Concrete Pour Card

Project Irasa Date:


Client Irasa Group
Contractor

Location

Structural Member RCC Consultant

W/C ratio Ref. Drawing no:

Slump Grade of Concrete

Concrete Start time Concrete Finish time

Threotical Quantity Actual Quantity

Threotical Cement Actual cement

checking list:
Sr. no. List Yes No Remarks
1 All reinforcement is as per drawing
2 Lap length provided
3 All dia. of bar are as per structural drawing
4 Binding wire/guage
5 Sleeves/pocket/opening provided
6 Chair/ spacerbar provided (if any)
7 Cover block provided
8 Formwork checked
9 All line levels are as per architectural drawing
10 All measurements are ok
11 All supports are ok
12 Concrete is as per mix design.
13 concrete cube to be cast (6 Nos)
14 Slump to be check
15 Cleaning in slab has done