
5% @ RM RM 0.17
E Profit
15% @ RM RM 0.52
RM 4.15 /kg
ITEM OUTPUT
A Material
Supply BRC A6 RM 7.34 /m2
: Size 2.2m x 6.0m 5.00 litre
: RM97.00 RM 193.60
RM 38.72 /litre
*1 litre = 5 m2
RM 7.34 /m2 RM 7.34 /m2
7.71 /m2
B Plant
Included in Preliminaries
C Labour
D Overhead
5% @ RM RM 0.70
E Profit
15% @ RM RM 2.09
RM 16.75 /m2